Home / Browse projects / Surat, Gujarat / Harrod's The Empire (Building B Phase 1)

Valid until 28 Oct 2026 Commercial project

Harrod's The Empire (Building B Phase 1)

By HARROD S ENTERPRISE LLP

RG-GJ-92155 · RERA PR/GJ/SURAT/CHORASI/SUDA/CAA03184/A1C/EX2/310125/280625 · Last updated on GujRERA portal: 2 Dec 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 40 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Oct 2026Possession promisedmoved 40 months from the original
3 of 9Construction stages donefurthest along: Staircases, 90%
59 of 258Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

Harrod's The Empire (Building B Phase 1) is a Commercial project by HARROD S ENTERPRISE LLP in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORASI/SUDA/CAA03184/A1C/EX2/310125/280625 on 19 Jul 2018. Possession is promised by 28 Oct 2026. The completion date has moved by 40 months from the original filing. 199 of the 258 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameHarrod's The Empire (Building B Phase 1)
  • TypeCommercial
  • Location
    • T.P. No 28 (Rundh-Vesu)
    • F.P. No-35
    • O.P. No35
    • At- Rundh-Vesu Surat
    • Rundh Vesu
    • Chorasi
    • Surat
    • 395007
  • Pincode395007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORASI/SUDA/CAA03184/A1C/EX2/310125/280625
  • ReraGenie IDRG-GJ-92155

Builder

  • NameHARROD S ENTERPRISE LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2018First promiseJun 2023Revised toOct 2026

Key facts

Registration and timeline

  • StatusValid until 28 Oct 2026
  • Registered on19 Jul 2018
  • Promised completion28 Oct 2026
  • Revised completionRevised to 28 Oct 2026 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed38 files

Current status

77%199 of 258 units booked
88.2%Of the estimated cost spent so far

Figures as on 2 Dec 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING B---0258258

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 2 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

BUILDING B: 75% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing65%

Progress on shared amenities19

As on 2 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes30%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes30%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,378 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 79.36 cr
Cost incurredRs 70.00 cr
Spent of the estimate88.21%
BuildingWingEstimatedIncurred
BUILDING BNARs 79.36 crRs 70.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBlack Ink (Sanjay Joshi)
EngineerDarshit B Vejani

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/CHORASI/SUDA/CAA03184/A1C/EX1/260924/290624Applied May 2024; approved Sep 2024
PR/GJ/SURAT/CHORASI/SUDA/CAA03184/A1C/EX2/310125/280625Applied Oct 2024; approved Jan 2025
ExtensionApplied Nov 2025; no approval date filed

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORASI/SUDA/CAA03184/A1C/EX2/310125/280625 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)2 Dec 2024
Architect's certificate (Form 1)25 Oct 2024
Engineer's certificate (Form 2)25 Oct 2024
Engineer's certificate annexure25 Oct 2024
Site photograph, BUILDING B24 Oct 2024
RERA registration certificate19 Jul 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

77%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 40 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep Harrod's The Empire (Building B Phase 1) on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rundh Vesu2,600+ in Surat

2 kmHarrod's The Empire (BuiOther 162Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: HARROD S ENTERPRISE LLP

HARROD S ENTERPRISE LLP has 1 registration on GujRERA, including Harrod's The Empire (Building B Phase 1). Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if Harrod's The Empire (Building B Phase 1) is delayed beyond 28 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Harrod's The Empire (Building B Phase 1)?

The registered promoter entity is HARROD S ENTERPRISE LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Harrod's The Empire (Building B Phase 1)?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Harrod's The Empire (Building B Phase 1)?

The professionals named in the filing: Architect: Black Ink (Sanjay Joshi); Engineer: Darshit B Vejani. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Harrod's The Empire (Building B Phase 1)?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Harrod's The Empire (Building B Phase 1). Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Harrod's The Empire (Building B Phase 1) to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.