ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / HAJIRA BUSINESS HUB

Valid until 31 Jul 2027 Commercial project

HAJIRA BUSINESS HUB

By DHOLIA RAMESHBHAI GOVINDBHAI

RG-GJ-32140 · RERA PR/GJ/SURAT/CHORYASI/Surat Urban Development Authority/CAA14268/171024/310327 · Last updated on GujRERA portal: 2 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2027Possession promisedno revision filed
5 of 9Construction stages donefurthest along: Sanitary fittings within the flats, 80%
44 of 79Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

HAJIRA BUSINESS HUB is a Commercial project by DHOLIA RAMESHBHAI GOVINDBHAI in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORYASI/Surat Urban Development Authority/CAA14268/171024/310327 on 17 Oct 2024. Possession is promised by 31 Jul 2027. 35 of the 79 units on this registration are recorded sold or booked, and 5 of 9 construction stages are filed complete.

At a glance

Project

  • NameHAJIRA BUSINESS HUB
  • TypeCommercial
  • Location
    • R. S. NO. : 120/1
    • 120/2 & 250/C
    • SUB PLOT NO. : 1
    • MOJE : MORA
    • TAL. : CHORYASI
    • DIST. : SURAT-394517.
    • MORA
    • Choryasi
    • Surat
    • 394517
  • Pincode394517
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORYASI/Surat Urban Development Authority/CAA14268/171024/310327
  • ReraGenie IDRG-GJ-32140

Builder

  • NameDHOLIA RAMESHBHAI GOVINDBHAI
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredOct 2024PromisedJul 2027

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2027
  • Registered on17 Oct 2024
  • Promised completion31 Jul 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Current status

44%35 of 79 units booked
92.4%Of the estimated cost spent so far

Figures as on 2 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---07579

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 2 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 9 construction stages are filed complete. The stage furthest along is Sanitary fittings within the flats, at 80%.

A: 74% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing40%

Progress on shared amenities19

As on 2 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes10%
Sewerage (chamber, lines, septic tank, STP)Yes20%
Storm water drainsYes15%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes10%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,191 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 5.10 cr
Cost incurredRs 4.71 cr
Spent of the estimate92.44%
BuildingWingEstimatedIncurred
ANARs 5.10 crRs 4.71 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSwati Butani Swati
EngineerVIRAMBHAI RAMESHBHAI DHOLIYA

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORYASI/Surat Urban Development Authority/CAA14268/171024/310327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)2 Jul 2026
Engineer's certificate (Form 2)25 May 2026
Engineer's certificate annexure25 May 2026
Architect's certificate (Form 1)12 May 2026
Site photograph, A12 May 2026
RERA registration certificate17 Oct 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

44%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep HAJIRA BUSINESS HUB on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MORA2,600+ in Surat

2 kmHAJIRA BUSINESS HUBOther 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: DHOLIA RAMESHBHAI GOVINDBHAI

DHOLIA RAMESHBHAI GOVINDBHAI has 1 registration on GujRERA, including HAJIRA BUSINESS HUB. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if HAJIRA BUSINESS HUB is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of HAJIRA BUSINESS HUB?

The registered promoter entity is DHOLIA RAMESHBHAI GOVINDBHAI, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in HAJIRA BUSINESS HUB?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HAJIRA BUSINESS HUB?

The professionals named in the filing: Architect: Swati Butani Swati; Engineer: VIRAMBHAI RAMESHBHAI DHOLIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HAJIRA BUSINESS HUB?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HAJIRA BUSINESS HUB. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HAJIRA BUSINESS HUB to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.