Home / Browse projects / Belagavi, Karnataka / GROW MORE
GROW MORE
RG-KA-77269 · RERA PRM/KA/RERA/1249/447/PR/080323/005774 · Last updated on RERA Karnataka portal: 17 Feb 2023
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
GROW MORE is a Mixed Development project by CHANDWALE CONSTRUCTION in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/080323/005774 on 8 Mar 2023. Possession is promised by 31 Dec 2026.
At a glance
Project
- NameGROW MORE
- TypeMixed Development
- Location
- Belagavi
- 590016
- Pincode590016
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1249/447/PR/080323/005774
- ReraGenie IDRG-KA-77269
Builder
- NameCHANDWALE CONSTRUCTION
- Entity typeProprietorship Firm
- GSTIN29BIFPC3318H1ZH
- Authorized SignatoryMOHAMMED ZAIF M CHANDWALE
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on8 Mar 2023
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed111 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GROW MORE | - | - | - | - | - | 18 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 17 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 17 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
| Common storage spaces | No | Not applicable |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| NADEEM MOHAMMAD KASIM INAMDAR | - | - |
| NAJEEB MOHAMMADUASIN INAMDAR | - | - |
| MATEEN MOHAMMAD YASIN INAMDAR | - | - |
| MATEEN MOHAMMAD YASIN INAMDAR | - | - |
| NAJEEB MOHAMMAD UASIN INAMDAR | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 2.52 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mohammed Zaif M Chandwale |
| Engineer | Adif Javed Contractor |
| Chartered Accountant | BHAKTI ADITYA BHIDE |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed111
As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/080323/005774 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Profit and Loss for the year 2021-22 with CA UDINFile: P and L 21-22 with CA UDIN.pdf | 17 Feb 2023 |
| PROFIT AND LOSS FOR 2020-21 WITH CA UDINFile: P and L 20-21 with CA UDIN.pdf | 17 Feb 2023 |
| PROFIT AND LOSS FOR 2019-20 WITH CA UDINFile: P and L 19-20 with CA UDIN.pdf | 17 Feb 2023 |
| BALANCE SHEET FOR 2021-22 WITH CA UDINFile: BALANCE SHEET 2021-22 WITH CA UDIN.pdf | 17 Feb 2023 |
| BALANCE SHEET FOR 2020-21 WITH CA UDINFile: balance sheet 20-21 with CA UDIN.pdf | 17 Feb 2023 |
| BALANCE SHEET FOR 2019-20 WITH CA UDINFile: balance sheet 19-20 with CA UDIN.pdf | 17 Feb 2023 |
| FINANCIAL STATEMENT 2021-22File: financial statements 21-22.pdf | 17 Feb 2023 |
| FINANCIAL STATEMENT 2020-21File: financial statement 20_21.pdf | 17 Feb 2023 |
| FINANCIAL STATEMENT 2019-20File: financial statement 19-20.pdf | 17 Feb 2023 |
| BALANCE SHEET WITH CA UDIN 2021-22File: Balance sheet with CA UDIN 2021-22.pdf | 28 Jan 2023 |
| P & L WITH CA UDIN 2021-22File: P & L with CA UDIN 2021-22.pdf | 28 Jan 2023 |
| FINANCIAL STATEMENT WITH PROMOTER SIGNATURE AND UDIN FOR 2019-20File: A 2019-2020 it return.pdf | 28 Jan 2023 |
| FINANCIAL STATEMENT WITH PROMOTER SIGNATURE AND UDIN FOR 2020-21File: A 2020-2021 it return.pdf | 28 Jan 2023 |
| FINANCIAL STATEMENT WITH PROMOTER SIGNATURE AND CA UDIN FOR 2019-20File: Financial statement 2019-20.pdf | 28 Jan 2023 |
| FINANCIAL STATEMENT WITH PROMOTER SIGNATURE AND CA UDIN FOR 2020-21File: Financial statement 2020-21.pdf | 28 Jan 2023 |
| REGISTERED GIFT DEEDFile: Gift deeds.pdf | 28 Jan 2023 |
| PROFORMA OF ALLOTMENT LETTER WITH ANNEXURE AFile: DRAFT OF ALLOTMENT LETTER WITH ANNEXURE A.pdf | 28 Jan 2023 |
| Firm Registration certificateFile: Print Udyam Registration Certificate.pdf | 3 Jan 2023 |
| GST registration certificate of firm registrationFile: GST registration chandwale construction firm.pdf | 3 Jan 2023 |
| Balance sheet 2019-20 with CA UDINFile: Balance Sheet 2019-20 with CA UDIN.pdf | 3 Jan 2023 |
| Balance sheet 2020-21 with CA UDINFile: Balance Sheet 2020-21 with CA UDIN.pdf | 3 Jan 2023 |
| Balance sheet 2021-22 with CA UDINFile: Balance sheet 2021-22 with CA UDIN.pdf | 3 Jan 2023 |
| P & L 2019-20 with CA UDINFile: P & L 2019-20 with CA UDIN.pdf | 3 Jan 2023 |
| P & L 2020-21 with CA UDINFile: P & L 2020-21 with CA UDIN.pdf | 3 Jan 2023 |
| P & L 2021-22 with CA UDINFile: P & L 2021-22 with CA UDIN.pdf | 3 Jan 2023 |
| Form 1 of CAFile: FORM 1 OF CA.pdf | 3 Jan 2023 |
| title document Mohamed Yasim of CTS No. 7737/2/AFile: Oral Gift Deed of CTS 7737-2-A.pdf | 3 Jan 2023 |
| title document Mohamed Yasim of CTS No. 7737/2/BFile: Oral Gift Deed of CTS 7737-2-B.pdf | 3 Jan 2023 |
| draft of Allotment letter as prescribed formatFile: RERA allotment letter.pdf | 3 Jan 2023 |
| AOS with project name in point 14 and with specificationFile: Draft of Agreement of sale (1).pdf | 3 Jan 2023 |
| Firm Registration certificateFile: GST registration chandwale construction firm.pdf | 13 Dec 2022 |
| Balance sheet, P and L with CA UDIN and IT ack 2019-20File: it return 2019-2020 udin.pdf | 13 Dec 2022 |
| Balance sheet, P and L with CA UDIN and IT ack 2020-21File: it return 2020-2021 udin.pdf | 13 Dec 2022 |
| Balance sheet, P and L with CA UDIN and IT ack 2021-22File: it return 2021-2022 udin.pdf | 13 Dec 2022 |
| about title deed of Mohammed Yasim in respect of both CTSFile: about title deed.pdf | 13 Dec 2022 |
| Rule Card of CTS No. 7737/2/AFile: Rule Card A.pdf | 13 Dec 2022 |
| Rule Card of CTS No. 7737/2/BFile: Rule card B.pdf | 13 Dec 2022 |
| Local authority khata of both CTSFile: mahantesh nagar form no 2 (1).pdf | 13 Dec 2022 |
| GPA in favour of Prop. firmFile: new gp.pdf | 13 Dec 2022 |
| Land valuation certificate issued by SRO, BelagaviFile: Land valuation certificate.jpeg | 13 Dec 2022 |
| clarification about height of the building as per NHAI NOCFile: clarification about height as per NH NOC.pdf | 13 Dec 2022 |
| certified carpet area calculationFile: area statement in mts.pdf | 13 Dec 2022 |
| CDP mapFile: CDP.jpg | 13 Dec 2022 |
| CTS mapFile: CTS map.jpeg | 13 Dec 2022 |
| about commencement certificateFile: about commencement certificate.pdf | 13 Dec 2022 |
| about FARFile: about FAR.pdf | 13 Dec 2022 |
| about car parking allotmentFile: ABOUT CAR PARKING ALLOTMENT.pdf | 13 Dec 2022 |
| brief estimation of the project construction by EngineerFile: Breif estimation by Engineer.pdf | 13 Dec 2022 |
| Proforma of Agreement of saleFile: Draft of Agreement of sale (1).pdf | 13 Dec 2022 |
| Proforma of Allotment letterFile: allotment letter grow more.pdf | 13 Dec 2022 |
| Section 3 (1) AffidavitFile: sec 3 affidavit.pdf | 13 Dec 2022 |
| HESCOM NOC and about fees receipt of HESCOM NOCFile: heacom noc mahantesh nagar.pdf | 13 Dec 2022 |
| about fees receipt of water NOCFile: water noc mahantesh nagar.pdf | 13 Dec 2022 |
| Project specification with project name and addressFile: project specifications grow more.pdf | 13 Dec 2022 |
| Registration CertificateFile: GST registration chandwale construction firm.pdf | - |
| Certificate issued by CA Form 1File: FORM 1 OF CA_compressed.pdf | - |
| Certificate issued by Architect Form 2 | - |
| Certificate issued by Engineer Form 3File: Form 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: no litigation affidavit grow more.pdf | - |
| Certificate from Chartered AccountFile: FORM 1 OF CA_compressed.pdf | - |
| Balance Sheet 2021 - 2022File: Balance sheet 2020-21.pdf | - |
| Balance Sheet 2020 - 2021File: Balance sheet 2019-20.pdf | - |
| Balance Sheet 2019 - 2020File: Balance sheet 2018-19.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: P and L 2020-21.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: P and L 2019-20.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: P and L 2018-19.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: IT 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: IT 2020-21.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: IT 2019-20.pdf | - |
| Approved Copy | - |
| HESCOM NOC GROW MORE | - |
| water NOC Grow more | - |
| Approved plan grow more 1 | - |
| Approved plan grow more 1 | - |
| Approved plan grow more 1 | - |
| Approved plan grow more 1 | - |
| Approved plan grow more 1 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep GROW MORE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Filed coordinates, straight-line distance. 32 registered projects within 2 km.
Sunlight
Sunlight Builders and Developers
HONEYWELL ENCLAVE
SHUBHA SHANKAR DEVELOPERS
ELLITE RESIDENCY I
M/s. UNIQUE CONSTRUCTIONS
GARDENIA
SAUDAGAR URBAN LIFESTYLES
EVERGREEN RESIDENCY
M/s. UNIQUE CONSTRUCTIONS
CITY HEIGHTS
MNC INFRASTRUCTURE
See every Belagavi project, with the district possession charts
Builder: CHANDWALE CONSTRUCTION
CHANDWALE CONSTRUCTION has 1 registration on RERA Karnataka, including GROW MORE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if GROW MORE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of GROW MORE?
The registered promoter entity is CHANDWALE CONSTRUCTION, a proprietorship firm as per the filing. Its GSTIN 29BIFPC3318H1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in GROW MORE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at GROW MORE?
The professionals named in the filing: Architect: Mohammed Zaif M Chandwale; Engineer: Adif Javed Contractor; Chartered Accountant: BHAKTI ADITYA BHIDE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GROW MORE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback