Valid until 30 Dec 2026 Plotted Development project

GREENERA GARDENVILLA

By GREENERA INFRAWELL PRIVATE LIMITED

RG-GJ-53364 · RERA PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225 · Last updated on GujRERA portal: 16 Jun 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 36 months from the original
0 of 9Construction stages donefurthest along: Excavation, 0%
8 of 29Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

GREENERA GARDENVILLA is a Plotted Development project by GREENERA INFRAWELL PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225 on 5 Sep 2020. Possession is promised by 30 Dec 2026. The completion date has moved by 36 months from the original filing. 21 of the 29 units on this registration are recorded sold or booked, and 0 of 9 construction stages are filed complete.

At a glance

Project

  • NameGREENERA GARDENVILLA
  • TypePlotted Development
  • Location
    • F. P. NO.- 87
    • T.P. -2A
    • SR. NO.- 159+160(NEW)
    • BHIMTALAV
    • DHOLERA
    • Bhimtalav
    • Dhandhuka
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225
  • ReraGenie IDRG-GJ-53364

Builder

  • NameGREENERA INFRAWELL PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations3 more →

Key dates

this monthRegisteredSep 2020First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 30 Dec 2026
  • Registered on5 Sep 2020
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed41 files

Current status

72%21 of 29 units booked

Figures as on 16 Jun 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---0029

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 16 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 9 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

1: 0% average across the applicable activities

ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 16 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,475 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/030424/311224Applied Oct 2023; approved Apr 2024
PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225Applied May 2025; approved Aug 2025

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)16 Jun 2025
Architect's certificate (Form 1)4 Jun 2025
Engineer's certificate (Form 2)4 Jun 2025
Engineer's certificate annexure4 Jun 2025
Site photograph, 13 Jun 2025
RERA registration certificate5 Sep 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

72%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 36 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep GREENERA GARDENVILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhimtalav5,400+ in Ahmedabad

Builder: GREENERA INFRAWELL PRIVATE LIMITED

GREENERA INFRAWELL PRIVATE LIMITED has 4 registrations on GujRERA, including GREENERA GARDENVILLA and GREENERA PRIME 1. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if GREENERA GARDENVILLA is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of GREENERA GARDENVILLA?

The registered promoter entity is GREENERA INFRAWELL PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in GREENERA GARDENVILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in GREENERA GARDENVILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GREENERA GARDENVILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GREENERA GARDENVILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.