Home / Browse projects / Bhavnagar, Gujarat / GREEN PARK

Valid until 10 Jan 2026 Mixed Development project

GREEN PARK

By Royal Infracon

RG-GJ-26652 · RERA PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA08310/070421 · Last updated on GujRERA portal: 7 Jan 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jan 2026Possession promisedmoved 15 months from the original
8 of 18Construction stages doneacross 2 buildings; furthest along: Internal walls, 60%
56 of 85Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

GREEN PARK is a Mixed Development project by Royal Infracon in Bhavnagar, Gujarat, registered with GujRERA as PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA08310/070421 on 7 Apr 2021. Possession is promised by 10 Jan 2026. The completion date has moved by 15 months from the original filing. 29 of the 85 units on this registration are recorded sold or booked, and 8 of 18 construction stages are filed complete.

At a glance

Project

  • NameGREEN PARK
  • TypeMixed Development
  • Location
    • Plot no 433-434 RS NO-1639-1640 Ward no 5
    • Prabhudas talav Bhavnagar
    • Bhavnagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA08310/070421
  • ReraGenie IDRG-GJ-26652

Builder

  • NameRoyal Infracon
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2021First promiseOct 2024Revised toJan 2026

Key facts

Registration and timeline

  • StatusValid until 10 Jan 2026
  • Registered on7 Apr 2021
  • Promised completion10 Jan 2026
  • Revised completionRevised to 10 Jan 2026 (originally 10 Oct 2024)
  • Buildings2 building records
  • Documents filed42 files

Current status

34%29 of 85 units booked
56.8%Of the estimated cost spent so far

Figures as on 7 Jan 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---49150
B---34135

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 7 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 60%.

A67%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B61%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 7 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,483 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 7.12 cr
Cost incurredRs 4.05 cr
Spent of the estimate56.84%
BuildingWingEstimatedIncurred
ANARs 3.56 crRs 2.02 cr
BNARs 3.56 crRs 2.02 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMAL BHATT
EngineerBHAVESH VYAS

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Mar 2025; no approval date filed

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA08310/070421 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)7 Jan 2023
Architect's certificate (Form 1)6 Jan 2023
Engineer's certificate (Form 2)6 Jan 2023
Engineer's certificate annexure6 Jan 2023
Site photograph, A6 Jan 2023
Site photograph, B6 Jan 2023
RERA registration certificate7 Apr 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Bhavnagar

34%of this project is bookeddistrict median 50%
16%of Bhavnagar projects moved their completion datethis one moved by 15 months

Computed across the 730+ Bhavnagar projects on ReraGenie, from their own filings.

Keep GREEN PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhavnagar730+ in Bhavnagar

2 kmGREEN PARKOther 159Dot size: filed unitsN

Filed coordinates, straight-line distance. 159 registered projects within 2 km.

Builder: Royal Infracon

Royal Infracon has 1 registration on GujRERA, including GREEN PARK. Read the full track record. See more projects on the Bhavnagar district page.

Frequently asked questions

What are my rights if GREEN PARK is delayed beyond 10 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of GREEN PARK?

The registered promoter entity is Royal Infracon, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in GREEN PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GREEN PARK?

The professionals named in the filing: Architect: HEMAL BHATT; Engineer: BHAVESH VYAS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GREEN PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GREEN PARK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GREEN PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.