Home / Browse projects / Ahmedabad, Gujarat / GAMARA EXOTICA

Valid until 30 Sep 2024 Mixed Development project

GAMARA EXOTICA

By GAMARA CONSTRUCTION CO

RG-GJ-89495 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11051/EX1/020824/300924 · Last updated on GujRERA portal: 30 Sep 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Sep 2024Possession promisedmoved 6 months from the original
8 of 9Construction stages donefurthest along: Stilt Floor, 0%
10 of 36Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

GAMARA EXOTICA is a Mixed Development project by GAMARA CONSTRUCTION CO in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11051/EX1/020824/300924 on 17 Dec 2022. Possession is promised by 30 Sep 2024. The completion date has moved by 6 months from the original filing. 26 of the 36 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameGAMARA EXOTICA
  • TypeMixed Development
  • Location
    • T.P. No. 3 (Ghuma)
    • F.P. No. 21
    • S. R. No. 547
    • Moje:- Ghuma
    • Ta. :- Daskroi
    • Dis. - Ahmedabad.
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11051/EX1/020824/300924
  • ReraGenie IDRG-GJ-89495

Builder

  • NameGAMARA CONSTRUCTION CO
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2022First promiseMar 2024Revised toSep 2024

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2024
  • Registered on17 Dec 2022
  • Promised completion30 Sep 2024
  • Revised completionRevised to 30 Sep 2024 (originally 31 Mar 2024)
  • Buildings1 building record
  • Documents filed41 files

Current status

72%26 of 36 units booked
100.0%Of the estimated cost spent so far

Figures as on 30 Sep 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---35136

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 30 Sep 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

A: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Sep 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,275 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 11.00 cr
Cost incurredRs 11.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 11.00 crRs 11.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUHAS A. PATEL
EngineerRAVI N. PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11051/EX1/020824/300924Applied Apr 2024; approved Aug 2024

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11051/EX1/020824/300924 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)30 Sep 2024
Engineer's certificate (Form 2)30 Sep 2024
Engineer's certificate annexure30 Sep 2024
Accountant's certificate (Form 3)30 Sep 2024
Site photograph, A30 Sep 2024
RERA registration certificate17 Dec 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

72%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 6 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep GAMARA EXOTICA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmGAMARA EXOTICAOther 229Dot size: filed unitsN

Filed coordinates, straight-line distance. 229 registered projects within 2 km.

Builder: GAMARA CONSTRUCTION CO

GAMARA CONSTRUCTION CO has 2 registrations on GujRERA, including GAMARA CAPITAL and GAMARA EXOTICA. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if GAMARA EXOTICA is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of GAMARA EXOTICA?

The registered promoter entity is GAMARA CONSTRUCTION CO, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in GAMARA EXOTICA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GAMARA EXOTICA?

The professionals named in the filing: Architect: SUHAS A. PATEL; Engineer: RAVI N. PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GAMARA EXOTICA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GAMARA EXOTICA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GAMARA EXOTICA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.