Valid until 31 Oct 2026 Mixed Development project

EUREKA HEIGHTS

By ANAND BUILDCON

RG-GJ-62076 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09019/EX1/EX2/280726/311026 · Last updated on GujRERA portal: 19 Jun 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 19 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Oct 2026Possession promisedmoved 19 months from the original
8 of 9Construction stages donefurthest along: Installation of lifts, 95%
71 of 99Units unsoldnot recorded sold or booked
Jump to the 47 documents Report an error

EUREKA HEIGHTS is a Mixed Development project by ANAND BUILDCON in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09019/EX1/EX2/280726/311026 on 7 Sep 2021. Possession is promised by 31 Oct 2026. The completion date has moved by 19 months from the original filing. 28 of the 99 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameEUREKA HEIGHTS
  • TypeMixed Development
  • Location
    • Eureka Heights Besides Joggers Park
    • Opp Abhisek Apartment Near Navavadaj Community Hall
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09019/EX1/EX2/280726/311026
  • ReraGenie IDRG-GJ-62076

Builder

  • NameANAND BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2021First promiseMar 2025Revised toOct 2026

Key facts

Registration and timeline

  • StatusValid until 31 Oct 2026
  • Registered on7 Sep 2021
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 31 Mar 2025)
  • Buildings1 building record
  • Documents filed47 files

Current status

28%28 of 99 units booked
99.0%Of the estimated cost spent so far

Figures as on 19 Jun 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A + B---792099

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Installation of lifts, at 95%.

A + B: 99% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes95%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes90%
Street lightingYes95%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes95%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes95%
Letter boxYes95%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,426 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 15.22 cr
Cost incurredRs 15.06 cr
Spent of the estimate99.0%
BuildingWingEstimatedIncurred
A + BNARs 15.22 crRs 15.06 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09019/EX1/010725/300326Applied Feb 2025; approved Jul 2025
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09019/EX1/EX2/280726/311026Applied Mar 2026; approved Jul 2026

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA09019/EX1/EX2/280726/311026 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)19 Jun 2026
Engineer's certificate (Form 2)9 Jun 2026
Engineer's certificate annexure9 Jun 2026
Architect's certificate (Form 1)8 Jun 2026
Site photograph, A + B8 Jun 2026
Site photograph, A + B8 Jun 2026
Site photograph, A + B8 Jun 2026
Site photograph, A + B8 Jun 2026
Site photograph, A + B8 Jun 2026
Site photograph, A + B8 Jun 2026
RERA registration certificate7 Sep 2021
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

28%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 19 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep EUREKA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmEUREKA HEIGHTSOther 112Dot size: filed unitsN

Filed coordinates, straight-line distance. 112 registered projects within 2 km.

Builder: ANAND BUILDCON

ANAND BUILDCON has 1 registration on GujRERA, including EUREKA HEIGHTS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if EUREKA HEIGHTS is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EUREKA HEIGHTS?

The registered promoter entity is ANAND BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EUREKA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in EUREKA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EUREKA HEIGHTS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EUREKA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.