Home / Browse projects / Bhavnagar, Gujarat / ENIGMA PRIME

Valid until 31 Mar 2027 Residential/Group Housing project

ENIGMA PRIME

By ENIGMA DEVELOPERS

RG-GJ-23529 · RERA PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA11766/150523 · Last updated on GujRERA portal: 14 Feb 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2027Possession promisedno revision filed
8 of 9Construction stages donefurthest along: Plinth, 0%
8 of 20Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

ENIGMA PRIME is a Residential/Group Housing project by ENIGMA DEVELOPERS in Bhavnagar, Gujarat, registered with GujRERA as PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA11766/150523 on 15 May 2023. Possession is promised by 31 Mar 2027. 12 of the 20 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameENIGMA PRIME
  • TypeResidential/Group Housing
  • Location
    • PLOT NO. 2247/E
    • C.SUR. 3088/A/1
    • WARD NO.7
    • AT HILL DRIVE
    • KRISHNANAGAR
    • BHAVNAGAR
    • Bhavnagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA11766/150523
  • ReraGenie IDRG-GJ-23529

Builder

  • NameENIGMA DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2023PromisedMar 2027

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2027
  • Registered on15 May 2023
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

60%12 of 20 units booked
59.4%Of the estimated cost spent so far

Figures as on 14 Feb 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ENIGMA PRIME---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 14 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Plinth, at 0%.

ENIGMA PRIME: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 14 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area626 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 3.20 cr
Cost incurredRs 1.90 cr
Spent of the estimate59.38%
BuildingWingEstimatedIncurred
ENIGMA PRIMENARs 3.20 crRs 1.90 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIYATI ROHITKUAR MAKDANI
EngineerSUNIL A VASA

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA11766/150523 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)14 Feb 2025
Architect's certificate (Form 1)13 Feb 2025
Site photograph, ENIGMA PRIME13 Feb 2025
Engineer's certificate (Form 2)2 Oct 2024
Engineer's certificate annexure2 Oct 2024
RERA registration certificate15 May 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Bhavnagar

60%of this project is bookeddistrict median 50%
16%of Bhavnagar projects moved their completion datethis one has not

Computed across the 730+ Bhavnagar projects on ReraGenie, from their own filings.

Keep ENIGMA PRIME on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhavnagar730+ in Bhavnagar

2 kmENIGMA PRIMEOther 198Dot size: filed unitsN

Filed coordinates, straight-line distance. 198 registered projects within 2 km.

Builder: ENIGMA DEVELOPERS

ENIGMA DEVELOPERS has 1 registration on GujRERA, including ENIGMA PRIME. Read the full track record. See more projects on the Bhavnagar district page.

Frequently asked questions

What are my rights if ENIGMA PRIME is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ENIGMA PRIME?

The registered promoter entity is ENIGMA DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ENIGMA PRIME?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ENIGMA PRIME?

The professionals named in the filing: Architect: NIYATI ROHITKUAR MAKDANI; Engineer: SUNIL A VASA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ENIGMA PRIME?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ENIGMA PRIME. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ENIGMA PRIME to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.