Valid until 25 Dec 2025 Commercial project

EMPORIS

By AARUSH SPACES LLP

RG-GJ-48758 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA05920/A2C/EX2/110325/251225 · Last updated on GujRERA portal: 21 Dec 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Dec 2025Possession promisedmoved 24 months from the original
5 of 9Construction stages donefurthest along: Stilt Floor, 96%
313 of 407Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

EMPORIS is a Commercial project by AARUSH SPACES LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA05920/A2C/EX2/110325/251225 on 20 Aug 2019. Possession is promised by 25 Dec 2025. The completion date has moved by 24 months from the original filing. 94 of the 407 units on this registration are recorded sold or booked, and 5 of 9 construction stages are filed complete.

At a glance

Project

  • NameEMPORIS
  • TypeCommercial
  • Location
    • EMPORIS
    • SURVEY NO 101/1/1 ETC
    • BESIDES DCATHELON
    • VISAT-TAPOVAN ROAD
    • MOTERA
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA05920/A2C/EX2/110325/251225
  • ReraGenie IDRG-GJ-48758

Builder

  • NameAARUSH SPACES LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2019First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusValid until 25 Dec 2025
  • Registered on20 Aug 2019
  • Promised completion25 Dec 2025
  • Revised completionRevised to 25 Dec 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed38 files

Current status

23%94 of 407 units booked
87.1%Of the estimated cost spent so far

Figures as on 21 Dec 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EMPORIS---0407407

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 21 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 96%.

EMPORIS: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor96%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats74%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing49%

Progress on shared amenities23

As on 21 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes45%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes45%
Electrical meter room, sub-station, receiving stationYes25%
Fire fightingYes45%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable
Compound wallYes0%
Plinth protectionYes40%
Water tankYes55%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,440 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 85.00 cr
Cost incurredRs 74.00 cr
Spent of the estimate87.06%
BuildingWingEstimatedIncurred
EMPORISNARs 85.00 crRs 74.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANSHI SHAH
EngineerBHOOMI CONSULTANTS

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA05920/A2C/EX1/210324/281224Applied Jan 2024; approved Mar 2024
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA05920/A2C/EX2/110325/251225Applied Dec 2024; approved Mar 2025

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA05920/A2C/EX2/110325/251225 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)21 Dec 2024
Engineer's certificate annexure21 Dec 2024
RERA registration certificate20 Aug 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

23%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 24 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep EMPORIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmEMPORISOther 132Dot size: filed unitsN

Filed coordinates, straight-line distance. 132 registered projects within 2 km.

Builder: AARUSH SPACES LLP

AARUSH SPACES LLP has 1 registration on GujRERA, including EMPORIS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if EMPORIS is delayed beyond 25 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EMPORIS?

The registered promoter entity is AARUSH SPACES LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EMPORIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EMPORIS?

The professionals named in the filing: Architect: MANSHI SHAH; Engineer: BHOOMI CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EMPORIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EMPORIS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EMPORIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.