Home / Browse projects / Vadodara, Gujarat / DOVEDECK

Valid until 31 Dec 2022 Residential/Group Housing project

DOVEDECK

By SANGANI INFRASTRUCTURE INDIA PRIVATE LIMITED

RG-GJ-93722 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA01248/EX3/100522 · Last updated on GujRERA portal: 6 Aug 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 42 months
  • 3 extensions taken

Clear

  • Separate project account declared
Dec 2022Possession promisedmoved 42 months from the original
59 of 63Construction stages doneacross 7 buildings; furthest along: Internal walls, 95%
1 of 336Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

DOVEDECK is a Residential/Group Housing project by SANGANI INFRASTRUCTURE INDIA PRIVATE LIMITED in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA01248/EX3/100522 on 8 Jan 2018. Possession is promised by 31 Dec 2022. The completion date has moved by 42 months from the original filing. 335 of the 336 units on this registration are recorded sold or booked, and 59 of 63 construction stages are filed complete.

At a glance

Project

  • NameDOVEDECK
  • TypeResidential/Group Housing
  • Location
    • NEAR AMERICAN SCHOOL OF BARODA
    • VADODARA AAJWA ROAD
    • Sayjipura
    • Vadodara
    • 390019
  • Pincode390019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA01248/EX3/100522
  • ReraGenie IDRG-GJ-93722

Builder

  • NameSANGANI INFRASTRUCTURE INDIA PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations1 more →

Key dates

this monthRegisteredJan 2018First promiseJun 2019Revised toDec 2022

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2022
  • Registered on8 Jan 2018
  • Promised completion31 Dec 2022
  • Revised completionRevised to 31 Dec 2022 (originally 30 Jun 2019)
  • Buildings7 building records
  • Documents filed44 files

Current status

100%335 of 336 units booked
99.4%Of the estimated cost spent so far

Figures as on 6 Aug 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
K1---48048
K2---48048
O1---48048
O2---48048
L---48048
M---48048
N---48048

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 6 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

59 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Internal walls, at 95%.

K1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
K2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
O1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
O2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
L100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
M100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
N98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 6 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,033 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 31.50 cr
Cost incurredRs 31.32 cr
Spent of the estimate99.42%
BuildingWingEstimatedIncurred
K1NARs 4.50 crRs 4.47 cr
K2NARs 4.50 crRs 4.47 cr
O1NARs 4.50 crRs 4.47 cr
O2NARs 4.50 crRs 4.47 cr
LNARs 4.50 crRs 4.47 cr
MNARs 4.50 crRs 4.47 cr
NNARs 4.50 crRs 4.47 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUCHIR MANOJ SHETH
EngineerMEHUL PATEL

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA01248/EX1/150719Applied Jun 2019; approved Jul 2019
PR/GJ/VADODARA/VADODARA/Others/RAA01248/EX2/150421Applied Mar 2021; approved Apr 2021
PR/GJ/VADODARA/VADODARA/Others/RAA01248/EX3/100522Applied Apr 2022; approved May 2022

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA01248/EX3/100522 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Aug 2022
Engineer's certificate (Form 2)2 Aug 2022
Engineer's certificate annexure2 Aug 2022
Architect's certificate (Form 1)1 Aug 2022
Site photograph, K11 Aug 2022
Site photograph, K21 Aug 2022
Site photograph, O11 Aug 2022
Site photograph, O21 Aug 2022
Site photograph, L1 Aug 2022
Site photograph, M1 Aug 2022
Site photograph, N1 Aug 2022
RERA registration certificate8 Jan 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

100%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 42 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep DOVEDECK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sayjipura2,900+ in Vadodara

2 kmDOVEDECKOther 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 74 registered projects within 2 km.

Builder: SANGANI INFRASTRUCTURE INDIA PRIVATE LIMITED

SANGANI INFRASTRUCTURE INDIA PRIVATE LIMITED has 2 registrations on GujRERA, including SANGANI SKYZ and DOVEDECK. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if DOVEDECK is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DOVEDECK?

The registered promoter entity is SANGANI INFRASTRUCTURE INDIA PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DOVEDECK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DOVEDECK?

The professionals named in the filing: Architect: RUCHIR MANOJ SHETH; Engineer: MEHUL PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DOVEDECK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DOVEDECK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DOVEDECK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.