Home / Browse projects / Vadodara, Gujarat / DOVE DECK

Valid until 30 Apr 2021 Residential/Group Housing project

DOVE DECK

By OMSHIVAY BUILDERS LLP

RG-GJ-77837 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA03683/121018 · Last updated on GujRERA portal: 7 Feb 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Apr 2021Possession promisedmoved 16 months from the original
23 of 49Construction stages doneacross 6 buildings; furthest along: Sanitary fittings within the flats, 80%
Jump to the 41 documents Report an error

DOVE DECK is a Residential/Group Housing project by OMSHIVAY BUILDERS LLP in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA03683/121018 on 12 Oct 2018. Possession is promised by 30 Apr 2021. The completion date has moved by 16 months from the original filing.

At a glance

Project

  • NameDOVE DECK
  • TypeResidential/Group Housing
  • Location
    • DOVEDECK
    • OPP AMERICAN SCHOOL AJWA ROAD
    • Sayajipura
    • Vadodara
    • 390019
  • Pincode390019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA03683/121018
  • ReraGenie IDRG-GJ-77837

Builder

  • NameOMSHIVAY BUILDERS LLP
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2018First promiseDec 2019Revised toApr 2021

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2021
  • Registered on12 Oct 2018
  • Promised completion30 Apr 2021
  • Revised completionRevised to 30 Apr 2021 (originally 31 Dec 2019)
  • Buildings6 building records
  • Documents filed41 files

Current status

8.4%Of the estimated cost spent so far

Figures as on 7 Feb 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER G1-----42
TOWER G2-----45
TOWER H1-----47
TOWER H2-----46
TOWER I-----48
TOWER J-----47

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 7 Feb 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

23 of 49 construction stages are filed complete across 6 buildings. The stage furthest along is Sanitary fittings within the flats, at 80%.

TOWER G166%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
TOWER G282%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
TOWER H138%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, internal plaster, floorings, doors and windows within flats10%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TOWER H238%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, internal plaster, floorings, doors and windows within flats10%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TOWER I100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER J47%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats25%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 7 Feb 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes80%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes20%
Fire fightingNoNot applicable
Drinking water facilitiesYes20%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes20%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,663 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 37.66 cr
Cost incurredRs 3.15 cr
Spent of the estimate8.37%
BuildingWingEstimatedIncurred
TOWER G1NARs 6.28 crRs 52.50 lakh
TOWER G2NARs 6.28 crRs 52.50 lakh
TOWER H1NARs 6.28 crRs 52.50 lakh
TOWER H2NARs 6.28 crRs 52.50 lakh
TOWER INARs 6.28 crRs 52.50 lakh
TOWER JNARs 6.28 crRs 52.50 lakh

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Jul 2026; no approval date filed

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA03683/121018 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Feb 2019
Engineer's certificate (Form 2)7 Feb 2019
Site photograph, TOWER G17 Feb 2019
Site photograph, TOWER G27 Feb 2019
Site photograph, TOWER H17 Feb 2019
Site photograph, TOWER H27 Feb 2019
Site photograph, TOWER I7 Feb 2019
Site photograph, TOWER J7 Feb 2019
RERA registration certificate12 Oct 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

23%of Vadodara projects moved their completion datethis one moved by 16 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep DOVE DECK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sayajipura2,900+ in Vadodara

2 kmDOVE DECKOther 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: OMSHIVAY BUILDERS LLP

OMSHIVAY BUILDERS LLP has 1 registration on GujRERA, including DOVE DECK. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if DOVE DECK is delayed beyond 30 Apr 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DOVE DECK?

The registered promoter entity is OMSHIVAY BUILDERS LLP, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DOVE DECK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in DOVE DECK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DOVE DECK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DOVE DECK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.