ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / DHARM SKYLINK

Valid until 30 Apr 2028 Residential/Group Housing project

DHARM SKYLINK

By SHIVANTA BUILDCON

RG-GJ-85869 · RERA PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/RN87AA09987/230622 · Last updated on GujRERA portal: 30 Sep 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
13 of 18Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 94%
94 of 140Units unsoldnot recorded sold or booked
Jump to the 20 documents Report an error

DHARM SKYLINK is a Residential/Group Housing project by SHIVANTA BUILDCON in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/RN87AA09987/230622 on 23 Jun 2022. Possession is promised by 30 Apr 2028. 46 of the 140 units on this registration are recorded sold or booked, and 13 of 18 construction stages are filed complete.

At a glance

Project

  • NameDHARM SKYLINK
  • TypeResidential/Group Housing
  • Location
    • DHARM SKYLINK
    • NEAR DEVAM RESIDENCY
    • BEHIND KEDRAM VILLA
    • VATVA
    • AHMEDABAD
    • VATVA
    • Daskroi
    • Ahmedabad
    • 382440
  • Pincode382440
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/RN87AA09987/230622
  • ReraGenie IDRG-GJ-85869

Builder

  • NameSHIVANTA BUILDCON
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredJun 2022PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on23 Jun 2022
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed20 files

Current status

33%46 of 140 units booked
46.8%Of the estimated cost spent so far

Figures as on 30 Sep 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---60060
Block B+C---80080

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 30 Sep 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 94%.

Block A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block B+C87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor94%
Slabs of Super Structure91%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats94%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing94%

Progress on shared amenities23

As on 30 Sep 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes35%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes50%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes20%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,824 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 25.00 cr
Cost incurredRs 11.71 cr
Spent of the estimate46.84%
BuildingWingEstimatedIncurred
Block B+CNARs 15.00 crRs 4.26 cr
Block ANARs 10.00 crRs 7.45 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanket Kailashbhai Vora
EngineerCHIRAGKUMAR PRAGJIBHAI NAKRANI

Documents filed20

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/RN87AA09987/230622 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)30 Sep 2024
Engineer's certificate annexure30 Sep 2024
RERA registration certificate23 Jun 2022
Proforma agreement for sale-
Project specific document-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-

How this compares with Ahmedabad

33%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep DHARM SKYLINK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near VATVA5,400+ in Ahmedabad

2 kmDHARM SKYLINKOther 196Dot size: filed unitsN

Filed coordinates, straight-line distance. 196 registered projects within 2 km.

Builder: SHIVANTA BUILDCON

SHIVANTA BUILDCON has 3 registrations on GujRERA, including ANANTA GREENS AND ELYSIUM and DHARM SKYLINK. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if DHARM SKYLINK is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DHARM SKYLINK?

The registered promoter entity is SHIVANTA BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DHARM SKYLINK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DHARM SKYLINK?

The professionals named in the filing: Architect: Sanket Kailashbhai Vora; Engineer: CHIRAGKUMAR PRAGJIBHAI NAKRANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DHARM SKYLINK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DHARM SKYLINK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DHARM SKYLINK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.