Home / Browse projects / Ahmedabad, Gujarat / OMSHANTI GOLD PLUS-2

Valid until 30 Nov 2024 Mixed Development project

OMSHANTI GOLD PLUS-2

By OMSHANTI ESTATES PRIVATE LIMITED

RG-GJ-67928 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA06413/A2M/100222 · Last updated on GujRERA portal: 18 Nov 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Nov 2024Possession promisedno revision filed
49 of 63Construction stages doneacross 7 buildings; furthest along: Plinth, 0%
7 of 498Units unsoldnot recorded sold or booked
Jump to the 47 documents Report an error

OMSHANTI GOLD PLUS-2 is a Mixed Development project by OMSHANTI ESTATES PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA06413/A2M/100222 on 29 Nov 2019. Possession is promised by 30 Nov 2024. 491 of the 498 units on this registration are recorded sold or booked, and 49 of 63 construction stages are filed complete.

At a glance

Project

  • NameOMSHANTI GOLD PLUS-2
  • TypeMixed Development
  • Location
    • Omshanti Gold Plus-2
    • Nr. Omshanti Bunglows
    • Gamdi Road
    • Vatva
    • Vatva
    • Ahmedabad City
    • Ahmedabad
    • 382440
  • Pincode382440
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA06413/A2M/100222
  • ReraGenie IDRG-GJ-67928

Builder

  • NameOMSHANTI ESTATES PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations2 more →

Key dates

this monthRegisteredNov 2019PromisedNov 2024

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2024
  • Registered on29 Nov 2019
  • Promised completion30 Nov 2024
  • Revised completionNone
  • Buildings7 building records
  • Documents filed47 files

Current status

99%491 of 498 units booked
77.2%Of the estimated cost spent so far

Figures as on 18 Nov 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---40848
B---67067
C---67067
D---67067
E---81081
F---70070
G---782098

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 18 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

49 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Plinth, at 0%.

A78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 18 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,348 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 57.00 cr
Cost incurredRs 44.00 cr
Spent of the estimate77.19%
BuildingWingEstimatedIncurred
GNARs 11.50 crRs 8.91 cr
ENARs 10.97 crRs 8.05 cr
FNARs 10.97 crRs 8.05 cr
BNARs 6.43 crRs 5.15 cr
CNARs 6.43 crRs 4.33 cr
DNARs 6.43 crRs 5.66 cr
ANARs 4.27 crRs 3.84 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJagrut Patel (Vitan)
EngineerNaresh K. Shah

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA06413/A2M/100222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)18 Nov 2024
Engineer's certificate (Form 2)18 Nov 2024
Engineer's certificate annexure18 Nov 2024
Accountant's certificate (Form 3)18 Nov 2024
Site photograph, A18 Nov 2024
Site photograph, B18 Nov 2024
Site photograph, C18 Nov 2024
Site photograph, D18 Nov 2024
Site photograph, E18 Nov 2024
Site photograph, F18 Nov 2024
Site photograph, G18 Nov 2024
RERA registration certificate29 Nov 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

99%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep OMSHANTI GOLD PLUS-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vatva5,400+ in Ahmedabad

2 kmOMSHANTI GOLD PLUS-2Other 220Dot size: filed unitsN

Filed coordinates, straight-line distance. 220 registered projects within 2 km.

Builder: OMSHANTI ESTATES PRIVATE LIMITED

OMSHANTI ESTATES PRIVATE LIMITED has 3 registrations on GujRERA, including Omshanti Gold Plus and OMSHANTI RAJ NIWAS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if OMSHANTI GOLD PLUS-2 is delayed beyond 30 Nov 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of OMSHANTI GOLD PLUS-2?

The registered promoter entity is OMSHANTI ESTATES PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in OMSHANTI GOLD PLUS-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at OMSHANTI GOLD PLUS-2?

The professionals named in the filing: Architect: Jagrut Patel (Vitan); Engineer: Naresh K. Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OMSHANTI GOLD PLUS-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OMSHANTI GOLD PLUS-2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OMSHANTI GOLD PLUS-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.