Home / Browse projects / Ahmedabad, Gujarat / DEVASYA GOLD PLUS

Valid until 31 Dec 2025 Residential/Group Housing project

DEVASYA GOLD PLUS

By SHREE RAMDEV CORPORATION

RG-GJ-01363 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA08980/A1R/050423 · Last updated on GujRERA portal: 6 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2025Possession promisedno revision filed
18 of 18Construction stages doneacross 2 buildings; every applicable stage filed complete
12 of 96Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

DEVASYA GOLD PLUS is a Residential/Group Housing project by SHREE RAMDEV CORPORATION in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA08980/A1R/050423 on 3 Sep 2021. Possession is promised by 31 Dec 2025. 84 of the 96 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameDEVASYA GOLD PLUS
  • TypeResidential/Group Housing
  • Location
    • Devasya Gold Plus
    • Nr. Devasya School
    • B/h. Somnath Party Plot
    • Nikol
    • Ahmedabad-382350
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA08980/A1R/050423
  • ReraGenie IDRG-GJ-01363

Builder

  • NameSHREE RAMDEV CORPORATION
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2021PromisedDec 2025

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2025
  • Registered on3 Sep 2021
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed38 files

Current status

88%84 of 96 units booked
100.0%Of the estimated cost spent so far

Figures as on 6 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---48048
A---48048

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 6 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete across 2 buildings.

B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 6 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%
Compound wallYes100%
Plinth protectionYes100%
Water tankYes100%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,805 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 17.80 cr
Cost incurredRs 17.80 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 11.40 crRs 11.40 cr
BNARs 6.40 crRs 6.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKETAN K.PATEL
EngineerNARENDRA K.PATEL

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA08980/A1R/050423 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)6 Oct 2024
Engineer's certificate annexure6 Oct 2024
RERA registration certificate3 Sep 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

88%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep DEVASYA GOLD PLUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmDEVASYA GOLD PLUSOther 315Dot size: filed unitsN

Filed coordinates, straight-line distance. 315 registered projects within 2 km.

Builder: SHREE RAMDEV CORPORATION

SHREE RAMDEV CORPORATION has 1 registration on GujRERA, including DEVASYA GOLD PLUS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if DEVASYA GOLD PLUS is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DEVASYA GOLD PLUS?

The registered promoter entity is SHREE RAMDEV CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DEVASYA GOLD PLUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DEVASYA GOLD PLUS?

The professionals named in the filing: Architect: KETAN K.PATEL; Engineer: NARENDRA K.PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DEVASYA GOLD PLUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DEVASYA GOLD PLUS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DEVASYA GOLD PLUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.