ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / CORAL WOODS

Valid until 25 Dec 2019 Residential/Group Housing project

CORAL WOODS

By SHILP REALITY

RG-GJ-41314 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA02810/EX1/140219 · Last updated on GujRERA portal: 25 Dec 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Dec 2019Possession promisedmoved 12 months from the original
56 of 56Construction stages doneacross 8 buildings; every applicable stage filed complete
9 of 226Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

CORAL WOODS is a Residential/Group Housing project by SHILP REALITY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA02810/EX1/140219 on 2 Jun 2018. Possession is promised by 25 Dec 2019. The completion date has moved by 12 months from the original filing. 217 of the 226 units on this registration are recorded sold or booked, and 56 of 56 construction stages are filed complete.

At a glance

Project

  • NameCORAL WOODS
  • TypeResidential/Group Housing
  • Location
    • BEHIND RAJDEEP COMPLEX
    • TARSALI VADODARA
    • Tarsali
    • Vadodara
    • 390010
  • Pincode390010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA02810/EX1/140219
  • ReraGenie IDRG-GJ-41314

Builder

  • NameSHILP REALITY
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredJun 2018First promiseDec 2018Revised toDec 2019

Key facts

Registration and timeline

  • StatusValid until 25 Dec 2019
  • Registered on2 Jun 2018
  • Promised completion25 Dec 2019
  • Revised completionRevised to 25 Dec 2019 (originally 31 Dec 2018)
  • Buildings8 building records
  • Documents filed45 files

Current status

96%217 of 226 units booked
100.0%Of the estimated cost spent so far

Figures as on 25 Dec 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER A---20020
TOWER B---40040
TOWER C---40040
TOWER D---20020
TOWER E---30030
TOWER F---30030
TOWER G---30030
TOWER H---16016

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 25 Dec 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

56 of 56 construction stages are filed complete across 8 buildings.

TOWER A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 25 Dec 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingYes99%
Street lightingYes100%
Community buildingsYes98%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,968 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.23 cr
Cost incurredRs 11.23 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
TOWER ANARs 1.40 crRs 1.40 cr
TOWER BNARs 1.40 crRs 1.40 cr
TOWER CNARs 1.40 crRs 1.40 cr
TOWER DNARs 1.40 crRs 1.40 cr
TOWER ENARs 1.40 crRs 1.40 cr
TOWER FNARs 1.40 crRs 1.40 cr
TOWER GNARs 1.40 crRs 1.40 cr
TOWER HNARs 1.40 crRs 1.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANJALI ASSOCIATES
EngineerASHOK SHAH & ASSOCIATES

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA02810/EX1/140219Applied Dec 2018; approved Feb 2019

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA02810/EX1/140219 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)25 Dec 2019
Engineer's certificate (Form 2)25 Dec 2019
Engineer's certificate annexure25 Dec 2019
Accountant's certificate (Form 3)25 Dec 2019
Site photograph, TOWER A25 Dec 2019
Site photograph, TOWER B25 Dec 2019
Site photograph, TOWER C25 Dec 2019
Site photograph, TOWER D25 Dec 2019
Site photograph, TOWER E25 Dec 2019
Site photograph, TOWER F25 Dec 2019
Site photograph, TOWER G25 Dec 2019
Site photograph, TOWER H25 Dec 2019
RERA registration certificate2 Jun 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

96%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep CORAL WOODS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Tarsali2,900+ in Vadodara

2 kmCORAL WOODSOther 144Dot size: filed unitsN

Filed coordinates, straight-line distance. 144 registered projects within 2 km.

Builder: SHILP REALITY

SHILP REALITY has 2 registrations on GujRERA, including CORAL WOODS and HARIDARSHAN GREENS. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if CORAL WOODS is delayed beyond 25 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of CORAL WOODS?

The registered promoter entity is SHILP REALITY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in CORAL WOODS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CORAL WOODS?

The professionals named in the filing: Architect: ANJALI ASSOCIATES; Engineer: ASHOK SHAH & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CORAL WOODS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CORAL WOODS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CORAL WOODS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.