Valid until 30 Jun 2023 Mixed Development project

CITY HUB

By RISHIRAJ DEVELOPERS

RG-GJ-60230 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA03551/EX2/060722 · Last updated on GujRERA portal: 7 Apr 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jun 2023Possession promisedmoved 24 months from the original
6 of 9Construction stages donefurthest along: Internal walls, 92%
102 of 162Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

CITY HUB is a Mixed Development project by RISHIRAJ DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA03551/EX2/060722 on 29 Sep 2018. Possession is promised by 30 Jun 2023. The completion date has moved by 24 months from the original filing. 60 of the 162 units on this registration are recorded sold or booked, and 6 of 9 construction stages are filed complete.

At a glance

Project

  • NameCITY HUB
  • TypeMixed Development
  • Location
    • NR. MADHYAVARTI SCHOOL
    • DANDIA BAZAR MARKET MAIN ROAD
    • Babajipura
    • Vadodara
    • 390001
  • Pincode390001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA03551/EX2/060722
  • ReraGenie IDRG-GJ-60230

Builder

  • NameRISHIRAJ DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2018First promiseJun 2021Revised toJun 2023

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2023
  • Registered on29 Sep 2018
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed38 files

Current status

37%60 of 162 units booked
55.8%Of the estimated cost spent so far

Figures as on 7 Apr 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
single---10755162

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 92%.

single: 81% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats92%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%

Progress on shared amenities19

As on 7 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,268 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 14.30 cr
Cost incurredRs 7.99 cr
Spent of the estimate55.84%
BuildingWingEstimatedIncurred
singleNARs 14.30 crRs 7.99 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMBANI ASSOCIATE
EngineerPRAMUKH ASSOCIATES

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA03551/EX1/290621Applied Apr 2021; approved Jun 2021
PR/GJ/VADODARA/VADODARA/Others/MAA03551/EX2/060722Applied Apr 2022; approved Jul 2022

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA03551/EX2/060722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Apr 2023
Engineer's certificate (Form 2)7 Apr 2023
Engineer's certificate annexure7 Apr 2023
Accountant's certificate (Form 3)7 Apr 2023
Site photograph, single7 Apr 2023
RERA registration certificate29 Sep 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

37%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 24 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep CITY HUB on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Babajipura2,900+ in Vadodara

2 kmCITY HUBOther 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 118 registered projects within 2 km.

Builder: RISHIRAJ DEVELOPERS

RISHIRAJ DEVELOPERS has 1 registration on GujRERA, including CITY HUB. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if CITY HUB is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of CITY HUB?

The registered promoter entity is RISHIRAJ DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in CITY HUB?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CITY HUB?

The professionals named in the filing: Architect: AMBANI ASSOCIATE; Engineer: PRAMUKH ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CITY HUB?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CITY HUB. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CITY HUB to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.