Red flags

  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Oct 2027Possession promisedmoved 28 months from the original
5 of 9Construction stages donefurthest along: Sanitary fittings within the flats, 93%
183 of 185Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

CITY BUSINESS CENTRE is a Commercial project by DRA NAVSARI BUSPORT PRIVATE LIMITED in Navsari, Gujarat, registered with GujRERA as PR/GJ/NAVSARI/NAVSARI/Others/CAA06959/EX1/011025/300626 on 30 Apr 2020. Possession is promised by 30 Oct 2027. The completion date has moved by 28 months from the original filing. 2 of the 185 units on this registration are recorded sold or booked, and 5 of 9 construction stages are filed complete.

At a glance

Project

  • NameCITY BUSINESS CENTRE
  • TypeCommercial
  • Location
    • NAVSARI GSRTC BUS PORT
    • Depot Rd
    • Madhumati Colony
    • Navsari
    • Navsari
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/NAVSARI/NAVSARI/Others/CAA06959/EX1/011025/300626
  • ReraGenie IDRG-GJ-98930

Builder

  • NameDRA NAVSARI BUSPORT PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredApr 2020First promiseJun 2025Revised toOct 2027

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2027
  • Registered on30 Apr 2020
  • Promised completion30 Oct 2027
  • Revised completionRevised to 30 Oct 2027 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed40 files

Current status

1%2 of 185 units booked
87.6%Of the estimated cost spent so far

Figures as on 23 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
One---0169185

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 23 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 9 construction stages are filed complete. The stage furthest along is Sanitary fittings within the flats, at 93%.

One: 86% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats93%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing93%

Progress on shared amenities19

As on 23 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes90%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes70%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes70%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes75%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area26,414 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 76.50 cr
Cost incurredRs 67.03 cr
Spent of the estimate87.61%
BuildingWingEstimatedIncurred
OneNARs 76.50 crRs 67.03 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMamta Shah & Associates
EngineerZARNA ASSOCIATES

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/NAVSARI/NAVSARI/Others/CAA06959/EX1/011025/300626Applied Jul 2025; approved Oct 2025
ExtensionApplied Jun 2026; no approval date filed

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/NAVSARI/NAVSARI/Others/CAA06959/EX1/011025/300626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)23 Sep 2025
Engineer's certificate (Form 2)23 Sep 2025
Engineer's certificate annexure23 Sep 2025
Accountant's certificate (Form 3)23 Sep 2025
RERA registration certificate30 Apr 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Navsari

1%of this project is bookeddistrict median 40%
10%of Navsari projects moved their completion datethis one moved by 28 months

Computed across the 120+ Navsari projects on ReraGenie, from their own filings.

Keep CITY BUSINESS CENTRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Navsari120+ in Navsari

2 kmCITY BUSINESS CENTREOther 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 46 registered projects within 2 km.

Builder: DRA NAVSARI BUSPORT PRIVATE LIMITED

DRA NAVSARI BUSPORT PRIVATE LIMITED has 1 registration on GujRERA, including CITY BUSINESS CENTRE. Read the full track record. See more projects on the Navsari district page.

Frequently asked questions

What are my rights if CITY BUSINESS CENTRE is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of CITY BUSINESS CENTRE?

The registered promoter entity is DRA NAVSARI BUSPORT PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in CITY BUSINESS CENTRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CITY BUSINESS CENTRE?

The professionals named in the filing: Architect: Mamta Shah & Associates; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CITY BUSINESS CENTRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CITY BUSINESS CENTRE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CITY BUSINESS CENTRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.