Home / Browse projects / Navsari, Gujarat / PRABHAKUNJ PANAISHA

Valid until 11 Jul 2026 Mixed Development project

PRABHAKUNJ PANAISHA

By PRABHAKUNJ ARISE LLP

RG-GJ-60945 · RERA PR/GJ/NAVSARI/JALALPORE/Others/MAA04355/131218 · Last updated on GujRERA portal: 23 Aug 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2026Possession promisedno revision filed
16 of 27Construction stages doneacross 3 buildings; furthest along: Plinth, 0%
177 of 331Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

PRABHAKUNJ PANAISHA is a Mixed Development project by PRABHAKUNJ ARISE LLP in Navsari, Gujarat, registered with GujRERA as PR/GJ/NAVSARI/JALALPORE/Others/MAA04355/131218 on 13 Dec 2018. Possession is promised by 11 Jul 2026. 154 of the 331 units on this registration are recorded sold or booked, and 16 of 27 construction stages are filed complete.

At a glance

Project

  • NamePRABHAKUNJ PANAISHA
  • TypeMixed Development
  • Location
    • REVENUE SURVEY NO. 321/1/1
    • VILLAGE VIJALPORE
    • Jalapor
    • Jalalpore
    • Navsari
    • 396445
  • Pincode396445
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/NAVSARI/JALALPORE/Others/MAA04355/131218
  • ReraGenie IDRG-GJ-60945

Builder

  • NamePRABHAKUNJ ARISE LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2018PromisedJul 2026

Key facts

Registration and timeline

  • StatusValid until 11 Jul 2026
  • Registered on13 Dec 2018
  • Promised completion11 Jul 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed40 files

Current status

47%154 of 331 units booked
52.7%Of the estimated cost spent so far

Figures as on 23 Aug 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C---1200120
A---56864
B---1398147

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 23 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Plinth, at 0%.

C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 23 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes65%
Sewerage (chamber, lines, septic tank, STP)Yes50%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes60%
Street lightingYes80%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes60%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes60%
Fire fightingNoNot applicable
Drinking water facilitiesYes80%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes50%
Letter boxYes50%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,070 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 22.00 cr
Cost incurredRs 11.60 cr
Spent of the estimate52.73%
BuildingWingEstimatedIncurred
BNARs 10.40 cr-
CNARs 7.70 crRs 7.70 cr
ANARs 3.90 crRs 3.90 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMISTRY ANUP MUKUNDBHAI
EngineerMODI BHAVESHKUMAR YOGESHBHAI

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/NAVSARI/JALALPORE/Others/MAA04355/131218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)23 Aug 2025
Accountant's certificate (Form 3)23 Aug 2025
Site photograph, C22 Aug 2025
Site photograph, A22 Aug 2025
Site photograph, B22 Aug 2025
Engineer's certificate (Form 2)18 Oct 2024
Engineer's certificate annexure18 Oct 2024
RERA registration certificate13 Dec 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Navsari

47%of this project is bookeddistrict median 40%
10%of Navsari projects moved their completion datethis one has not

Computed across the 120+ Navsari projects on ReraGenie, from their own filings.

Keep PRABHAKUNJ PANAISHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Jalapor120+ in Navsari

2 kmPRABHAKUNJ PANAISHAOther 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: PRABHAKUNJ ARISE LLP

PRABHAKUNJ ARISE LLP has 1 registration on GujRERA, including PRABHAKUNJ PANAISHA. Read the full track record. See more projects on the Navsari district page.

Frequently asked questions

What are my rights if PRABHAKUNJ PANAISHA is delayed beyond 11 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PRABHAKUNJ PANAISHA?

The registered promoter entity is PRABHAKUNJ ARISE LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PRABHAKUNJ PANAISHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PRABHAKUNJ PANAISHA?

The professionals named in the filing: Architect: MISTRY ANUP MUKUNDBHAI; Engineer: MODI BHAVESHKUMAR YOGESHBHAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRABHAKUNJ PANAISHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRABHAKUNJ PANAISHA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRABHAKUNJ PANAISHA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.