ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Rural, Karnataka / Canterbury Meadows Phase 2

Registration approved No litigation declared Plotted Development project

Canterbury Meadows Phase 2

By Arunapanchami Estates Private Limited

RG-KA-31729 · RERA PRM/KA/RERA/1250/301/PR/150324/006703 · Last updated on RERA Karnataka portal: 6 Mar 2024

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 161 documents Report an error

Canterbury Meadows Phase 2 is a Plotted Development project by Arunapanchami Estates Private Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/301/PR/150324/006703 on 15 Mar 2024. Possession is promised by 30 Nov 2023.

At a glance

Project

  • NameCanterbury Meadows Phase 2
  • TypePlotted Development
  • Location
    • Doddaballapura
    • Bengaluru Rural
    • 561205
  • Pincode561205
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/301/PR/150324/006703
  • ReraGenie IDRG-KA-31729

Builder

  • NameArunapanchami Estates Private Limited
  • Entity typeCompany
  • CINU45203KA2013PTC070747
  • GSTIN29AALCA9860C1ZD
  • Authorized SignatoryH Mahadev Goud
  • Managing DirectorH Mahadev Goud
  • DirectorsP K Jagadeesh, Mahadeva Swamy, H Mahadev Goud
  • Project HeadH Mahadev Goud
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

Registered
15 Mar 2024
Promised
30 Nov 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Mar 2024
  • Promised completion30 Nov 2023
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed161 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership6

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners6
LandownerVillageDistrict
M/s Bangalore Regency Developers Private Limited--
M/s Bangalore Regency Developers Private Limited--
M/s Bangalore Regency Developers Private Limited--
M/s Bangalore Regency Developers Private Limited--
M/s Bangalore Regency Developers Private Limited--
M/s Bangalore Regency Developers Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.52 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 2.00 cr-
On-site expenditure-Salaries of workersRs 98.14 lakh-
On-site expenditure-Site OverheadRs 50.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 2.10 lakh-
On-site expenditure-Consultants FeesRs 2.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerVasudevan T S
Chartered AccountantCA Saurabh Srivastava

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed161

As listed on the registration, under the names the promoter filed them with; the newest 80 of 161 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/301/PR/150324/006703 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annexure 70 Permission Layout PlanFile: Annexure 70 Permission Layout Plan.pdf6 Mar 2024
Approval LetterFile: Approval Letter.jpeg6 Mar 2024
Area DetailsFile: Area Details.pdf6 Mar 2024
C_L_UFile: C_L_U.pdf6 Mar 2024
Cash Flow StatementFile: Cash Flow Statement.pdf6 Mar 2024
CDP Plan009File: CDP Plan009.pdf6 Mar 2024
CFS 2020_21File: CFS 2020_21.pdf6 Mar 2024
CFS 2021_22File: CFS 2021_22.pdf6 Mar 2024
CFS-2022_23File: CFS-2022_23.pdf6 Mar 2024
Final Approval LetterFile: Final Approval Letter.pdf6 Mar 2024
Gazette Jan 27 2009File: Gazette Jan 27 2009.pdf6 Mar 2024
Inventory DetailsFile: Inventory Details.pdf6 Mar 2024
Types of InventoryFile: Types of Inventory.pdf6 Mar 2024
EndorsementFile: Endorsement.jpeg6 Mar 2024
Directors Report for the Year 2022-23File: A2 Directors report.pdf15 Feb 2024
Form B AffidavitFile: Form B Affidavit.pdf15 Feb 2024
Relinquishment Deed for Roads and ParksFile: Phase 2 - Layout Relinquishment Deed Park & Road.pdf15 Feb 2024
CDP LetterFile: CDP Plan009.pdf15 Feb 2024
Detailed Cost Certificate by the engineerFile: A26 Detailed cost certificate.pdf15 Feb 2024
Norarized Section 3(1) AffidavitFile: Notarized Sec 3(1) Affidavit.pdf15 Feb 2024
Proforma Agreement for SaleFile: Agreement for sale.pdf15 Feb 2024
Model Allotment LetterFile: allotment letter.pdf15 Feb 2024
Engineer Completion CertificateFile: Engineer Certificate of completion.pdf15 Feb 2024
Self-attested Sold and Unsold plots detailsFile: Signed Sold and Unslod RERA.pdf15 Feb 2024
Reply LetterFile: RERA Reply Letter.pdf19 Dec 2023
Annexure 1File: A1 BS.pdf19 Dec 2023
Annexure 2File: A2 Directors report.pdf19 Dec 2023
Annexure 3File: A3 No litigation affidavit.pdf19 Dec 2023
Annexure 4File: A4 Form_B Affidivit.pdf19 Dec 2023
Annexure 5File: A5 Sy No 54 bar 8 RTC.pdf19 Dec 2023
Annexure 6File: A6 Village Map 54-8.pdf19 Dec 2023
Annexure 7File: A7 Sale deeds- Bangalore Regency 54 bar 8.pdf19 Dec 2023
Annexure 8File: A8 Sy no 71-Sale deed Favour of Bangalore.pdf19 Dec 2023
Annexure 9File: A9 Sy no 72 Bar 2-Sale deed Favour of Bangalore.pdf19 Dec 2023
Annexure 10File: A10 EC Copies For All Sy Nos.pdf19 Dec 2023
Annexure 11File: A11 Guidance Value certificate.pdf19 Dec 2023
Annexure 12File: A12 Hissa Phody For - Sy No 54 Bar 8.pdf19 Dec 2023
Annexure 13File: A13 Hissa Phody For - Sy No 63 Bar 4.pdf19 Dec 2023
Annexure 14File: A14 Hissa Phody For - Sy No 72 Bar 1.pdf19 Dec 2023
Annexure 15File: A15 Hissa Phody For - Sy No 72 Bar 2.pdf19 Dec 2023
Annexure 16File: A16 Hissa or Mula Phody For - Sy No 71.pdf19 Dec 2023
Annexure 17File: A17 Hissa or Mula Phody For - Sy No 83.pdf19 Dec 2023
Annexure 18File: A18 Title deed Sy no 54 bar 8.pdf19 Dec 2023
Annexure 19File: A19 Plot wise area breakup.pdf19 Dec 2023
Annexure 20File: A20 Individual Plot details.pdf19 Dec 2023
Annexure 21File: A21 Layout Relinquishment Deed.pdf19 Dec 2023
Annexure 22File: A22 Completion certificate.pdf19 Dec 2023
Annexure 23File: A23 Horticulture Department NOC for the development of Park.pdf19 Dec 2023
Annexure 24File: A24 Village map showing the Site.pdf19 Dec 2023
Annexure 25File: A25 Chartered Engineer Certifcate.pdf19 Dec 2023
Annexure 26File: A26 Detailed cost certificate.pdf19 Dec 2023
Annexure 27File: A27 Specfification Certificate.pdf19 Dec 2023
Annexure 28File: A28 Agreement of Sale Proforma.pdf19 Dec 2023
Annexure 29File: A29 Proforma Allotment letter.pdf19 Dec 2023
Annexure 30File: A30 BESCOM NOC.pdf19 Dec 2023
Annexure 31File: A31 STP and sewage plan.pdf19 Dec 2023
Annexure 32File: A32 Self attested land cost calculation sheet.pdf19 Dec 2023
RTC, survey 54/8-
Mutation, survey 54/8-
Encumbrance Certificate, survey 54/8-
Conversion/Alienation Order, survey 54/8-
Sale/Title/Gift Deed, survey 54/8-
JDA, survey 54/8-
Khatha, survey 54/8-
RTC, survey 63/4-
Mutation, survey 63/4-
Encumbrance Certificate, survey 63/4-
Conversion/Alienation Order, survey 63/4-
Sale/Title/Gift Deed, survey 63/4-
JDA, survey 63/4-
Khatha, survey 63/4-
RTC, survey 71-
Mutation, survey 71-
Encumbrance Certificate, survey 71-
Conversion/Alienation Order, survey 71-
Sale/Title/Gift Deed, survey 71-
JDA, survey 71-
Khatha, survey 71-
RTC, survey 72/1-
Mutation, survey 72/1-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
CANTERBURY MEADOWS - Phase 1Canterbury Meadows, Dandudasakodigehalli Village, Toobagere Hobli, Doddaballapura TalukCompleted-No date filed

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Canterbury Meadows Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

Builder: Arunapanchami Estates Private Limited

Arunapanchami Estates Private Limited has 2 registrations on RERA Karnataka, including Canterbury Meadows Phase 2 and CANTERBURRY MEADOWS. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Canterbury Meadows Phase 2 is delayed beyond 30 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Canterbury Meadows Phase 2?

The registered promoter entity is Arunapanchami Estates Private Limited, a company as per the filing. Its CIN U45203KA2013PTC070747 and GSTIN 29AALCA9860C1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Canterbury Meadows Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Canterbury Meadows Phase 2?

The professionals named in the filing: Engineer: Vasudevan T S; Chartered Accountant: CA Saurabh Srivastava. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Canterbury Meadows Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Canterbury Meadows Phase 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Canterbury Meadows Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.