ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / BLOSSOM

Registration approved No litigation declared Residential/Group Housing project

BLOSSOM

By BRUHASPATI BUILDERS LLP

RG-KA-32924 · RERA PRM/KA/RERA/1251/310/PR/180722/005078 · Last updated on RERA Karnataka portal: 1 Jul 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Nov 2024Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 141 documents Report an error

BLOSSOM is a Residential/Group Housing project by BRUHASPATI BUILDERS LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/180722/005078 on 18 Jul 2022. Possession is promised by 12 Nov 2024. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameBLOSSOM
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 562109
  • Pincode562109
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/180722/005078
  • ReraGenie IDRG-KA-32924

Builder

  • NameBRUHASPATI BUILDERS LLP
  • Entity typePartnership Firm
  • GSTIN29AAYFB1195PIZE
  • Authorized SignatoryJayanth Naga B S

Key dates

this monthRegisteredJul 2022First promiseNov 2023Revised toNov 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Jul 2022
  • Promised completion12 Nov 2024
  • Revised completionRevised to 12 Nov 2024 (originally 12 Nov 2023)
  • Buildings1 building record
  • Documents filed141 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 1---32032

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 1 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 1 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,196 sq m
Named landowners3
LandownerVillageDistrict
BRUHASPATI BUILDERS LLP--
BRUHASPATI BUILDERS LLP--
BRUHASPATI BUILDERS LLP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.38 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 6.43 cr-
Administrative CostRs 82.15 lakh-
Payment of taxesRs 11.10 lakh-
Architect , Engineer Consultant FeesRs 1.64 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPurohit and Associates
EngineerIndiresh and Associates
Chartered AccountantK M Narasimha Murthy

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/240202/005078Nov 2023 → Nov 2024

Reason as filed by the promoterApplied for modification

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed141

As listed on the registration, under the names the promoter filed them with; the newest 80 of 141 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/180722/005078 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
AOSFile: Agreement of Sale Proforma.pdf1 Jul 2022
site plan and demarcationFile: BLOSSOM - Demarcation Location Site Plan.pdf9 Jun 2022
K Bommaraju to BS NagarajuFile: Hejjala Sy No 8 Div P3 Sale Deed from K Bommaraju to BSN.pdf9 Jun 2022
Ashwathaiah to P NagarajuFile: Hejjala SyNo8 Div 13 Sale Deed from Ashwathaiah to P Nagaraju.pdf9 Jun 2022
BS NAGARAJU to IDPLFile: Hejjala SyNo8 Div P3 and 8 Div P5 Sale Deed - BSN to IDPL.pdf9 Jun 2022
Lingaiah to BSNAGARAJUFile: Hejjala SyNo8 Div P5 Sale Deed from Lingaiah to BSN.pdf9 Jun 2022
LOCATION DEMARCATIONFile: Location and Demarcation Drawing.pdf9 Jun 2022
SEWAGE LINEDEMARCATIONFile: SEWAGE demarcationDrawing.pdf9 Jun 2022
P Nagaraju to IDPL-8/13File: SyNo 8 Div 13Sale Deed from P Nagaraju to IDPL.pdf9 Jun 2022
QUERY REPLYFile: QUERY REPLY.pdf9 Jun 2022
conversion orderFile: 8-13 Conversion order.pdf16 May 2022
conversion orderFile: 8p3 Converstion order.pdf16 May 2022
EC 8-13File: 8-13 EC til date.pdf16 May 2022
EC 8/P3File: 8P3 EC.pdf16 May 2022
EC 8/P3File: 8P3 Till date.pdf16 May 2022
EC 8/P5File: 8P5 EC.pdf16 May 2022
EC 8/P5File: 8P5 Till date.pdf16 May 2022
FINANCIALS 2020-2021File: BBLLP Financials FY 2020-21.pdf16 May 2022
FINANCIALS 2021-2022File: BBLLP Provisional FY 2021-22.pdf16 May 2022
ADVOCATE SEARCH REPORTFile: Advocate Search Report.pdf16 May 2022
AOSFile: Agreement of Sale Proforma.pdf16 May 2022
AMALGAMATION SANCTION ORDERFile: Amagalation order.pdf16 May 2022
AMALGAMATION SANCTION PLANFile: Amalgamation Santion Plan - 321 & 322.PDF16 May 2022
BESCOM NOCFile: BESCOM NOC.pdf16 May 2022
BMRD SANCTION PLANFile: Blossom - BMRDA Sanction Plan.jpg16 May 2022
BWSSB NOCFile: BWSSB Water NOC.pdf16 May 2022
CANCELLED CHEQUEFile: CANCELLED CHEQUE.pdf16 May 2022
HEJJALA VILLAGE MAPFile: Hejjala Village map.pdf16 May 2022
LAND DEMARCATIONFile: LAND DEMARCATION.png16 May 2022
MULTI PLOT LAYOUT PLANFile: Multi plot layout plan.PDF16 May 2022
MULTI PLOT LAYOUT PLANFile: Multi plot layout plan.PDF16 May 2022
SECTION 3 AFFIDAVITFile: Section 3 affidavit.pdf16 May 2022
SANCTION PLANFile: Blossom - BMRDA Sanction Plan.jpg16 May 2022
STPFile: STP.pdf16 May 2022
RTC, survey 8/13-
Mutation, survey 8/13-
Encumbrance Certificate, survey 8/13-
Conversion/Alienation Order, survey 8/13-
Sale/Title/Gift Deed, survey 8/13-
Khatha, survey 8/13-
RTC, survey 8/P3-
Mutation, survey 8/P3-
Encumbrance Certificate, survey 8/P3-
Conversion/Alienation Order, survey 8/P3-
Sale/Title/Gift Deed, survey 8/P3-
Khatha, survey 8/P3-
RTC, survey 8/P5-
Mutation, survey 8/P5-
Encumbrance Certificate, survey 8/P5-
Conversion/Alienation Order, survey 8/P5-
Sale/Title/Gift Deed, survey 8/P5-
Khatha, survey 8/P5-
Registration CertificateFile: Certificate of LLP Incorporation.pdf-
Partnership DeedFile: Registered Partnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect certificate.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 CA Certificate.pdf-
Balance Sheet 2020 - 2021File: Balance sheet.pdf-
Balance Sheet 2019 - 2020File: FINANCIALS.pdf-
Balance Sheet 2018 - 2019File: FINANCIALS.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit and loss.pdf-
Audited Profit and Loss Statement 2019 - 2020File: FINANCIALS.pdf-
Audited Profit and Loss Statement 2018 - 2019File: FINANCIALS.pdf-
Director's Report 2019 - 2020File: FINANCIALS.pdf-
Director's Report 2018 - 2019File: FINANCIALS.pdf-
Cash Flow Statement 2020 - 2021File: Cashflow statement.pdf-
Cash Flow Statement 2019 - 2020File: FINANCIALS.pdf-
Auditor's Report 2020 - 2021File: Auditor report.pdf-
Auditor's Report 2019 - 2020File: FINANCIALS.pdf-
Auditor's Report 2018 - 2019File: FINANCIALS.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: FINANCIALS.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: FINANCIALS.pdf-
Approval letter-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep BLOSSOM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmBLOSSOMOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: BRUHASPATI BUILDERS LLP

BRUHASPATI BUILDERS LLP has 1 registration on RERA Karnataka, including BLOSSOM. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if BLOSSOM is delayed beyond 12 Nov 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of BLOSSOM?

The registered promoter entity is BRUHASPATI BUILDERS LLP, a partnership firm as per the filing. Its GSTIN 29AAYFB1195PIZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in BLOSSOM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BLOSSOM?

The professionals named in the filing: Architect: Purohit and Associates; Engineer: Indiresh and Associates; Chartered Accountant: K M Narasimha Murthy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BLOSSOM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BLOSSOM. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BLOSSOM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.