Home / Browse projects / Ahmedabad, Gujarat / Bileshwar Residency
Bileshwar Residency
RG-GJ-31409 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00748/171117 · Last updated on GujRERA portal: 6 Jul 2019
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
- Separate project account declared
Saved.
Bileshwar Residency is a Residential/Group Housing project by Uma Developers in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00748/171117 on 17 Nov 2017. Possession is promised by 31 Dec 2018. 33 of the 55 units on this registration are recorded sold or booked, and 440 of 440 construction stages are filed complete.
At a glance
Project
- NameBileshwar Residency
- TypeResidential/Group Housing
- Location
- Bileshwar Residency Bh Vangi Restaurant and panchvati party plot
- Bareja Cross road Bareja
- Bareja
- Ahmedabad City
- Ahmedabad
- 382425
- Pincode382425
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00748/171117
- ReraGenie IDRG-GJ-31409
Builder
- NameUma Developers
- Entity typePARTNERSHIP FIRM
- Other registrations12 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Dec 2018
- Registered on17 Nov 2017
- Promised completion31 Dec 2018
- Revised completionNone
- Buildings55 building records
- Documents filed91 files
Current status
Figures as on 6 Jul 2019, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 | - | - | - | 1 | 0 | 1 |
| 2 | - | - | - | 1 | 0 | 1 |
| 3 | - | - | - | 1 | 0 | 1 |
| 4 | - | - | - | 1 | 0 | 1 |
| 5 | - | - | - | 1 | 0 | 1 |
| 6 | - | - | - | 1 | 0 | 1 |
| 7 | - | - | - | 1 | 0 | 1 |
| 8 | - | - | - | 1 | 0 | 1 |
| 9 | - | - | - | 1 | 0 | 1 |
| 10 | - | - | - | 1 | 0 | 1 |
| 11 | - | - | - | 1 | 0 | 1 |
| 12 | - | - | - | 1 | 0 | 1 |
| 13 | - | - | - | 1 | 0 | 1 |
| 14 | - | - | - | 1 | 0 | 1 |
| 15 | - | - | - | 1 | 0 | 1 |
| 16 | - | - | - | 1 | 0 | 1 |
| 17 | - | - | - | 1 | 0 | 1 |
| 18 | - | - | - | 1 | 0 | 1 |
| 19 | - | - | - | 1 | 0 | 1 |
| 20 | - | - | - | 1 | 0 | 1 |
| 21 | - | - | - | 1 | 0 | 1 |
| 22 | - | - | - | 1 | 0 | 1 |
| 23 | - | - | - | 1 | 0 | 1 |
| 24 | - | - | - | 1 | 0 | 1 |
| 25 | - | - | - | 1 | 0 | 1 |
| 26 | - | - | - | 1 | 0 | 1 |
| 27 | - | - | - | 1 | 0 | 1 |
| 28 | - | - | - | 1 | 0 | 1 |
| 29 | - | - | - | 1 | 0 | 1 |
| 30 | - | - | - | 1 | 0 | 1 |
| 31 | - | - | - | 1 | 0 | 1 |
| 32 | - | - | - | 1 | 0 | 1 |
| 33 | - | - | - | 1 | 0 | 1 |
| 34 | - | - | - | 1 | 0 | 1 |
| 35 | - | - | - | 1 | 0 | 1 |
| 36 | - | - | - | 1 | 0 | 1 |
| 37 | - | - | - | 1 | 0 | 1 |
| 38 | - | - | - | 1 | 0 | 1 |
| 39 | - | - | - | 1 | 0 | 1 |
| 40 | - | - | - | 1 | 0 | 1 |
| 41 | - | - | - | 1 | 0 | 1 |
| 42 | - | - | - | 1 | 0 | 1 |
| 43 | - | - | - | 1 | 0 | 1 |
| 44 | - | - | - | 1 | 0 | 1 |
| 45 | - | - | - | 1 | 0 | 1 |
| 46 | - | - | - | 1 | 0 | 1 |
| 47 | - | - | - | 1 | 0 | 1 |
| 48 | - | - | - | 1 | 0 | 1 |
| 49 | - | - | - | 1 | 0 | 1 |
| 50 | - | - | - | 1 | 0 | 1 |
| 51 | - | - | - | 1 | 0 | 1 |
| 52 | - | - | - | 1 | 0 | 1 |
| 53 | - | - | - | 1 | 0 | 1 |
| 54 | - | - | - | 1 | 0 | 1 |
| 55 | - | - | - | 1 | 0 | 1 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building20
As on 6 Jul 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 55 buildings; the table lists the first 20.
440 of 440 construction stages are filed complete across 55 buildings.
1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
6100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
7100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
8100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
9100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
10100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
11100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
12100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
13100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
14100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
15100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
16100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
17100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
18100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
19100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
20100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 6 Jul 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 100% |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 100% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| 1 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 2 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 3 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 4 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 5 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 6 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 7 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 8 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 9 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 10 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 11 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
| 12 | NA | Rs 10.20 lakh | Rs 10.20 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Manoj Kumar Lalji Bhai Kanani |
| Engineer | Ketan Kumar Kanubhai Patel |
Documents filed91
As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00748/171117 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 6 Jul 2019 |
| Engineer's certificate (Form 2) | 6 Jul 2019 |
| Accountant's certificate (Form 3) | 6 Jul 2019 |
| Site photograph, 1 | 6 Jul 2019 |
| Site photograph, 2 | 6 Jul 2019 |
| Site photograph, 3 | 6 Jul 2019 |
| Site photograph, 4 | 6 Jul 2019 |
| Site photograph, 5 | 6 Jul 2019 |
| Site photograph, 6 | 6 Jul 2019 |
| Site photograph, 7 | 6 Jul 2019 |
| Site photograph, 8 | 6 Jul 2019 |
| Site photograph, 9 | 6 Jul 2019 |
| Site photograph, 10 | 6 Jul 2019 |
| Site photograph, 11 | 6 Jul 2019 |
| Site photograph, 12 | 6 Jul 2019 |
| Site photograph, 13 | 6 Jul 2019 |
| Site photograph, 14 | 6 Jul 2019 |
| Site photograph, 15 | 6 Jul 2019 |
| Site photograph, 16 | 6 Jul 2019 |
| Site photograph, 17 | 6 Jul 2019 |
| Site photograph, 18 | 6 Jul 2019 |
| Site photograph, 19 | 6 Jul 2019 |
| Site photograph, 20 | 6 Jul 2019 |
| Site photograph, 21 | 6 Jul 2019 |
| Site photograph, 22 | 6 Jul 2019 |
| Site photograph, 23 | 6 Jul 2019 |
| Site photograph, 24 | 6 Jul 2019 |
| Site photograph, 25 | 6 Jul 2019 |
| Site photograph, 26 | 6 Jul 2019 |
| Site photograph, 27 | 6 Jul 2019 |
| Site photograph, 28 | 6 Jul 2019 |
| Site photograph, 29 | 6 Jul 2019 |
| Site photograph, 30 | 6 Jul 2019 |
| Site photograph, 31 | 6 Jul 2019 |
| Site photograph, 32 | 6 Jul 2019 |
| Site photograph, 33 | 6 Jul 2019 |
| Site photograph, 34 | 6 Jul 2019 |
| Site photograph, 35 | 6 Jul 2019 |
| Site photograph, 36 | 6 Jul 2019 |
| Site photograph, 37 | 6 Jul 2019 |
| Site photograph, 38 | 6 Jul 2019 |
| Site photograph, 39 | 6 Jul 2019 |
| Site photograph, 40 | 6 Jul 2019 |
| Site photograph, 41 | 6 Jul 2019 |
| Site photograph, 42 | 6 Jul 2019 |
| Site photograph, 43 | 6 Jul 2019 |
| Site photograph, 44 | 6 Jul 2019 |
| Site photograph, 45 | 6 Jul 2019 |
| Site photograph, 46 | 6 Jul 2019 |
| Site photograph, 47 | 6 Jul 2019 |
| Site photograph, 48 | 6 Jul 2019 |
| Site photograph, 49 | 6 Jul 2019 |
| Site photograph, 50 | 6 Jul 2019 |
| Site photograph, 51 | 6 Jul 2019 |
| Site photograph, 52 | 6 Jul 2019 |
| Site photograph, 53 | 6 Jul 2019 |
| Site photograph, 54 | 6 Jul 2019 |
| Site photograph, 55 | 6 Jul 2019 |
| RERA registration certificate | 17 Nov 2017 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ahmedabad
Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.
Keep Bileshwar Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bareja5,400+ in Ahmedabad
Filed coordinates, straight-line distance. 22 registered projects within 2 km.
OMKAR RESIDENCY
MAHAVIR CORPORATION
ASTHAVINAYAK RESIDENCY
SHREE ASTHAVINAYAK DEVELOPERS
AANGAN BUNGLOWS
AARADHYA INFRA
Hari Nandan Residency
Madhuben Dhanjibhai Patel Proprietor of Ji
AKSHAR VILLA
NEELKANTH GROUP
Aaradhana Residency - 2
Prerna Developers
See every Ahmedabad project, with the district possession charts
Builder: Uma Developers
UMA DEVELOPERS has 13 registrations on GujRERA, including UMA DARSHAN and Bileshwar Residency. Read the full track record. See more projects on the Ahmedabad district page.
Frequently asked questions
What are my rights if Bileshwar Residency is delayed beyond 31 Dec 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Bileshwar Residency?
The registered promoter entity is Uma Developers, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Bileshwar Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Bileshwar Residency?
The professionals named in the filing: Architect: Manoj Kumar Lalji Bhai Kanani; Engineer: Ketan Kumar Kanubhai Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Bileshwar Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback