Home / Browse projects / Ahmedabad, Gujarat / AKSHAR VILLA

Valid until 30 Apr 2029 Residential/Group Housing project

AKSHAR VILLA

By NEELKANTH GROUP

RG-GJ-49758 · RERA PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Urban Development Authority/RAA16196/091225/311228 · Last updated on GujRERA portal: 9 Dec 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
30 of 135Construction stages doneacross 15 buildings; furthest along: Internal walls, 20%
55 of 55Units unsoldnot recorded sold or booked
Jump to the 57 documents Report an error

AKSHAR VILLA is a Residential/Group Housing project by NEELKANTH GROUP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Urban Development Authority/RAA16196/091225/311228 on 9 Dec 2025. Possession is promised by 30 Apr 2029. 0 of the 55 units on this registration are recorded sold or booked, and 30 of 135 construction stages are filed complete.

At a glance

Project

  • NameAKSHAR VILLA
  • TypeResidential/Group Housing
  • Location
    • AKSHAR VILLA NR. OMKAR ANANTA RASAM RESIDENCY VAIBHAV LAXMI PARISAR
    • BAREJA
    • Daskroi
    • Ahmedabad
    • 382425
  • Pincode382425
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Urban Development Authority/RAA16196/091225/311228
  • ReraGenie IDRG-GJ-49758

Builder

  • NameNEELKANTH GROUP
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2025PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on9 Dec 2025
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings15 building records
  • Documents filed57 files

Current status

0%0 of 55 units booked
80.0%Of the estimated cost spent so far

Figures as on 9 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---101
B---11011
C---101
D---101
E---11011
F---101
G---101
H---11011
J---101
I---101
K---606
L---101
M---101
N---606
O---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building15

As on 9 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 135 construction stages are filed complete across 15 buildings. The stage furthest along is Internal walls, at 20%.

A33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
B33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
C33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
D33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
E33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
F33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
G33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
H33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
J33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
I33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
K33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
L33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
M33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
N33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
O33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%

Progress on shared amenities19

As on 9 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,767 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 13.46 cr
Cost incurredRs 10.77 cr
Spent of the estimate80.0%
BuildingWingEstimatedIncurred
ANARs 89.76 lakhRs 71.81 lakh
BNARs 89.76 lakhRs 71.81 lakh
CNARs 89.76 lakhRs 71.81 lakh
DNARs 89.76 lakhRs 71.81 lakh
ENARs 89.76 lakhRs 71.81 lakh
FNARs 89.76 lakhRs 71.81 lakh
GNARs 89.76 lakhRs 71.81 lakh
HNARs 89.76 lakhRs 71.81 lakh
JNARs 89.76 lakhRs 71.81 lakh
INARs 89.76 lakhRs 71.81 lakh
KNARs 89.76 lakhRs 71.81 lakh
LNARs 89.76 lakhRs 71.81 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectViral Patel
EngineerKARAN BHARATKUMAR RAVAL

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Urban Development Authority/RAA16196/091225/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate9 Dec 2025
Accountant's certificate (Form 3)3 Dec 2025
Architect's certificate (Form 1)2 Dec 2025
Engineer's certificate (Form 2)2 Dec 2025
Engineer's certificate annexure2 Dec 2025
Site photograph, A2 Dec 2025
Site photograph, B2 Dec 2025
Site photograph, C2 Dec 2025
Site photograph, D2 Dec 2025
Site photograph, E2 Dec 2025
Site photograph, F2 Dec 2025
Site photograph, G2 Dec 2025
Site photograph, H2 Dec 2025
Site photograph, J2 Dec 2025
Site photograph, I2 Dec 2025
Site photograph, K2 Dec 2025
Site photograph, L2 Dec 2025
Site photograph, M2 Dec 2025
Site photograph, N2 Dec 2025
Site photograph, O2 Dec 2025
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

0%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep AKSHAR VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near BAREJA5,400+ in Ahmedabad

2 kmAKSHAR VILLAOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: NEELKANTH GROUP

NEELKANTH GROUP has 1 registration on GujRERA, including AKSHAR VILLA. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if AKSHAR VILLA is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AKSHAR VILLA?

The registered promoter entity is NEELKANTH GROUP, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AKSHAR VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AKSHAR VILLA?

The professionals named in the filing: Architect: Viral Patel; Engineer: KARAN BHARATKUMAR RAVAL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AKSHAR VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AKSHAR VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AKSHAR VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.