ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / BANSARI LUXURIA

Valid until 30 Mar 2025 Mixed Development project

BANSARI LUXURIA

By AMAR GROUP

RG-GJ-80644 · RERA PR/GJ/SURAT/KAMREJ/SUDA/MAA06592/080120 · Last updated on GujRERA portal: 2 Jan 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2025Possession promisedno revision filed
35 of 36Construction stages doneacross 4 buildings; furthest along: External plumbing and external plaster, 90%
109 of 254Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

BANSARI LUXURIA is a Mixed Development project by AMAR GROUP in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/KAMREJ/SUDA/MAA06592/080120 on 8 Jan 2020. Possession is promised by 30 Mar 2025. 145 of the 254 units on this registration are recorded sold or booked, and 35 of 36 construction stages are filed complete.

At a glance

Project

  • NameBANSARI LUXURIA
  • TypeMixed Development
  • Location
    • BLOCK NO. 347-348
    • F.P. NO. 137-138
    • T.P.S. NO. 48 (KHOLVAD)
    • Kolvad
    • Kamrej
    • Surat
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/KAMREJ/SUDA/MAA06592/080120
  • ReraGenie IDRG-GJ-80644

Builder

  • NameAMAR GROUP
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2020PromisedMar 2025

Key facts

Registration and timeline

  • StatusValid until 30 Mar 2025
  • Registered on8 Jan 2020
  • Promised completion30 Mar 2025
  • Revised completionNone
  • Buildings4 building records
  • Documents filed40 files

Current status

57%145 of 254 units booked
113.1%Of the estimated cost spent so far

Figures as on 2 Jan 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-B---561571
C-D---56056
E-F---56056
G-H---561571

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 2 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

35 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

A-B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C-D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E-F99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G-H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 2 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes50%
Water conservation, rain water harvestingYes50%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes100%
Plinth protectionYes100%
Water tankYes100%
Other requirementsYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,279 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 13.18 cr
Cost incurredRs 14.92 cr
Spent of the estimate113.14%
BuildingWingEstimatedIncurred
A-BNARs 3.30 crRs 3.73 cr
C-DNARs 3.30 crRs 3.73 cr
E-FNARs 3.30 crRs 3.73 cr
G-HNARs 3.30 crRs 3.73 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHVINBHAI R DOBARIA
EngineerMITULKUMAR B PATEL

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/KAMREJ/SUDA/MAA06592/080120 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Site photograph, E-F2 Jan 2025
Site photograph, G-H2 Jan 2025
Engineer's certificate (Form 2)27 Oct 2023
Engineer's certificate annexure27 Oct 2023
RERA registration certificate8 Jan 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

57%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep BANSARI LUXURIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kolvad2,600+ in Surat

2 kmBANSARI LUXURIAOther 69Dot size: filed unitsN

Filed coordinates, straight-line distance. 69 registered projects within 2 km.

Builder: AMAR GROUP

AMAR GROUP has 1 registration on GujRERA, including BANSARI LUXURIA. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if BANSARI LUXURIA is delayed beyond 30 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of BANSARI LUXURIA?

The registered promoter entity is AMAR GROUP, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in BANSARI LUXURIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BANSARI LUXURIA?

The professionals named in the filing: Architect: ASHVINBHAI R DOBARIA; Engineer: MITULKUMAR B PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BANSARI LUXURIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BANSARI LUXURIA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BANSARI LUXURIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.