Valid until 31 Dec 2020 Residential/Group Housing project

BAAGBAN RESIDENCY

By Altair Infraspace Private Limited

RG-GJ-30814 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00974/EX2/201120 · Last updated on GujRERA portal: 19 Oct 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Separate project account declared
Dec 2020Possession promisedmoved 21 months from the original
30 of 30Construction stages doneacross 3 buildings; every applicable stage filed complete
31 of 210Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

BAAGBAN RESIDENCY is a Residential/Group Housing project by Altair Infraspace Private Limited in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00974/EX2/201120 on 11 Dec 2017. Possession is promised by 31 Dec 2020. The completion date has moved by 21 months from the original filing. 179 of the 210 units on this registration are recorded sold or booked, and 30 of 30 construction stages are filed complete.

At a glance

Project

  • NameBAAGBAN RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • BAAGBAN (OLD ANANT MILL COMPOUND)
    • AJIT MILL CROSS ROAD
    • RAKHIYAL
    • Rakhiyal
    • Ahmedabad City
    • Ahmedabad
    • 380023
  • Pincode380023
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00974/EX2/201120
  • ReraGenie IDRG-GJ-30814

Builder

  • NameAltair Infraspace Private Limited
  • Entity typeCOMPANY
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2017First promiseMar 2019Revised toDec 2020

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2020
  • Registered on11 Dec 2017
  • Promised completion31 Dec 2020
  • Revised completionRevised to 31 Dec 2020 (originally 31 Mar 2019)
  • Buildings3 building records
  • Documents filed41 files

Current status

85%179 of 210 units booked
100.0%Of the estimated cost spent so far

Figures as on 19 Oct 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
R---60060
S---60060
P+Q---90090

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 19 Oct 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 30 construction stages are filed complete across 3 buildings.

R100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
S100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
P+Q100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 19 Oct 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,369 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 21.00 cr
Cost incurredRs 21.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
RNARs 7.00 crRs 7.00 cr
SNARs 7.00 crRs 7.00 cr
P+QNARs 7.00 crRs 7.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAKAR ASSOCIATES
EngineerSAKAR ASSOCIATES

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00974/EX1/100419Applied Mar 2019; approved Apr 2019
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00974/EX2/201120Applied Oct 2020; approved Nov 2020

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA00974/EX2/201120 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)19 Oct 2020
Site photograph, R19 Oct 2020
Site photograph, S19 Oct 2020
Site photograph, P+Q19 Oct 2020
Site photograph, P+Q19 Oct 2020
Accountant's certificate (Form 3)7 Oct 2019
RERA registration certificate11 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Engineer's certificate (Form 2)-
Engineer's certificate annexure-

How this compares with Ahmedabad

85%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 21 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep BAAGBAN RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rakhiyal5,400+ in Ahmedabad

2 kmBAAGBAN RESIDENCYOther 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: Altair Infraspace Private Limited

Altair Infraspace Private Limited has 2 registrations on GujRERA, including BAAGBAN RESIDENCY and Baagban Elite (Block H+I and J+K). Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if BAAGBAN RESIDENCY is delayed beyond 31 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of BAAGBAN RESIDENCY?

The registered promoter entity is Altair Infraspace Private Limited, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in BAAGBAN RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BAAGBAN RESIDENCY?

The professionals named in the filing: Architect: SAKAR ASSOCIATES; Engineer: SAKAR ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BAAGBAN RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BAAGBAN RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BAAGBAN RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.