Home / Browse projects / Ahmedabad, Gujarat / AARAT INDUSTRIAL ESTATE

Valid until 31 Mar 2020 Commercial project

AARAT INDUSTRIAL ESTATE

By GURUKRUPA PROCONS PRIVATE LIMITED

RG-GJ-94031 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA03228/EX1/120419 · Last updated on GujRERA portal: 28 Jun 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2020Possession promisedmoved 12 months from the original
80 of 80Construction stages doneacross 10 buildings; every applicable stage filed complete
121 of 265Units unsoldnot recorded sold or booked
Jump to the 47 documents Report an error

AARAT INDUSTRIAL ESTATE is a Commercial project by GURUKRUPA PROCONS PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA03228/EX1/120419 on 24 Jul 2018. Possession is promised by 31 Mar 2020. The completion date has moved by 12 months from the original filing. 144 of the 265 units on this registration are recorded sold or booked, and 80 of 80 construction stages are filed complete.

At a glance

Project

  • NameAARAT INDUSTRIAL ESTATE
  • TypeCommercial
  • Location
    • SURVEY NO 311/3 TP SCHEME NO 10 FP 2
    • RAKHIAYL
    • NR PANNA ESTATE
    • Rakhial
    • Ahmedabad City
    • Ahmedabad
    • 380023
  • Pincode380023
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA03228/EX1/120419
  • ReraGenie IDRG-GJ-94031

Builder

  • NameGURUKRUPA PROCONS PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredJul 2018First promiseMar 2019Revised toMar 2020

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2020
  • Registered on24 Jul 2018
  • Promised completion31 Mar 2020
  • Revised completionRevised to 31 Mar 2020 (originally 31 Mar 2019)
  • Buildings10 building records
  • Documents filed47 files

Current status

54%144 of 265 units booked
100.0%Of the estimated cost spent so far

Figures as on 28 Jun 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---04855
B---0014
C---0014
D---0014
E---0014
F---007
G---0011
H---0022
I---0022
J---08192

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building10

As on 28 Jun 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

80 of 80 construction stages are filed complete across 10 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
I100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
J100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 28 Jun 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,516 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 8.55 cr
Cost incurredRs 8.55 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 85.50 lakhRs 85.50 lakh
BNARs 85.50 lakhRs 85.50 lakh
CNARs 85.50 lakhRs 85.50 lakh
DNARs 85.50 lakhRs 85.50 lakh
ENARs 85.50 lakhRs 85.50 lakh
FNARs 85.50 lakhRs 85.50 lakh
GNARs 85.50 lakhRs 85.50 lakh
HNARs 85.50 lakhRs 85.50 lakh
INARs 85.50 lakhRs 85.50 lakh
JNARs 85.50 lakhRs 85.50 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPATEL ANKUR KUMAR C
EngineerDIGANT MUKUNDBHAI SHAH

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA03228/EX1/120419Applied Mar 2019; approved Apr 2019

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA03228/EX1/120419 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)28 Jun 2020
Architect's certificate (Form 1)27 Jun 2020
Engineer's certificate (Form 2)27 Jun 2020
Engineer's certificate annexure27 Jun 2020
Site photograph, A27 Jun 2020
Site photograph, B27 Jun 2020
Site photograph, C27 Jun 2020
Site photograph, D27 Jun 2020
Site photograph, E27 Jun 2020
Site photograph, F27 Jun 2020
Site photograph, G27 Jun 2020
Site photograph, H27 Jun 2020
Site photograph, I27 Jun 2020
Site photograph, J27 Jun 2020
RERA registration certificate24 Jul 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

54%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep AARAT INDUSTRIAL ESTATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rakhial5,400+ in Ahmedabad

2 kmAARAT INDUSTRIAL ESTATEOther 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: GURUKRUPA PROCONS PRIVATE LIMITED

GURUKRUPA PROCONS PRIVATE LIMITED has 1 registration on GujRERA, including AARAT INDUSTRIAL ESTATE. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if AARAT INDUSTRIAL ESTATE is delayed beyond 31 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AARAT INDUSTRIAL ESTATE?

The registered promoter entity is GURUKRUPA PROCONS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AARAT INDUSTRIAL ESTATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AARAT INDUSTRIAL ESTATE?

The professionals named in the filing: Architect: PATEL ANKUR KUMAR C; Engineer: DIGANT MUKUNDBHAI SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARAT INDUSTRIAL ESTATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARAT INDUSTRIAL ESTATE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARAT INDUSTRIAL ESTATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.