Home / Browse projects / Surat, Gujarat / AVADH ERCOLE

Valid until 30 Apr 2029 Residential/Group Housing project

AVADH ERCOLE

By AVADH INFRABUILD

RG-GJ-62998 · RERA PR/GJ/SURAT/CHORASI/Surat Municipal Corporation/RAA10610/A1R/050526/311228 · Last updated on GujRERA portal: 22 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
105 of 135Construction stages doneacross 15 buildings; furthest along: Installation of lifts, 95%
112 of 371Units unsoldnot recorded sold or booked
Jump to the 58 documents Report an error

AVADH ERCOLE is a Residential/Group Housing project by AVADH INFRABUILD in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORASI/Surat Municipal Corporation/RAA10610/A1R/050526/311228 on 30 Aug 2022. Possession is promised by 30 Apr 2029. 259 of the 371 units on this registration are recorded sold or booked, and 105 of 135 construction stages are filed complete.

At a glance

Project

  • NameAVADH ERCOLE
  • TypeResidential/Group Housing
  • Location
    • T.P.S. NO: 26 (ABHVA)
    • F.P. NO: 84 + 85/1 + 92 + 93 + 94
    • O.P. NO : 84 + 85/1 + 92 + 93 + 94
    • BLOCK NO.394
    • 389
    • 393+395/1+
    • 395/2
    • 396 AT : ABHVA
    • TA : MAJURA
    • ...
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORASI/Surat Municipal Corporation/RAA10610/A1R/050526/311228
  • ReraGenie IDRG-GJ-62998

Builder

  • NameAVADH INFRABUILD
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2022PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on30 Aug 2022
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings15 building records
  • Documents filed58 files

Current status

70%259 of 371 units booked
96.9%Of the estimated cost spent so far

Figures as on 22 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C---22022
D+E---48048
F---34034
G---22022
H---22022
I---22022
J---22022
K---22022
L---22022
M---22022
N---22022
O---24024
P---22022
A---23023
B---22022

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building15

As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

105 of 135 construction stages are filed complete across 15 buildings. The stage furthest along is Installation of lifts, at 95%.

C94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
D+E94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
F94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
G94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
H94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
I94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
J94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
K94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
L94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
M94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
N94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
O94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
P94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
A94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
B94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes95%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsYes90%
Landscaping and tree plantingYes95%
Street lightingYes75%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes75%
Solid waste management and disposalYes50%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes95%
Fire fightingYes95%
Drinking water facilitiesYes95%
Emergency evacuationYes95%
Use of renewable energyNoNot applicable
SecurityYes50%
Letter boxYes95%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,039 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 300.00 cr
Cost incurredRs 290.60 cr
Spent of the estimate96.87%
BuildingWingEstimatedIncurred
D+ENARs 28.20 crRs 27.75 cr
FNARs 25.80 crRs 25.00 cr
KNARs 24.00 crRs 23.50 cr
PNARs 23.35 crRs 22.80 cr
BNARs 21.85 crRs 21.00 cr
CNARs 21.85 crRs 21.00 cr
ANARs 20.80 crRs 20.00 cr
HNARs 19.75 crRs 19.00 cr
GNARs 18.65 crRs 18.00 cr
INARs 18.55 crRs 18.00 cr
JNARs 18.30 crRs 18.00 cr
MNARs 14.90 crRs 14.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY RIDDHISHANKAR JOSHI
EngineerHARDIKBHAI CHIMANBHAI SORATHIYA

Documents filed58

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORASI/Surat Municipal Corporation/RAA10610/A1R/050526/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)22 Apr 2026
Engineer's certificate (Form 2)22 Apr 2026
Engineer's certificate annexure22 Apr 2026
Accountant's certificate (Form 3)22 Apr 2026
Site photograph, C22 Apr 2026
Site photograph, D+E22 Apr 2026
Site photograph, F22 Apr 2026
Site photograph, G22 Apr 2026
Site photograph, H22 Apr 2026
Site photograph, I22 Apr 2026
Site photograph, I22 Apr 2026
Site photograph, J22 Apr 2026
Site photograph, K22 Apr 2026
Site photograph, L22 Apr 2026
Site photograph, M22 Apr 2026
Site photograph, N22 Apr 2026
Site photograph, O22 Apr 2026
Site photograph, P22 Apr 2026
Site photograph, A22 Apr 2026
Site photograph, B22 Apr 2026
RERA registration certificate30 Aug 2022
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

70%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep AVADH ERCOLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near ABHVA2,600+ in Surat

2 kmAVADH ERCOLEOther 108Dot size: filed unitsN

Filed coordinates, straight-line distance. 108 registered projects within 2 km.

Builder: AVADH INFRABUILD

AVADH INFRABUILD has 1 registration on GujRERA, including AVADH ERCOLE. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if AVADH ERCOLE is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AVADH ERCOLE?

The registered promoter entity is AVADH INFRABUILD, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AVADH ERCOLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AVADH ERCOLE?

The professionals named in the filing: Architect: SANJAY RIDDHISHANKAR JOSHI; Engineer: HARDIKBHAI CHIMANBHAI SORATHIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AVADH ERCOLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AVADH ERCOLE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AVADH ERCOLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.