ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / ATRIUS

Valid until 31 Jul 2026 Residential/Group Housing project

ATRIUS

By ADANI INFRASTRUCTURE AND DEVELOPERS PRIVATE LIMITED

RG-GJ-07906 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09989/EX1/210725/310726 · Last updated on GujRERA portal: 9 Jul 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jul 2026Possession promisedmoved 12 months from the original
45 of 45Construction stages doneacross 5 buildings; every applicable stage filed complete
89 of 400Units unsoldnot recorded sold or booked
Jump to the 46 documents Report an error

ATRIUS is a Residential/Group Housing project by ADANI INFRASTRUCTURE AND DEVELOPERS PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09989/EX1/210725/310726 on 31 Mar 2022. Possession is promised by 31 Jul 2026. The completion date has moved by 12 months from the original filing. 311 of the 400 units on this registration are recorded sold or booked, and 45 of 45 construction stages are filed complete.

At a glance

Project

  • NameATRIUS
  • TypeResidential/Group Housing
  • Location
    • TP 34
    • FP 5
    • Nr.jagatpur Cross Rd. Jagatpur
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09989/EX1/210725/310726
  • ReraGenie IDRG-GJ-07906

Builder

  • NameADANI INFRASTRUCTURE AND DEVELOPERS PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations6 more →

Key dates

this monthRegisteredMar 2022First promiseJul 2025Revised toJul 2026

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2026
  • Registered on31 Mar 2022
  • Promised completion31 Jul 2026
  • Revised completionRevised to 31 Jul 2026 (originally 31 Jul 2025)
  • Buildings5 building records
  • Documents filed46 files

Current status

78%311 of 400 units booked
100.0%Of the estimated cost spent so far

Figures as on 9 Jul 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---80080
C+D---80080
E+F---80080
G+H---80080
I+J---80080

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 9 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 45 construction stages are filed complete across 5 buildings.

A+B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C+D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E+F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G+H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
I+J100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 9 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes70%
Street lightingYes85%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationYes100%
Use of renewable energyYes100%
SecurityYes85%
Letter boxYes85%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,810 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 99.74 cr
Cost incurredRs 99.74 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
I+JNARs 22.44 crRs 22.44 cr
A+BNARs 22.44 crRs 22.44 cr
E+FNARs 19.95 crRs 19.95 cr
C+DNARs 17.45 crRs 17.45 cr
G+HNARs 17.45 crRs 17.45 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAAA (Apoorva Amin Architects)
EngineerVIJAYKUMAR DASHRATHLAL SHAH

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09989/EX1/210725/310726Applied Jun 2025; approved Jul 2025

Documents filed46

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09989/EX1/210725/310726 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)9 Jul 2025
Architect's certificate (Form 1)27 Jun 2025
Engineer's certificate (Form 2)27 Jun 2025
Engineer's certificate annexure27 Jun 2025
Site photograph, A+B27 Jun 2025
Site photograph, A+B27 Jun 2025
Site photograph, C+D27 Jun 2025
Site photograph, E+F27 Jun 2025
Site photograph, G+H27 Jun 2025
Site photograph, I+J27 Jun 2025
RERA registration certificate31 Mar 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

78%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep ATRIUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmATRIUSOther 265Dot size: filed unitsN

Filed coordinates, straight-line distance. 265 registered projects within 2 km.

Builder: ADANI INFRASTRUCTURE AND DEVELOPERS PRIVATE LIMITED

ADANI INFRASTRUCTURE AND DEVELOPERS PRIVATE LIMITED has 7 registrations on GujRERA, including Pratham Phase - II (Tower - K to U) and ATRIUS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if ATRIUS is delayed beyond 31 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ATRIUS?

The registered promoter entity is ADANI INFRASTRUCTURE AND DEVELOPERS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ATRIUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ATRIUS?

The professionals named in the filing: Architect: AAA (Apoorva Amin Architects); Engineer: VIJAYKUMAR DASHRATHLAL SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ATRIUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATRIUS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATRIUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.