Home / Browse projects / Ahmedabad, Gujarat / ATLANTIS

Valid until 31 Dec 2026 Residential/Group Housing project

ATLANTIS

By SHREE KHODIYAR BUILDERS

RG-GJ-89592 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09367/A1R/171023 · Last updated on GujRERA portal: 9 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
26 of 45Construction stages doneacross 5 buildings; furthest along: External plumbing and external plaster, 85%
126 of 260Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

ATLANTIS is a Residential/Group Housing project by SHREE KHODIYAR BUILDERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09367/A1R/171023 on 26 Nov 2021. Possession is promised by 31 Dec 2026. 134 of the 260 units on this registration are recorded sold or booked, and 26 of 45 construction stages are filed complete.

At a glance

Project

  • NameATLANTIS
  • TypeResidential/Group Housing
  • Location
    • Atlantis
    • Opp.Malbar Hills Bunglows
    • M G Road
    • Nikol
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09367/A1R/171023
  • ReraGenie IDRG-GJ-89592

Builder

  • NameSHREE KHODIYAR BUILDERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredNov 2021PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on26 Nov 2021
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings5 building records
  • Documents filed41 files

Current status

52%134 of 260 units booked
79.2%Of the estimated cost spent so far

Figures as on 9 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---52052
BLOCK C---52052
BLOCK B---52052
BLOCK E---52052
BLOCK D---52052

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 9 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

26 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 85%.

BLOCK A71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor55%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK C76%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor55%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
BLOCK B71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor55%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK E67%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor45%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK D73%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor55%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 9 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes60%
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,016 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 75.00 cr
Cost incurredRs 59.40 cr
Spent of the estimate79.2%
BuildingWingEstimatedIncurred
BLOCK ANARs 15.00 crRs 11.80 cr
BLOCK BNARs 15.00 crRs 11.80 cr
BLOCK CNARs 15.00 crRs 11.80 cr
BLOCK DNARs 15.00 crRs 12.20 cr
BLOCK ENARs 15.00 crRs 11.80 cr

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09367/A1R/171023 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)9 Apr 2026
Engineer's certificate (Form 2)9 Apr 2026
Engineer's certificate annexure9 Apr 2026
Accountant's certificate (Form 3)9 Apr 2026
Site photograph, BLOCK A8 Apr 2026
Site photograph, BLOCK C8 Apr 2026
Site photograph, BLOCK B8 Apr 2026
Site photograph, BLOCK E8 Apr 2026
Site photograph, BLOCK D8 Apr 2026
RERA registration certificate26 Nov 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Approved building or plotting plan-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

52%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep ATLANTIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmATLANTISOther 376Dot size: filed unitsN

Filed coordinates, straight-line distance. 376 registered projects within 2 km.

Builder: SHREE KHODIYAR BUILDERS

SHREE KHODIYAR BUILDERS has 1 registration on GujRERA, including ATLANTIS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if ATLANTIS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ATLANTIS?

The registered promoter entity is SHREE KHODIYAR BUILDERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ATLANTIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in ATLANTIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATLANTIS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATLANTIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.