ATLANTA SKY DECK
RG-GJ-26736 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA04766/EX1/050124 · Last updated on GujRERA portal: 25 Jun 2024
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Nothing verified clear yet
Saved.
ATLANTA SKY DECK is a Residential/Group Housing project by SHREE KRISHNA INFRA in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA04766/EX1/050124 on 29 Jan 2019. Possession is promised by 29 Sep 2024. The completion date has moved by 12 months from the original filing. 164 of the 456 units on this registration are recorded sold or booked, and 49 of 60 construction stages are filed complete.
At a glance
Project
- NameATLANTA SKY DECK
- TypeResidential/Group Housing
- Location
- T.P.S. NO.- 42 (BHIMRAD)
- R.S.NO.- 89/A/PAIKEE-1
- O.P.NO.-28
- F.P.NO.- 32 PAIKEE SUB PLOT NO -1
- SURAT.
- Bhimrad
- Surat City
- Surat
- 395007
- Pincode395007
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA04766/EX1/050124
- ReraGenie IDRG-GJ-26736
Builder
- NameSHREE KRISHNA INFRA
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 29 Sep 2024
- Registered on29 Jan 2019
- Promised completion29 Sep 2024
- Revised completionRevised to 29 Sep 2024 (originally 30 Sep 2023)
- Buildings6 building records
- Documents filed52 files
Current status
Figures as on 25 Jun 2024, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | - | - | - | 76 | 0 | 76 |
| Building B | - | - | - | 76 | 0 | 76 |
| Building C | - | - | - | 76 | 0 | 76 |
| Building D | - | - | - | 76 | 0 | 76 |
| Building E | - | - | - | 76 | 0 | 76 |
| Building F | - | - | - | 76 | 0 | 76 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building6
As on 25 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
49 of 60 construction stages are filed complete across 6 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
Building A98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 80% |
Building B98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 80% |
Building C99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 90% |
Building D99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 90% |
Building E91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 50% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 95% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 80% |
Building F92%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 50% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 95% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 80% |
Progress on shared amenities19
As on 25 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 70% |
| Street lighting | Yes | 30% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Water conservation, rain water harvesting | Yes | 80% |
| Energy management | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | Yes | 100% |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | Yes | 100% |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building A | NA | Rs 11.88 cr | Rs 11.80 cr |
| Building B | NA | Rs 11.88 cr | Rs 11.80 cr |
| Building C | NA | Rs 11.88 cr | Rs 11.80 cr |
| Building D | NA | Rs 11.88 cr | Rs 11.80 cr |
| Building E | NA | Rs 11.88 cr | Rs 11.80 cr |
| Building F | NA | Rs 11.88 cr | Rs 11.80 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANJAY JOSSHI |
| Engineer | KUNAL SUTHAR |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed52
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA04766/EX1/050124 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 25 Jun 2024 |
| Engineer's certificate (Form 2) | 17 Jun 2024 |
| Engineer's certificate annexure | 17 Jun 2024 |
| Architect's certificate (Form 1) | 7 Jun 2024 |
| Site photograph, Building A | 6 Jun 2024 |
| Site photograph, Building A | 6 Jun 2024 |
| Site photograph, Building B | 6 Jun 2024 |
| Site photograph, Building B | 6 Jun 2024 |
| Site photograph, Building C | 6 Jun 2024 |
| Site photograph, Building C | 6 Jun 2024 |
| Site photograph, Building D | 6 Jun 2024 |
| Site photograph, Building D | 6 Jun 2024 |
| Site photograph, Building E | 6 Jun 2024 |
| Site photograph, Building E | 6 Jun 2024 |
| Site photograph, Building F | 6 Jun 2024 |
| Site photograph, Building F | 6 Jun 2024 |
| RERA registration certificate | 29 Jan 2019 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Surat
Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.
Keep ATLANTA SKY DECK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bhimrad2,600+ in Surat
Filed coordinates, straight-line distance. 183 registered projects within 2 km.
SUMAN BHARGAV EWS-32 TP NO 13 (BHARTHANA-VESU)
SURAT MUNICIPAL CORPORATION
AVADH SELENIC
AVADH INFRASPACE LLP
MILLENNIUM PARK
MILLENNIUM RESIDENCY
Construction Of 660 DUs Of EWS-II Type at T.P.
SURAT MUNICIPAL CORPORATION
RAJHANS BLUE CLOUD
RAJHANS INFRACON (INDIA) PRIVATE LIMITED
RAJHANS SYNFONIA
RAJHANS INFRACON (INDIA) PRIVATE LIMITED
See every Surat project, with the district possession charts
Builder: SHREE KRISHNA INFRA
SHREE KRISHNA INFRA has 2 registrations on GujRERA, including ATLANTA SKY DECK and SIGNATURE HOUSE. Read the full track record. See more projects on the Surat district page.
Frequently asked questions
What are my rights if ATLANTA SKY DECK is delayed beyond 29 Sep 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of ATLANTA SKY DECK?
The registered promoter entity is SHREE KRISHNA INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in ATLANTA SKY DECK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at ATLANTA SKY DECK?
The professionals named in the filing: Architect: SANJAY JOSSHI; Engineer: KUNAL SUTHAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ATLANTA SKY DECK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.