Home / Browse projects / Surat, Gujarat / ATLANTA ELIZA

Valid until 28 Jun 2025 Residential/Group Housing project

ATLANTA ELIZA

By Atlanta Corporation

RG-GJ-00516 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA05434/A1R/EX2/061124/280625 · Last updated on GujRERA portal: 28 May 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Jun 2025Possession promisedmoved 24 months from the original
24 of 27Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 50%
66 of 102Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

ATLANTA ELIZA is a Residential/Group Housing project by Atlanta Corporation in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA05434/A1R/EX2/061124/280625 on 14 May 2019. Possession is promised by 28 Jun 2025. The completion date has moved by 24 months from the original filing. 36 of the 102 units on this registration are recorded sold or booked, and 24 of 27 construction stages are filed complete.

At a glance

Project

  • NameATLANTA ELIZA
  • TypeResidential/Group Housing
  • Location
    • BLOCK NO 174
    • TP NO 13
    • FP NO 108
    • OP NO 82
    • BHARTHANA VESU
    • Bharthana
    • Surat City
    • Surat
    • 395007
  • Pincode395007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA05434/A1R/EX2/061124/280625
  • ReraGenie IDRG-GJ-00516

Builder

  • NameAtlanta Corporation
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2019First promiseJun 2023Revised toJun 2025

Key facts

Registration and timeline

  • StatusValid until 28 Jun 2025
  • Registered on14 May 2019
  • Promised completion28 Jun 2025
  • Revised completionRevised to 28 Jun 2025 (originally 30 Jun 2023)
  • Buildings3 building records
  • Documents filed38 files

Current status

35%36 of 102 units booked
56.5%Of the estimated cost spent so far

Figures as on 28 May 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---34034
B---34034
C---34034

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 28 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 50%.

A94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 28 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes75%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable
Compound wallYes50%
Plinth protectionYes100%
Water tankYes100%
Other requirementsYes50%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,025 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 63.75 cr
Cost incurredRs 36.00 cr
Spent of the estimate56.47%
BuildingWingEstimatedIncurred
ANARs 21.25 crRs 12.00 cr
BNARs 21.25 crRs 12.00 cr
CNARs 21.25 crRs 12.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJIT B JARIWALA
EngineerHIREN G DESAI

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA05434/A1R/EX1/070224/290624Applied Dec 2023; approved Feb 2024
PR/GJ/SURAT/SURAT CITY/SUDA/RAA05434/A1R/EX2/061124/280625Applied Jun 2024; approved Nov 2024

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA05434/A1R/EX2/061124/280625 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)28 May 2024
Engineer's certificate annexure28 May 2024
RERA registration certificate14 May 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

35%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 24 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep ATLANTA ELIZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bharthana2,600+ in Surat

2 kmATLANTA ELIZAOther 160Dot size: filed unitsN

Filed coordinates, straight-line distance. 160 registered projects within 2 km.

Builder: Atlanta Corporation

Atlanta Corporation has 1 registration on GujRERA, including ATLANTA ELIZA. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if ATLANTA ELIZA is delayed beyond 28 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ATLANTA ELIZA?

The registered promoter entity is Atlanta Corporation, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ATLANTA ELIZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ATLANTA ELIZA?

The professionals named in the filing: Architect: AJIT B JARIWALA; Engineer: HIREN G DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ATLANTA ELIZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATLANTA ELIZA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATLANTA ELIZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.