Valid until 30 Sep 2021 Residential/Group Housing project

Ashapura Park

By JADEJA DEVELOPERS PRIVATE LIMITED

RG-GJ-04774 · RERA PR/GJ/KUTCH/GANDHIDHAM/Others/RAA06538/311219 · Last updated on GujRERA portal: 21 Sep 2020

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Sep 2021Possession promisedno revision filed
1 of 3Construction stages donefurthest along: Staircases, 80%
9 of 11Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

Ashapura Park is a Residential/Group Housing project by JADEJA DEVELOPERS PRIVATE LIMITED in Kutch, Gujarat, registered with GujRERA as PR/GJ/KUTCH/GANDHIDHAM/Others/RAA06538/311219 on 31 Dec 2019. Possession is promised by 30 Sep 2021. 2 of the 11 units on this registration are recorded sold or booked, and 1 of 3 construction stages are filed complete.

At a glance

Project

  • NameAshapura Park
  • TypeResidential/Group Housing
  • Location
    • Plot No. 361
    • Ward 6-A
    • Adipur
    • Adipur
    • Gandhidham
    • Kutch
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/KUTCH/GANDHIDHAM/Others/RAA06538/311219
  • ReraGenie IDRG-GJ-04774

Builder

  • NameJADEJA DEVELOPERS PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredDec 2019PromisedSep 2021

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2021
  • Registered on31 Dec 2019
  • Promised completion30 Sep 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Current status

18%2 of 11 units booked
58.2%Of the estimated cost spent so far

Figures as on 21 Sep 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-A---11011

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 21 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 3 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

BLOCK-A: 73% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 21 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area345 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 71.25 lakh
Cost incurredRs 41.50 lakh
Spent of the estimate58.24%
BuildingWingEstimatedIncurred
BLOCK-ANARs 71.25 lakhRs 41.50 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNitin Gurnani
EngineerKamlesh K Dabhi

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/KUTCH/GANDHIDHAM/Others/RAA06538/311219 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)21 Sep 2020
Engineer's certificate (Form 2)21 Sep 2020
Engineer's certificate annexure21 Sep 2020
Accountant's certificate (Form 3)21 Sep 2020
RERA registration certificate31 Dec 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Kutch

18%of this project is bookeddistrict median 42%
6%of Kutch projects moved their completion datethis one has not

Computed across the 80 Kutch projects on ReraGenie, from their own filings.

Keep Ashapura Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Adipur80 in Kutch

2 kmAshapura ParkOther 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: JADEJA DEVELOPERS PRIVATE LIMITED

JADEJA DEVELOPERS PRIVATE LIMITED has 1 registration on GujRERA, including Ashapura Park. Read the full track record. See more projects on the Kutch district page.

Frequently asked questions

What are my rights if Ashapura Park is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Ashapura Park?

The registered promoter entity is JADEJA DEVELOPERS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Ashapura Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Ashapura Park?

The professionals named in the filing: Architect: Nitin Gurnani; Engineer: Kamlesh K Dabhi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ashapura Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ashapura Park. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ashapura Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.