Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 6 months from the original
51 of 54Construction stages doneacross 6 buildings; furthest along: Installation of lifts, 80%
133 of 330Units unsoldnot recorded sold or booked
Jump to the 48 documents Report an error

ARISE VIBRANT is a Residential/Group Housing project by SILVERSTONE BUILDCON in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09045/EX1/080726/301226 on 14 Sep 2021. Possession is promised by 30 Dec 2026. The completion date has moved by 6 months from the original filing. 197 of the 330 units on this registration are recorded sold or booked, and 51 of 54 construction stages are filed complete.

At a glance

Project

  • NameARISE VIBRANT
  • TypeResidential/Group Housing
  • Location
    • ARISE VIBRANT
    • B/H LOTUS TEMPLE
    • NR. SGVP
    • OPP. NIRMA UNIVERSITY
    • CHHARODI
    • AHMEDABAD
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09045/EX1/080726/301226
  • ReraGenie IDRG-GJ-26759

Builder

  • NameSILVERSTONE BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2021First promiseJun 2026Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 30 Dec 2026
  • Registered on14 Sep 2021
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 30 Jun 2026)
  • Buildings6 building records
  • Documents filed48 files

Current status

60%197 of 330 units booked
98.0%Of the estimated cost spent so far

Figures as on 31 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---56056
BLOCK B---56056
BLOCK C---56056
BLOCK D---54054
BLOCK E---54054
BLOCK F---54054

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 31 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

51 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Installation of lifts, at 80%.

BLOCK A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK C98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
BLOCK D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK E98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
BLOCK F98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%

Progress on shared amenities19

As on 31 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes60%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes90%
Landscaping and tree plantingYes0%
Street lightingYes75%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes75%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,623 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 97.00 cr
Cost incurredRs 95.10 cr
Spent of the estimate98.04%
BuildingWingEstimatedIncurred
BLOCK ANARs 16.17 crRs 16.17 cr
BLOCK BNARs 16.17 crRs 16.17 cr
BLOCK CNARs 16.17 crRs 15.53 cr
BLOCK DNARs 16.17 crRs 16.17 cr
BLOCK ENARs 16.17 crRs 15.53 cr
BLOCK FNARs 16.17 crRs 15.53 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR. Brijesh V. Patel
EngineerNitin J. Patel

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09045/EX1/080726/301226Applied Jun 2026; approved Jul 2026

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA09045/EX1/080726/301226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)31 May 2026
Engineer's certificate (Form 2)27 May 2026
Engineer's certificate annexure27 May 2026
Architect's certificate (Form 1)26 May 2026
Site photograph, BLOCK A25 May 2026
Site photograph, BLOCK B25 May 2026
Site photograph, BLOCK C25 May 2026
Site photograph, BLOCK D25 May 2026
Site photograph, BLOCK D25 May 2026
Site photograph, BLOCK E25 May 2026
Site photograph, BLOCK F25 May 2026
RERA registration certificate14 Sep 2021
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

60%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 6 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep ARISE VIBRANT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmARISE VIBRANTOther 132Dot size: filed unitsN

Filed coordinates, straight-line distance. 132 registered projects within 2 km.

Builder: SILVERSTONE BUILDCON

SILVERSTONE BUILDCON has 1 registration on GujRERA, including ARISE VIBRANT. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if ARISE VIBRANT is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ARISE VIBRANT?

The registered promoter entity is SILVERSTONE BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ARISE VIBRANT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ARISE VIBRANT?

The professionals named in the filing: Architect: AR. Brijesh V. Patel; Engineer: Nitin J. Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARISE VIBRANT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARISE VIBRANT. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARISE VIBRANT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.