Home / Browse projects / Ahmedabad, Gujarat / ARCUS GREENS

Valid until 31 Jul 2028 Residential/Group Housing project

ARCUS GREENS

By GALAXY REAL ESTATE DEVELOPERS GUJ PRIVATE LIMITED

RG-GJ-02539 · RERA PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Urban Development Authority/RAA13248/050424/310328 · Last updated on GujRERA portal: 25 Jun 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2028Possession promisedno revision filed
22 of 108Construction stages doneacross 12 buildings; furthest along: Slabs of Super Structure, 86%
187 of 203Units unsoldnot recorded sold or booked
Jump to the 55 documents Report an error

ARCUS GREENS is a Residential/Group Housing project by GALAXY REAL ESTATE DEVELOPERS GUJ PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Urban Development Authority/RAA13248/050424/310328 on 5 Apr 2024. Possession is promised by 31 Jul 2028. 16 of the 203 units on this registration are recorded sold or booked, and 22 of 108 construction stages are filed complete.

At a glance

Project

  • NameARCUS GREENS
  • TypeResidential/Group Housing
  • Location
    • SANAND ROAD
    • SANATHAL
    • AHMEDABAD
    • SANATHAL - TELAV
    • Sanand
    • Ahmedabad
    • 382210
  • Pincode382210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Urban Development Authority/RAA13248/050424/310328
  • ReraGenie IDRG-GJ-02539

Builder

  • NameGALAXY REAL ESTATE DEVELOPERS GUJ PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations2 more →

Key dates

this monthRegisteredApr 2024PromisedJul 2028

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2028
  • Registered on5 Apr 2024
  • Promised completion31 Jul 2028
  • Revised completionNone
  • Buildings12 building records
  • Documents filed55 files

Current status

8%16 of 203 units booked
33.4%Of the estimated cost spent so far

Figures as on 25 Jun 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E---202
D---202
G---12012
F---404
I---101
H---404
A1---202
A---707
A3---404
A2---303
C---38038
B---1240124

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building12

As on 25 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 108 construction stages are filed complete across 12 buildings. The stage furthest along is Slabs of Super Structure, at 86%.

E42%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D44%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
G33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
I1%
ActivityProgress
Excavation10%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
H7%
ActivityProgress
Excavation30%
Podiums (if any)Not applicable
Plinth30%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A164%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A40%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure86%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A33%
ActivityProgress
Excavation30%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A20%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 25 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area80,967 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 241.13 cr
Cost incurredRs 80.57 cr
Spent of the estimate33.41%
BuildingWingEstimatedIncurred
BNARs 141.41 crRs 52.04 cr
CNARs 42.57 crRs 15.37 cr
GNARs 13.63 cr-
ANARs 12.54 crRs 8.78 cr
A3NARs 7.16 cr-
A2NARs 5.38 cr-
HNARs 4.63 crRs 69.38 lakh
FNARs 4.56 crRs 68.41 lakh
A1NARs 3.56 crRs 2.55 cr
ENARs 2.24 cr-
DNARs 2.23 crRs 33.47 lakh
INARs 1.23 crRs 12.27 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAPURVA AMIN
EngineerSIDDHARTH RAJENDRAKUMAR DESAI

Documents filed55

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Urban Development Authority/RAA13248/050424/310328 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)25 Jun 2026
Architect's certificate (Form 1)23 Jun 2026
Engineer's certificate (Form 2)23 Jun 2026
Engineer's certificate annexure23 Jun 2026
Site photograph, E18 Jun 2026
Site photograph, D18 Jun 2026
Site photograph, G18 Jun 2026
Site photograph, F18 Jun 2026
Site photograph, I18 Jun 2026
Site photograph, H18 Jun 2026
Site photograph, A118 Jun 2026
Site photograph, A18 Jun 2026
Site photograph, A318 Jun 2026
Site photograph, A218 Jun 2026
Site photograph, C18 Jun 2026
Site photograph, B18 Jun 2026
RERA registration certificate5 Apr 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

8%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep ARCUS GREENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near SANATHAL - TELAV5,400+ in Ahmedabad

2 kmARCUS GREENSOther 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: GALAXY REAL ESTATE DEVELOPERS GUJ PRIVATE LIMITED

GALAXY REAL ESTATE DEVELOPERS GUJ PRIVATE LIMITED has 3 registrations on GujRERA, including RIVIERA PRESTIGE and ORCHID GOLD. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if ARCUS GREENS is delayed beyond 31 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ARCUS GREENS?

The registered promoter entity is GALAXY REAL ESTATE DEVELOPERS GUJ PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ARCUS GREENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ARCUS GREENS?

The professionals named in the filing: Architect: APURVA AMIN; Engineer: SIDDHARTH RAJENDRAKUMAR DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARCUS GREENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARCUS GREENS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARCUS GREENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.