Home / Browse projects / Ahmedabad, Gujarat / ANUSTHAN HARMONY

Valid until 31 Dec 2025 Residential/Group Housing project

ANUSTHAN HARMONY

By CHINTAN PRAVINBHAI PRAJAPATI

RG-GJ-40929 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10467/180722 · Last updated on GujRERA portal: 6 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2025Possession promisedno revision filed
47 of 72Construction stages doneacross 8 buildings; furthest along: External plumbing and external plaster, 92%
5 of 48Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

ANUSTHAN HARMONY is a Residential/Group Housing project by CHINTAN PRAVINBHAI PRAJAPATI in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10467/180722 on 18 Jul 2022. Possession is promised by 31 Dec 2025. 43 of the 48 units on this registration are recorded sold or booked, and 47 of 72 construction stages are filed complete.

At a glance

Project

  • NameANUSTHAN HARMONY
  • TypeResidential/Group Housing
  • Location
    • ANUSHTHAN HARMONY
    • NR. TULIP RECIDENCY
    • LAMBHA-VATVA 100 FT ROAD
    • OPP. LAMBHA TURNING
    • NAROL-ASLALI HIGH WAY
    • NAROL
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10467/180722
  • ReraGenie IDRG-GJ-40929

Builder

  • NameCHINTAN PRAVINBHAI PRAJAPATI
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2025
  • Registered on18 Jul 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings8 building records
  • Documents filed38 files

Current status

90%43 of 48 units booked
80.9%Of the estimated cost spent so far

Figures as on 6 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
F---11011
G---11011
H---101
A---101
B---11011
C---11011
D---101
E---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 6 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

47 of 72 construction stages are filed complete across 8 buildings. The stage furthest along is External plumbing and external plaster, at 92%.

F78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor91%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats73%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing74%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing64%
G79%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor91%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats82%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing55%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing82%
H83%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing45%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing92%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing92%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing73%
C73%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats45%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing45%
D87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 6 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes75%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes55%
Street lightingYes20%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes55%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%
Compound wallYes15%
Plinth protectionYes25%
Water tankYes45%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,253 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 10.80 cr
Cost incurredRs 8.74 cr
Spent of the estimate80.9%
BuildingWingEstimatedIncurred
BNARs 2.48 crRs 2.25 cr
CNARs 2.48 crRs 2.01 cr
FNARs 2.48 crRs 1.90 cr
GNARs 2.48 crRs 1.80 cr
ANARs 22.50 lakhRs 20.50 lakh
DNARs 22.50 lakhRs 19.60 lakh
ENARs 22.50 lakhRs 19.60 lakh
HNARs 22.50 lakhRs 18.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNANAVATI NISHANT VANDESHKUMAR
EngineerVIREN DILIPBHAI PAREKH

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10467/180722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)6 Oct 2024
Engineer's certificate annexure6 Oct 2024
RERA registration certificate18 Jul 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

90%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep ANUSTHAN HARMONY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmANUSTHAN HARMONYOther 250Dot size: filed unitsN

Filed coordinates, straight-line distance. 250 registered projects within 2 km.

Builder: CHINTAN PRAVINBHAI PRAJAPATI

CHINTAN PRAVINBHAI PRAJAPATI has 1 registration on GujRERA, including ANUSTHAN HARMONY. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if ANUSTHAN HARMONY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ANUSTHAN HARMONY?

The registered promoter entity is CHINTAN PRAVINBHAI PRAJAPATI, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ANUSTHAN HARMONY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ANUSTHAN HARMONY?

The professionals named in the filing: Architect: NANAVATI NISHANT VANDESHKUMAR; Engineer: VIREN DILIPBHAI PAREKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANUSTHAN HARMONY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANUSTHAN HARMONY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANUSTHAN HARMONY to a free account