Home / Browse projects / Vadodara, Gujarat / ANANTA SAVAN

Valid until 25 Dec 2021 Residential/Group Housing project

ANANTA SAVAN

By SAVAN HOMES

RG-GJ-47150 · RERA PR/GJ/VADODARA/VAGHODIA/Others/RAA02733/EX2/080921 · Last updated on GujRERA portal: 15 Mar 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Separate project account declared
Dec 2021Possession promisedmoved 24 months from the original
15 of 24Construction stages doneacross 4 buildings; furthest along: Internal walls, 90%
20 of 122Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

ANANTA SAVAN is a Residential/Group Housing project by SAVAN HOMES in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VAGHODIA/Others/RAA02733/EX2/080921 on 28 May 2018. Possession is promised by 25 Dec 2021. The completion date has moved by 24 months from the original filing. 102 of the 122 units on this registration are recorded sold or booked, and 15 of 24 construction stages are filed complete.

At a glance

Project

  • NameANANTA SAVAN
  • TypeResidential/Group Housing
  • Location
    • ANANTA SAVAN SR NO.24 PAVLEPUR
    • WAGHODIA ROAD NEAR GAYATRI MANDIR
    • Pavlepur
    • Amodar
    • Vaghodia
    • Vadodara
    • 390019
  • Pincode390019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VAGHODIA/Others/RAA02733/EX2/080921
  • ReraGenie IDRG-GJ-47150

Builder

  • NameSAVAN HOMES
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2018First promiseDec 2019Revised toDec 2021

Key facts

Registration and timeline

  • StatusValid until 25 Dec 2021
  • Registered on28 May 2018
  • Promised completion25 Dec 2021
  • Revised completionRevised to 25 Dec 2021 (originally 25 Dec 2019)
  • Buildings4 building records
  • Documents filed40 files

Current status

84%102 of 122 units booked
87.5%Of the estimated cost spent so far

Figures as on 15 Mar 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A1---23023
TYPE A---53053
TYPE B---19019
TYPE C---27027

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 15 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 24 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 90%.

TYPE A189%
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE A84%
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats52%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE B91%
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats60%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE C91%
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats60%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 15 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes8%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area26,367 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 14.93 cr
Cost incurredRs 13.06 cr
Spent of the estimate87.51%
BuildingWingEstimatedIncurred
TYPE A1NARs 3.73 crRs 3.27 cr
TYPE ANARs 3.73 crRs 3.27 cr
TYPE BNARs 3.73 crRs 3.27 cr
TYPE CNARs 3.73 crRs 3.27 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VAGHODIA/Others/RAA02733/EX1/050820Applied Jun 2020; approved Aug 2020
PR/GJ/VADODARA/VAGHODIA/Others/RAA02733/EX2/080921Applied Mar 2021; approved Sep 2021

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VAGHODIA/Others/RAA02733/EX2/080921 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)15 Mar 2021
Site photograph, TYPE A115 Mar 2021
Site photograph, TYPE A15 Mar 2021
Site photograph, TYPE B15 Mar 2021
Site photograph, TYPE C15 Mar 2021
Accountant's certificate (Form 3)21 Sep 2020
RERA registration certificate28 May 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Engineer's certificate (Form 2)-
Engineer's certificate annexure-

How this compares with Vadodara

84%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 24 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep ANANTA SAVAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Pavlepur, Amodar2,900+ in Vadodara

2 kmANANTA SAVANOther 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 60 registered projects within 2 km.

Builder: SAVAN HOMES

SAVAN HOMES has 1 registration on GujRERA, including ANANTA SAVAN. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if ANANTA SAVAN is delayed beyond 25 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ANANTA SAVAN?

The registered promoter entity is SAVAN HOMES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ANANTA SAVAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in ANANTA SAVAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANTA SAVAN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANTA SAVAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.