Home / Browse projects / Surat, Gujarat / ANANT HOMES

Valid until 29 Jun 2026 Mixed Development project

ANANT HOMES

By ANANT ENTERPRISE

RG-GJ-19261 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA05720/A1M/EX1/110825/290626 · Last updated on GujRERA portal: 13 Oct 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jun 2026Possession promisedmoved 12 months from the original
16 of 18Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 0%
63 of 110Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

ANANT HOMES is a Mixed Development project by ANANT ENTERPRISE in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA05720/A1M/EX1/110825/290626 on 15 Jul 2019. Possession is promised by 29 Jun 2026. The completion date has moved by 12 months from the original filing. 47 of the 110 units on this registration are recorded sold or booked, and 16 of 18 construction stages are filed complete.

At a glance

Project

  • NameANANT HOMES
  • TypeMixed Development
  • Location
    • T.P.27 F.P.52 ANANAT HOMES AMBEY VELLY ROAD
    • UTRAN SURAT
    • Surat City
    • Surat
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA05720/A1M/EX1/110825/290626
  • ReraGenie IDRG-GJ-19261

Builder

  • NameANANT ENTERPRISE
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredJul 2019First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusValid until 29 Jun 2026
  • Registered on15 Jul 2019
  • Promised completion29 Jun 2026
  • Revised completionRevised to 29 Jun 2026 (originally 30 Jun 2025)
  • Buildings2 building records
  • Documents filed43 files

Current status

43%47 of 110 units booked
100.0%Of the estimated cost spent so far

Figures as on 13 Oct 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C---28937
A+B---561773

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 13 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 0%.

C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A+B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 13 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes90%
Landscaping and tree plantingYes90%
Street lightingYes90%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Fire fightingYes90%
Drinking water facilitiesYes90%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,646 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 8.50 cr
Cost incurredRs 8.50 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
A+BNARs 5.75 crRs 5.75 cr
CNARs 2.75 crRs 2.75 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTUSHAR H SUTARIYA
EngineerJIGNESH PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA05720/A1M/EX1/110825/290626Applied Jun 2025; approved Aug 2025

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA05720/A1M/EX1/110825/290626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)13 Oct 2025
Engineer's certificate (Form 2)13 Oct 2025
Engineer's certificate annexure13 Oct 2025
Accountant's certificate (Form 3)13 Oct 2025
Site photograph, C13 Oct 2025
Site photograph, A+B13 Oct 2025
RERA registration certificate15 Jul 2019
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

43%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep ANANT HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Surat2,600+ in Surat

2 kmANANT HOMESOther 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 101 registered projects within 2 km.

Builder: ANANT ENTERPRISE

ANANT ENTERPRISE has 2 registrations on GujRERA, including GOVARDHAN SQUARE and ANANT HOMES. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if ANANT HOMES is delayed beyond 29 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ANANT HOMES?

The registered promoter entity is ANANT ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ANANT HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ANANT HOMES?

The professionals named in the filing: Architect: TUSHAR H SUTARIYA; Engineer: JIGNESH PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANANT HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANT HOMES. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANT HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.