Home / Browse projects / Vadodara, Gujarat / AMBIKA AVENUE

Valid until 18 Sep 2020 Mixed Development project

AMBIKA AVENUE

By AMBIKA REALITY

RG-GJ-40545 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA03750/EX1/260919 · Last updated on GujRERA portal: 4 Feb 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2020Possession promisedmoved 12 months from the original
2 of 8Construction stages donefurthest along: Installation of lifts, 95%
8 of 65Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

AMBIKA AVENUE is a Mixed Development project by AMBIKA REALITY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA03750/EX1/260919 on 20 Oct 2018. Possession is promised by 18 Sep 2020. The completion date has moved by 12 months from the original filing. 57 of the 65 units on this registration are recorded sold or booked, and 2 of 8 construction stages are filed complete.

At a glance

Project

  • NameAMBIKA AVENUE
  • TypeMixed Development
  • Location
    • N H 8 KAPURI CHOKDI
    • WAGHODIYA ROAD
    • Kapurai
    • Vadodara
    • 390025
  • Pincode390025
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA03750/EX1/260919
  • ReraGenie IDRG-GJ-40545

Builder

  • NameAMBIKA REALITY
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2018First promiseSep 2019Revised toSep 2020

Key facts

Registration and timeline

  • StatusValid until 18 Sep 2020
  • Registered on20 Oct 2018
  • Promised completion18 Sep 2020
  • Revised completionRevised to 18 Sep 2020 (originally 18 Sep 2019)
  • Buildings1 building record
  • Documents filed37 files

Current status

88%57 of 65 units booked
73.3%Of the estimated cost spent so far

Figures as on 4 Feb 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER A + B---333265

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 4 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 8 construction stages are filed complete. The stage furthest along is Installation of lifts, at 95%.

TOWER A + B: 94% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor92%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats92%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing92%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 4 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes95%
Solid waste management and disposalYes94%
Water conservation, rain water harvestingYes100%
Energy managementYes97%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes95%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,051 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.60 cr
Cost incurredRs 2.64 cr
Spent of the estimate73.29%
BuildingWingEstimatedIncurred
TOWER A + BNARs 3.60 crRs 2.64 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRISHI ARCHITECT
EngineerCHETAN KAMBAD

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA03750/EX1/260919Applied Sep 2019; approved Sep 2019

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA03750/EX1/260919 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)4 Feb 2021
Engineer's certificate (Form 2)4 Feb 2021
Engineer's certificate annexure4 Feb 2021
Accountant's certificate (Form 3)4 Feb 2021
RERA registration certificate20 Oct 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

88%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep AMBIKA AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kapurai2,900+ in Vadodara

2 kmAMBIKA AVENUEOther 184Dot size: filed unitsN

Filed coordinates, straight-line distance. 184 registered projects within 2 km.

Builder: AMBIKA REALITY

AMBIKA REALITY has 1 registration on GujRERA, including AMBIKA AVENUE. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if AMBIKA AVENUE is delayed beyond 18 Sep 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AMBIKA AVENUE?

The registered promoter entity is AMBIKA REALITY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AMBIKA AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AMBIKA AVENUE?

The professionals named in the filing: Architect: RISHI ARCHITECT; Engineer: CHETAN KAMBAD. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMBIKA AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMBIKA AVENUE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMBIKA AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.