ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / AMARDEEP LANDMARK PHASE-I

Valid until 30 Nov 2024 Mixed Development project

AMARDEEP LANDMARK PHASE-I

By AARADHYA REALITY

RG-GJ-55676 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA05581/EX1/020724/301124 · Last updated on GujRERA portal: 17 Oct 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Nov 2024Possession promisedmoved 12 months from the original
72 of 81Construction stages doneacross 9 buildings; furthest along: Stilt Floor, 0%
7 of 261Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

AMARDEEP LANDMARK PHASE-I is a Mixed Development project by AARADHYA REALITY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA05581/EX1/020724/301124 on 19 Jun 2019. Possession is promised by 30 Nov 2024. The completion date has moved by 12 months from the original filing. 254 of the 261 units on this registration are recorded sold or booked, and 72 of 81 construction stages are filed complete.

At a glance

Project

  • NameAMARDEEP LANDMARK PHASE-I
  • TypeMixed Development
  • Location
    • Amardeep Landmark Phase-I
    • Opp.Pandit Din dayal Upadhyay Nagar Gruh
    • Near Amardeep Homes
    • Ajwa Road
    • SAYAJIPURA
    • Vadodara
    • 390019
  • Pincode390019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA05581/EX1/020724/301124
  • ReraGenie IDRG-GJ-55676

Builder

  • NameAARADHYA REALITY
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredJun 2019First promiseNov 2023Revised toNov 2024

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2024
  • Registered on19 Jun 2019
  • Promised completion30 Nov 2024
  • Revised completionRevised to 30 Nov 2024 (originally 30 Nov 2023)
  • Buildings9 building records
  • Documents filed49 files

Current status

97%254 of 261 units booked
100.0%Of the estimated cost spent so far

Figures as on 17 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER A1---28432
TOWER A2---28533
TOWER B---28028
TOWER C---28028
TOWER F1---28028
TOWER F2---28028
TOWER H---28028
TOWER J1---28028
TOWER J2---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 17 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

72 of 81 construction stages are filed complete across 9 buildings. The stage furthest along is Stilt Floor, at 0%.

TOWER A189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER A289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER F189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER F289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER H89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER J189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER J289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 17 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes95%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes0%
Landscaping and tree plantingYes100%
Street lightingYes0%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,818 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 29.36 cr
Cost incurredRs 29.36 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
TOWER BNARs 4.03 crRs 4.03 cr
TOWER CNARs 4.03 crRs 4.03 cr
TOWER HNARs 3.24 crRs 3.24 cr
TOWER A1NARs 3.12 crRs 3.12 cr
TOWER A2NARs 3.12 crRs 3.12 cr
TOWER F1NARs 2.96 crRs 2.96 cr
TOWER F2NARs 2.96 crRs 2.96 cr
TOWER J1NARs 2.96 crRs 2.96 cr
TOWER J2NARs 2.96 crRs 2.96 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAGAT VIRENDRABHAI PANDYA
EngineerAshok Shah & Associates

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA05581/EX1/020724/301124Applied Apr 2024; approved Jul 2024

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA05581/EX1/020724/301124 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)17 Oct 2024
Engineer's certificate (Form 2)15 Oct 2024
Engineer's certificate annexure15 Oct 2024
Architect's certificate (Form 1)6 Oct 2024
Site photograph, TOWER A15 Oct 2024
Site photograph, TOWER A25 Oct 2024
Site photograph, TOWER B5 Oct 2024
Site photograph, TOWER C5 Oct 2024
Site photograph, TOWER F15 Oct 2024
Site photograph, TOWER F25 Oct 2024
Site photograph, TOWER H5 Oct 2024
Site photograph, TOWER J15 Oct 2024
Site photograph, TOWER J25 Oct 2024
RERA registration certificate19 Jun 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

97%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep AMARDEEP LANDMARK PHASE-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near SAYAJIPURA2,900+ in Vadodara

2 kmAMARDEEP LANDMARK PHASE-Other 102Dot size: filed unitsN

Filed coordinates, straight-line distance. 102 registered projects within 2 km.

Builder: AARADHYA REALITY

AARADHYA REALITY has 2 registrations on GujRERA, including AMARDEEP LANDMARK PHASE-I and AMARDEEP LANDMARK PHASE II. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if AMARDEEP LANDMARK PHASE-I is delayed beyond 30 Nov 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AMARDEEP LANDMARK PHASE-I?

The registered promoter entity is AARADHYA REALITY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AMARDEEP LANDMARK PHASE-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AMARDEEP LANDMARK PHASE-I?

The professionals named in the filing: Architect: JAGAT VIRENDRABHAI PANDYA; Engineer: Ashok Shah & Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMARDEEP LANDMARK PHASE-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMARDEEP LANDMARK PHASE-I. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMARDEEP LANDMARK PHASE-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.