Home / Browse projects / Vadodara, Gujarat / AL HUDA RESIDENCY

Valid until 30 Apr 2028 Residential/Group Housing project

AL HUDA RESIDENCY

By VINTAGE CORPORATION

RG-GJ-93964 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13688/180624/311227 · Last updated on GujRERA portal: 28 May 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
42 of 144Construction stages doneacross 16 buildings; furthest along: Internal walls, 80%
28 of 65Units unsoldnot recorded sold or booked
Jump to the 58 documents Report an error

AL HUDA RESIDENCY is a Residential/Group Housing project by VINTAGE CORPORATION in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13688/180624/311227 on 18 Jun 2024. Possession is promised by 30 Apr 2028. 37 of the 65 units on this registration are recorded sold or booked, and 42 of 144 construction stages are filed complete.

At a glance

Project

  • NameAL HUDA RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • 00
    • Savera Bunglow
    • Near Samarpan Society
    • Makrand Desai Road
    • Tandalja
    • TANDALJA
    • Vadodara
    • 390020
  • Pincode390020
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13688/180624/311227
  • ReraGenie IDRG-GJ-93964

Builder

  • NameVINTAGE CORPORATION
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2024PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on18 Jun 2024
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings16 building records
  • Documents filed58 files

Current status

57%37 of 65 units booked
50.2%Of the estimated cost spent so far

Figures as on 28 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E (TYPE)---808
D (TYPE)---101
F (TYPE)---808
D1 (TYPE)---101
A5 (TYPE)---404
A4 (TYPE)---12012
D2 (TYPE)---202
A2 (TYPE)---404
A3 (TYPE)---101
A (TYPE)---202
A1 (TYPE)---13013
A6 (TYPE)---202
A7 (TYPE)---202
F1 (TYPE)---202
A8 (TYPE)---101
E1 (TYPE)---202

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building16

As on 28 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

42 of 144 construction stages are filed complete across 16 buildings. The stage furthest along is Internal walls, at 80%.

E (TYPE)54%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing2%
D (TYPE)12%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth10%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F (TYPE)50%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing2%
D1 (TYPE)12%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth10%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A5 (TYPE)44%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure66%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks66%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A4 (TYPE)58%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats68%
Sanitary fittings within the flats66%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks67%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D2 (TYPE)12%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth10%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A2 (TYPE)44%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats25%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A3 (TYPE)44%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats25%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A (TYPE)44%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats25%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A1 (TYPE)56%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats68%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%
A6 (TYPE)55%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing12%
A7 (TYPE)56%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats67%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing10%
F1 (TYPE)64%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats25%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing8%
A8 (TYPE)43%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats25%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E1 (TYPE)58%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing2%

Progress on shared amenities19

As on 28 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,708 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 17.00 cr
Cost incurredRs 8.54 cr
Spent of the estimate50.24%
BuildingWingEstimatedIncurred
A1 (TYPE)NARs 3.21 crRs 1.77 cr
A4 (TYPE)NARs 2.96 crRs 1.66 cr
E (TYPE)NARs 2.36 crRs 1.30 cr
F (TYPE)NARs 2.36 crRs 1.23 cr
A2 (TYPE)NARs 88.33 lakhRs 42.40 lakh
A5 (TYPE)NARs 88.33 lakhRs 48.58 lakh
D2 (TYPE)NARs 72.01 lakh-
F1 (TYPE)NARs 56.11 lakhRs 49.95 lakh
E1 (TYPE)NARs 56.11 lakhRs 30.86 lakh
A6 (TYPE)NARs 45.69 lakhRs 25.13 lakh
A7 (TYPE)NARs 45.69 lakhRs 25.13 lakh
D1 (TYPE)NARs 43.77 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHRENIK RAJENDRAKUMAR SONI
EngineerVINUBHAI RATILAL PATEL

Documents filed58

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA13688/180624/311227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)28 May 2026
Engineer's certificate annexure28 May 2026
Accountant's certificate (Form 3)28 May 2026
Architect's certificate (Form 1)27 May 2026
Site photograph, E (TYPE)20 Apr 2026
Site photograph, D (TYPE)20 Apr 2026
Site photograph, F (TYPE)20 Apr 2026
Site photograph, D1 (TYPE)20 Apr 2026
Site photograph, A5 (TYPE)20 Apr 2026
Site photograph, A4 (TYPE)20 Apr 2026
Site photograph, D2 (TYPE)20 Apr 2026
Site photograph, A2 (TYPE)20 Apr 2026
Site photograph, A3 (TYPE)20 Apr 2026
Site photograph, A (TYPE)20 Apr 2026
Site photograph, A1 (TYPE)20 Apr 2026
Site photograph, A6 (TYPE)20 Apr 2026
Site photograph, A7 (TYPE)20 Apr 2026
Site photograph, F1 (TYPE)20 Apr 2026
Site photograph, A8 (TYPE)20 Apr 2026
Site photograph, E1 (TYPE)20 Apr 2026
RERA registration certificate18 Jun 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

57%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep AL HUDA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near TANDALJA2,900+ in Vadodara

2 kmAL HUDA RESIDENCYOther 215Dot size: filed unitsN

Filed coordinates, straight-line distance. 215 registered projects within 2 km.

Builder: VINTAGE CORPORATION

VINTAGE CORPORATION has 1 registration on GujRERA, including AL HUDA RESIDENCY. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if AL HUDA RESIDENCY is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AL HUDA RESIDENCY?

The registered promoter entity is VINTAGE CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AL HUDA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AL HUDA RESIDENCY?

The professionals named in the filing: Architect: SHRENIK RAJENDRAKUMAR SONI; Engineer: VINUBHAI RATILAL PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AL HUDA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AL HUDA RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AL HUDA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.