Home / Browse projects / Vadodara, Gujarat / AL HATIM

Valid until 30 Jun 2026 Mixed Development project

AL HATIM

By FRIENDS ENTERPRISE

RG-GJ-13668 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA04234/041218 · Last updated on GujRERA portal: 30 Dec 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2026Possession promisedno revision filed
13 of 27Construction stages doneacross 3 buildings; furthest along: Internal walls, 98%
40 of 284Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

AL HATIM is a Mixed Development project by FRIENDS ENTERPRISE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA04234/041218 on 4 Dec 2018. Possession is promised by 30 Jun 2026. 244 of the 284 units on this registration are recorded sold or booked, and 13 of 27 construction stages are filed complete.

At a glance

Project

  • NameAL HATIM
  • TypeMixed Development
  • Location
    • FP No. 64
    • TP No. 26
    • TANDALJA
    • TANDALJA
    • Vadodara
    • 390012
  • Pincode390012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA04234/041218
  • ReraGenie IDRG-GJ-13668

Builder

  • NameFRIENDS ENTERPRISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2018PromisedJun 2026

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2026
  • Registered on4 Dec 2018
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed40 files

Current status

86%244 of 284 units booked
92.3%Of the estimated cost spent so far

Figures as on 30 Dec 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ABCD---11223135
EF---54054
GH---811495

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 30 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 98%.

ABCD99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats98%
Sanitary fittings within the flats98%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing98%
EF99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats98%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing98%
GH99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats98%
Sanitary fittings within the flats98%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing98%

Progress on shared amenities19

As on 30 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes90%
Landscaping and tree plantingYes90%
Street lightingYes90%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,220 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 19.50 cr
Cost incurredRs 18.00 cr
Spent of the estimate92.31%
BuildingWingEstimatedIncurred
ABCDNARs 6.50 crRs 6.00 cr
EFNARs 6.50 crRs 6.00 cr
GHNARs 6.50 crRs 6.00 cr

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHARMI H. PANDYA

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA04234/041218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)30 Dec 2021
Architect's certificate (Form 1)28 Dec 2021
Engineer's certificate (Form 2)28 Dec 2021
Engineer's certificate annexure28 Dec 2021
Site photograph, ABCD28 Dec 2021
Site photograph, EF28 Dec 2021
Site photograph, GH28 Dec 2021
RERA registration certificate4 Dec 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

86%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep AL HATIM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmAL HATIMOther 391Dot size: filed unitsN

Filed coordinates, straight-line distance. 391 registered projects within 2 km.

Builder: FRIENDS ENTERPRISE

FRIENDS ENTERPRISE has 1 registration on GujRERA, including AL HATIM. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if AL HATIM is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AL HATIM?

The registered promoter entity is FRIENDS ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AL HATIM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AL HATIM?

The professionals named in the filing: Architect: CHARMI H. PANDYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AL HATIM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AL HATIM. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AL HATIM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.