Home / Browse projects / Dharwad, Karnataka / Akshay Town Yerikoppa
Akshay Town Yerikoppa
RG-KA-84891 · RERA PRM/KA/RERA/1259/410/PR/171215/001076
Source: official RERA Karnataka filing
Red flags
- 2 complaints at RERA Karnataka
- Completion date moved by 9 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
Akshay Town Yerikoppa is a Mixed Development project by Suresh Enterprises Pvt.Ltd in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/410/PR/171215/001076 on 15 Dec 2017. Possession is promised by 30 Mar 2023. The completion date has moved by 9 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameAkshay Town Yerikoppa
- TypeMixed Development
- Location
- Dharwad
- PincodeNot stated
- RERA no.PRM/KA/RERA/1259/410/PR/171215/001076
- ReraGenie IDRG-KA-84891
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 Dec 2017
- Promised completion30 Mar 2023
- Revised completionRevised to 30 Mar 2023 (originally 30 Jun 2022)
- Buildings49 building records
- Documents filed38 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 | - | - | - | 4 | 0 | 4 |
| 2 | - | - | - | 4 | 0 | 4 |
| 3 | - | - | - | 4 | 0 | 4 |
| 4 | - | - | - | 4 | 0 | 4 |
| 5 | - | - | - | 4 | 0 | 4 |
| 6 | - | - | - | 4 | 0 | 4 |
| 7 | - | - | - | 4 | 0 | 4 |
| 8 | - | - | - | 1 | 0 | 1 |
| 9 | - | - | - | 1 | 0 | 1 |
| 10 | - | - | - | 1 | 0 | 1 |
| 11 | - | - | - | 1 | 0 | 1 |
| 12 | - | - | - | 1 | 0 | 1 |
| 13 | - | - | - | 1 | 0 | 1 |
| 14 | - | - | - | 1 | 0 | 1 |
| 15 | - | - | - | 1 | 0 | 1 |
| 16 | - | - | - | 1 | 0 | 1 |
| 17 | - | - | - | 1 | 0 | 1 |
| 18 | - | - | - | 1 | 0 | 1 |
| 19 | - | - | - | 1 | 0 | 1 |
| 20 | - | - | - | 1 | 0 | 1 |
| 21 | - | - | - | 1 | 0 | 1 |
| 22 | - | - | - | 1 | 0 | 1 |
| 23 | - | - | - | 1 | 0 | 1 |
| 24 | - | - | - | 1 | 0 | 1 |
| 25 | - | - | - | 1 | 0 | 1 |
| 26 | - | - | - | 1 | 0 | 1 |
| 27 | - | - | - | 1 | 0 | 1 |
| 28 | - | - | - | 1 | 0 | 1 |
| 29 | - | - | - | 1 | 0 | 1 |
| 30 | - | - | - | 1 | 0 | 1 |
| 31 | - | - | - | 1 | 0 | 1 |
| 32 | - | - | - | 1 | 0 | 1 |
| 33 | - | - | - | 1 | 0 | 1 |
| 34 | - | - | - | 1 | 0 | 1 |
| 35 | - | - | - | 1 | 0 | 1 |
| 36 | - | - | - | 1 | 0 | 1 |
| 37 | - | - | - | 1 | 0 | 1 |
| 38 | - | - | - | 1 | 0 | 1 |
| 39 | - | - | - | 1 | 0 | 1 |
| 40 | - | - | - | 1 | 0 | 1 |
| 41 | - | - | - | 1 | 0 | 1 |
| 42 | - | - | - | 1 | 0 | 1 |
| 43 | - | - | - | 1 | 0 | 1 |
| 44 | - | - | - | 1 | 0 | 1 |
| 45 | - | - | - | 1 | 0 | 1 |
| 46 | - | - | - | 1 | 0 | 1 |
| 47 | - | - | - | 1 | 0 | 1 |
| 48 | - | - | - | 1 | 0 | 1 |
| 49 | - | - | - | 0 | 4 | 4 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | Yes | - |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | No | Not applicable |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sanjeev V. Revankar |
| Engineer | Manjunath V. Revankar |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CMP/200718/0006202 | - | Suresh Enterprises Pvt.Ltd | 18/07/2020 |
| 00029/2026 | - | Suresh Enterprises Pvt.Ltd | 08/01/2026 |
Documents filed38
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/410/PR/171215/001076 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: SEPL Registration Certificate.pdf | - |
| 9 Commencement Cert | - |
| 10 Building Plan | - |
| 11 Approved Layout Plan | - |
| Proforma Sale Deed | - |
| Agreement for Sale | - |
| Sale Deed | - |
| 14 Infrastructure Plan of Plotting | - |
| 15 Area Devolpment Plan - Copy | - |
| Allottment Letter | - |
| Brochure | - |
| 18 All NOCs from Authorities | - |
| 22 Project Specification | - |
| EC | - |
| Not-Applicable | - |
| JDADA | - |
| Convertion Order | - |
| Balance Sheet 2015 - 2016File: 1 BS 1516.pdf | - |
| Balance Sheet 2014 - 2015File: 1 BS 1415.pdf | - |
| Balance Sheet 2013 - 2014File: 1 BS 1314.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: 2 P&L 1516.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: 2 P&L 1415.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: 2 P&L 1314.pdf | - |
| Director's Report 2015 - 2016File: 3 DR 1516.pdf | - |
| Director's Report 2014 - 2015File: 3 DR 1415.pdf | - |
| Director's Report 2013 - 2014File: 5 DR 1314.pdf | - |
| Cash Flow Statement 2015 - 2016File: 4 CF 1516.pdf | - |
| Cash Flow Statement 2014 - 2015File: 4 CF 1415.pdf | - |
| Auditor's Report 2015 - 2016File: 5 AR 1516.pdf | - |
| Auditor's Report 2014 - 2015File: 5 AR 1415.pdf | - |
| Auditor's Report 2013 - 2014File: 3 AR 1314.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: 6 IT ACK 15-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: 6 IT ACK 14-15.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: 6 IT ACK 13-14.pdf | - |
| 19 Declaration (Form B) Affidavit | - |
| Prospectus/BrochureFile: Brochure - Akshay Town Yerikoppa.docx | - |
| Advertisement Copy 1File: Brochure - Akshay Town Yerikoppa.docx | - |
| Tower Excel SheetFile: PRM_KA_RERA_1259_410_PR_171215_001076.xlsx | - |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Chabbi Akshay Corner | - | Completed | Aug 2017 | No date filed |
| Akshay Samarth | - | Completed | Aug 2017 | No date filed |
| Akshay Residency | - | Completed | Aug 2017 | No date filed |
| Akshay Plaza | - | Completed | Aug 2017 | No date filed |
| Akshay Klassic | - | Completed | Aug 2017 | No date filed |
| AKSHAY COMFORTS | - | Completed | Aug 2017 | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dharwad
Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.
Keep Akshay Town Yerikoppa on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dharwad250+ in Dharwad
construction of 1248 houses at Hubli
Commissioner
Akshay Town Tarihal Sector A
Suresh Enterprises Pvt.Ltd
ONE HUBLI PHASE-1
SHETTY-PATIL DEVELOPERS LLP
construction of 784 houses at Hubli
Commissioner
M/s. PRIDE IKON
M/s. PRIDE GROUP
Pourakarmikas Gruha Bhagya Yojane
Hubli Dharwad Municipal Corporation
See every Dharwad project, with the district possession charts
Builder: Suresh Enterprises Pvt.Ltd
Suresh Enterprises Pvt.Ltd has 3 registrations on RERA Karnataka, including Akshay Town Tarihal Sector A and Akshay Town Yerikoppa. Its filings declare 6 earlier projects, 6 of them declared completed. Read the full track record. See more projects on the Dharwad district page.
Frequently asked questions
What are my rights if Akshay Town Yerikoppa is delayed beyond 30 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Akshay Town Yerikoppa?
The registered promoter entity is Suresh Enterprises Pvt.Ltd, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Akshay Town Yerikoppa?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Akshay Town Yerikoppa?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at Akshay Town Yerikoppa?
The professionals named in the filing: Architect: Sanjeev V. Revankar; Engineer: Manjunath V. Revankar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Akshay Town Yerikoppa?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.