Home / Browse projects / Vadodara, Gujarat / Akshar Paradise
Akshar Paradise
RG-GJ-07729 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA02287/060418 · Last updated on GujRERA portal: 7 Jun 2019
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
- Separate project account declared
Saved.
Akshar Paradise is a Mixed Development project by Akshar Reality in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA02287/060418 on 6 Apr 2018. Possession is promised by 1 Aug 2018.
At a glance
Project
- NameAkshar Paradise
- TypeMixed Development
- Location
- Akshar Paradise
- 30mtr
- ring road
- nr
- solitude
- Narayan Kathiyawadi
- Padra
- Vadodara 390012
- Kalali
- Vadodara
- 390012
- Pincode390012
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA02287/060418
- ReraGenie IDRG-GJ-07729
Builder
- NameAkshar Reality
- Entity typePARTNERSHIP FIRM
- Other registrations5 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 1 Aug 2018
- Registered on6 Apr 2018
- Promised completion1 Aug 2018
- Revised completionNone
- Buildings74 building records
- Documents filed109 files
Current status
Figures as on 7 Jun 2019, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A+B | - | - | - | - | - | 40 |
| C+D | - | - | - | - | - | 40 |
| E+F | - | - | - | - | - | 40 |
| G | - | - | - | - | - | 20 |
| H | - | - | - | - | - | 20 |
| I | - | - | - | - | - | 20 |
| J | - | - | - | - | - | 20 |
| K+L | - | - | - | - | - | 40 |
| M+N | - | - | - | - | - | 40 |
| O | - | - | - | - | - | 20 |
| P+Q+R | - | - | - | - | - | 90 |
| DUPLEX 1 | - | - | - | - | - | 1 |
| DUPLEX 2 | - | - | - | - | - | 1 |
| DUPLEX 3 | - | - | - | - | - | 1 |
| DUPLEX 4 | - | - | - | - | - | 1 |
| DUPLEX 5 | - | - | - | - | - | 1 |
| DUPLEX 6 | - | - | - | - | - | 1 |
| DUPLEX 7 | - | - | - | - | - | 1 |
| DUPLEX 8 | - | - | - | - | - | 1 |
| DUPLEX 9 | - | - | - | - | - | 1 |
| DUPLEX 10 | - | - | - | - | - | 1 |
| DUPLEX 11 | - | - | - | - | - | 1 |
| DUPLEX 12 | - | - | - | - | - | 1 |
| DUPLEX 13 | - | - | - | - | - | 1 |
| DUPLEX 14 | - | - | - | - | - | 1 |
| DUPLEX 15 | - | - | - | - | - | 1 |
| DUPLEX 16 | - | - | - | - | - | 1 |
| DUPLEX 17 | - | - | - | - | - | 1 |
| DUPLEX 18 | - | - | - | - | - | 1 |
| DUPLEX 19 | - | - | - | - | - | 1 |
| DUPLEX 20 | - | - | - | - | - | 1 |
| DUPLEX 21 | - | - | - | - | - | 1 |
| DUPLEX 22 | - | - | - | - | - | 1 |
| DUPLEX 23 | - | - | - | - | - | 1 |
| DUPLEX 24 | - | - | - | - | - | 1 |
| DUPLEX 25 | - | - | - | - | - | 1 |
| DUPLEX 26 | - | - | - | - | - | 1 |
| DUPLEX 27 | - | - | - | - | - | 1 |
| DUPLEX 28 | - | - | - | - | - | 1 |
| DUPLEX 29 | - | - | - | - | - | 1 |
| DUPLEX 30 | - | - | - | - | - | 1 |
| DUPLEX 31 | - | - | - | - | - | 1 |
| DUPLEX 32 | - | - | - | - | - | 1 |
| DUPLEX 33 | - | - | - | - | - | 1 |
| DUPLEX 34 | - | - | - | - | - | 1 |
| DUPLEX 35 | - | - | - | - | - | 1 |
| DUPLEX 36 | - | - | - | - | - | 1 |
| DUPLEX 37 | - | - | - | - | - | 1 |
| DUPLEX 38 | - | - | - | - | - | 1 |
| DUPLEX 39 | - | - | - | - | - | 1 |
| DUPLEX 40 | - | - | - | - | - | 1 |
| DUPLEX 41 | - | - | - | - | - | 1 |
| DUPLEX 42 | - | - | - | - | - | 1 |
| DUPLEX 43 | - | - | - | - | - | 1 |
| DUPLEX 44 | - | - | - | - | - | 1 |
| DUPLEX 45 | - | - | - | - | - | 1 |
| DUPLEX 46 | - | - | - | - | - | 1 |
| DUPLEX 47 | - | - | - | - | - | 1 |
| DUPLEX 48 | - | - | - | - | - | 1 |
| DUPLEX 49 | - | - | - | - | - | 1 |
| DUPLEX 50 | - | - | - | - | - | 1 |
| DUPLEX 51 | - | - | - | - | - | 1 |
| DUPLEX 52 | - | - | - | - | - | 1 |
| DUPLEX 53 | - | - | - | - | - | 1 |
| DUPLEX 54 | - | - | - | - | - | 1 |
| DUPLEX 55 | - | - | - | - | - | 1 |
| DUPLEX 56 | - | - | - | - | - | 1 |
| DUPLEX 57 | - | - | - | - | - | 1 |
| DUPLEX 58 | - | - | - | - | - | 1 |
| DUPLEX 59 | - | - | - | - | - | 1 |
| DUPLEX 60 | - | - | - | - | - | 1 |
| DUPLEX 61 | - | - | - | - | - | 1 |
| DUPLEX 62 | - | - | - | - | - | 1 |
| DUPLEX 63 | - | - | - | - | - | 1 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building20
As on 7 Jun 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 74 buildings; the table lists the first 20.
665 of 666 construction stages are filed complete across 74 buildings. The stage furthest along is Excavation, at 85%.
A+B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
C+D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
E+F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
G100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
H100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
I100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
J100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
K+L100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
M+N100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
O100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
P+Q+R100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 6100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 7100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 8100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
DUPLEX 9100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 7 Jun 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A+B | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| C+D | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| E+F | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| G | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| H | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| I | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| J | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| K+L | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| M+N | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| O | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| P+Q+R | NA | Rs 42.46 lakh | Rs 42.46 lakh |
| DUPLEX 1 | NA | Rs 42.46 lakh | Rs 42.46 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Parth R Ganatra |
| Architect | Ruchir Sheth |
| Engineer | Ashutosh Desai |
Documents filed109
As listed on the registration, under the names the promoter filed them with; the newest 80 of 109 are shown. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA02287/060418 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 7 Jun 2019 |
| Engineer's certificate (Form 2) | 7 Jun 2019 |
| Site photograph, A+B | 7 Jun 2019 |
| Site photograph, C+D | 7 Jun 2019 |
| Site photograph, E+F | 7 Jun 2019 |
| Site photograph, G | 7 Jun 2019 |
| Site photograph, H | 7 Jun 2019 |
| Site photograph, I | 7 Jun 2019 |
| Site photograph, J | 7 Jun 2019 |
| Site photograph, K+L | 7 Jun 2019 |
| Site photograph, M+N | 7 Jun 2019 |
| Site photograph, O | 7 Jun 2019 |
| Site photograph, P+Q+R | 7 Jun 2019 |
| Site photograph, DUPLEX 1 | 7 Jun 2019 |
| Site photograph, DUPLEX 2 | 7 Jun 2019 |
| Site photograph, DUPLEX 3 | 7 Jun 2019 |
| Site photograph, DUPLEX 4 | 7 Jun 2019 |
| Site photograph, DUPLEX 5 | 7 Jun 2019 |
| Site photograph, DUPLEX 6 | 7 Jun 2019 |
| Site photograph, DUPLEX 7 | 7 Jun 2019 |
| Site photograph, DUPLEX 8 | 7 Jun 2019 |
| Site photograph, DUPLEX 9 | 7 Jun 2019 |
| Site photograph, DUPLEX 10 | 7 Jun 2019 |
| Site photograph, DUPLEX 11 | 7 Jun 2019 |
| Site photograph, DUPLEX 12 | 7 Jun 2019 |
| Site photograph, DUPLEX 13 | 7 Jun 2019 |
| Site photograph, DUPLEX 14 | 7 Jun 2019 |
| Site photograph, DUPLEX 15 | 7 Jun 2019 |
| Site photograph, DUPLEX 16 | 7 Jun 2019 |
| Site photograph, DUPLEX 17 | 7 Jun 2019 |
| Site photograph, DUPLEX 18 | 7 Jun 2019 |
| Site photograph, DUPLEX 19 | 7 Jun 2019 |
| Site photograph, DUPLEX 20 | 7 Jun 2019 |
| Site photograph, DUPLEX 21 | 7 Jun 2019 |
| Site photograph, DUPLEX 22 | 7 Jun 2019 |
| Site photograph, DUPLEX 23 | 7 Jun 2019 |
| Site photograph, DUPLEX 24 | 7 Jun 2019 |
| Site photograph, DUPLEX 25 | 7 Jun 2019 |
| Site photograph, DUPLEX 26 | 7 Jun 2019 |
| Site photograph, DUPLEX 27 | 7 Jun 2019 |
| Site photograph, DUPLEX 28 | 7 Jun 2019 |
| Site photograph, DUPLEX 29 | 7 Jun 2019 |
| Site photograph, DUPLEX 30 | 7 Jun 2019 |
| Site photograph, DUPLEX 31 | 7 Jun 2019 |
| Site photograph, DUPLEX 32 | 7 Jun 2019 |
| Site photograph, DUPLEX 33 | 7 Jun 2019 |
| Site photograph, DUPLEX 34 | 7 Jun 2019 |
| Site photograph, DUPLEX 35 | 7 Jun 2019 |
| Site photograph, DUPLEX 36 | 7 Jun 2019 |
| Site photograph, DUPLEX 37 | 7 Jun 2019 |
| Site photograph, DUPLEX 38 | 7 Jun 2019 |
| Site photograph, DUPLEX 39 | 7 Jun 2019 |
| Site photograph, DUPLEX 40 | 7 Jun 2019 |
| Site photograph, DUPLEX 41 | 7 Jun 2019 |
| Site photograph, DUPLEX 42 | 7 Jun 2019 |
| Site photograph, DUPLEX 43 | 7 Jun 2019 |
| Site photograph, DUPLEX 44 | 7 Jun 2019 |
| Site photograph, DUPLEX 45 | 7 Jun 2019 |
| Site photograph, DUPLEX 46 | 7 Jun 2019 |
| Site photograph, DUPLEX 47 | 7 Jun 2019 |
| Site photograph, DUPLEX 48 | 7 Jun 2019 |
| Site photograph, DUPLEX 49 | 7 Jun 2019 |
| Site photograph, DUPLEX 50 | 7 Jun 2019 |
| Site photograph, DUPLEX 51 | 7 Jun 2019 |
| Site photograph, DUPLEX 52 | 7 Jun 2019 |
| Site photograph, DUPLEX 53 | 7 Jun 2019 |
| Site photograph, DUPLEX 54 | 7 Jun 2019 |
| Site photograph, DUPLEX 55 | 7 Jun 2019 |
| Site photograph, DUPLEX 56 | 7 Jun 2019 |
| Site photograph, DUPLEX 57 | 7 Jun 2019 |
| Site photograph, DUPLEX 58 | 7 Jun 2019 |
| Site photograph, DUPLEX 59 | 7 Jun 2019 |
| Site photograph, DUPLEX 60 | 7 Jun 2019 |
| Site photograph, DUPLEX 61 | 7 Jun 2019 |
| Site photograph, DUPLEX 62 | 7 Jun 2019 |
| Site photograph, DUPLEX 63 | 7 Jun 2019 |
| RERA registration certificate | 6 Apr 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep Akshar Paradise on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kalali2,900+ in Vadodara
Filed coordinates, straight-line distance. 274 registered projects within 2 km.
SHYAMAL PARK
SHREE GANESH INFRA HOMES
AARYA EMPIRE
SHIVAM INFRA
Star City I
SAMANVAY SPARSH
AAMRAPALI RESI-COM
GAYATRI DEVELOPERS
SHREE BALAJI SKYRISE
MANAV INFRASTRUCTURE PRIVATE LIMITED
SAFAL IRIS
SAHAJANAND INFRA
See every Vadodara project, with the district possession charts
Builder: Akshar Reality
Akshar Reality has 6 registrations on GujRERA, including Akshar Paradise and AKSHAR KUNJ. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if Akshar Paradise is delayed beyond 1 Aug 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Akshar Paradise?
The registered promoter entity is Akshar Reality, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Akshar Paradise?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Akshar Paradise?
The professionals named in the filing: Architect: Parth R Ganatra; Architect: Ruchir Sheth; Engineer: Ashutosh Desai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Akshar Paradise?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.