Home / Browse projects / Vadodara, Gujarat / AKSHAR GREEN
AKSHAR GREEN
RG-GJ-74256 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA05954/EX1/040925/300626 · Last updated on GujRERA portal: 9 Sep 2026
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Nothing verified clear yet
Saved.
AKSHAR GREEN is a Residential/Group Housing project by SHREENATHJI ASSOCIATE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA05954/EX1/040925/300626 on 28 Aug 2019. Possession is promised by 30 Jun 2026. The completion date has moved by 12 months from the original filing. 212 of the 324 units on this registration are recorded sold or booked, and 72 of 108 construction stages are filed complete.
At a glance
Project
- NameAKSHAR GREEN
- TypeResidential/Group Housing
- Location
- AKSHAR GREEN B/H LABH RESIDENCY SUN PHARMA
- ATLADARA ROAD ATLADARA
- Atladara
- Vadodara
- 390012
- Pincode390012
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA05954/EX1/040925/300626
- ReraGenie IDRG-GJ-74256
Builder
- NameSHREENATHJI ASSOCIATE
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Jun 2026
- Registered on28 Aug 2019
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
- Buildings12 building records
- Documents filed53 files
Current status
Figures as on 9 Sep 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D11 | - | - | - | 28 | 0 | 28 |
| D | - | - | - | 28 | 0 | 28 |
| D1 | - | - | - | 28 | 0 | 28 |
| D2 | - | - | - | 28 | 0 | 28 |
| D3 | - | - | - | 16 | 0 | 16 |
| D4 | - | - | - | 28 | 0 | 28 |
| D5 | - | - | - | 28 | 0 | 28 |
| D6 | - | - | - | 28 | 0 | 28 |
| D7 | - | - | - | 28 | 0 | 28 |
| D8 | - | - | - | 28 | 0 | 28 |
| D9 | - | - | - | 28 | 0 | 28 |
| D10 | - | - | - | 28 | 0 | 28 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building12
As on 9 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
72 of 108 construction stages are filed complete across 12 buildings. The stage furthest along is Excavation, at 0%.
D11100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
D4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D6100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D70%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
D80%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
D90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
D10100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 9 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 90% |
| Water supply | Yes | 90% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 90% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 90% |
| Street lighting | Yes | 90% |
| Community buildings | Yes | 90% |
| Treatment and disposal of sewage and sullage water | Yes | 90% |
| Solid waste management and disposal | Yes | 90% |
| Water conservation, rain water harvesting | Yes | 90% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 90% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 90% |
| Letter box | Yes | 90% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| D2 | NA | Rs 1.86 cr | Rs 2.10 cr |
| D | NA | Rs 1.86 cr | Rs 2.10 cr |
| D1 | NA | Rs 1.86 cr | Rs 2.10 cr |
| D4 | NA | Rs 1.86 cr | Rs 2.10 cr |
| D10 | NA | Rs 1.86 cr | Rs 2.50 cr |
| D11 | NA | Rs 1.86 cr | Rs 2.65 cr |
| D5 | NA | Rs 1.86 cr | Rs 2.10 cr |
| D6 | NA | Rs 1.86 cr | Rs 2.10 cr |
| D7 | NA | Rs 1.86 cr | - |
| D8 | NA | Rs 1.86 cr | - |
| D9 | NA | Rs 1.86 cr | - |
| D3 | NA | Rs 1.33 cr | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RUCHIR SHETH(DESIGN STUDIO ASSOCIATES) |
| Engineer | AASHUTOSH A DESAI |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed53
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA05954/EX1/040925/300626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 9 Sep 2026 |
| Architect's certificate (Form 1) | 8 Sep 2026 |
| Engineer's certificate (Form 2) | 8 Sep 2026 |
| Engineer's certificate annexure | 8 Sep 2026 |
| Site photograph, D11 | 5 Sep 2026 |
| Site photograph, D | 5 Sep 2026 |
| Site photograph, D1 | 5 Sep 2026 |
| Site photograph, D2 | 5 Sep 2026 |
| Site photograph, D3 | 5 Sep 2026 |
| Site photograph, D4 | 5 Sep 2026 |
| Site photograph, D5 | 5 Sep 2026 |
| Site photograph, D6 | 5 Sep 2026 |
| Site photograph, D7 | 5 Sep 2026 |
| Site photograph, D8 | 5 Sep 2026 |
| Site photograph, D9 | 5 Sep 2026 |
| Site photograph, D10 | 5 Sep 2026 |
| RERA registration certificate | 28 Aug 2019 |
| Extension certificate | - |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep AKSHAR GREEN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Atladara2,900+ in Vadodara
Filed coordinates, straight-line distance. 337 registered projects within 2 km.
SHYAMAL PARK
SHREE GANESH INFRA HOMES
AARYA EMPIRE
SHIVAM INFRA
Star City I
SAMANVAY SPARSH
AAMRAPALI RESI-COM
GAYATRI DEVELOPERS
SHREE BALAJI SKYRISE
MANAV INFRASTRUCTURE PRIVATE LIMITED
SAFAL IRIS
SAHAJANAND INFRA
See every Vadodara project, with the district possession charts
Builder: SHREENATHJI ASSOCIATE
SHREENATHJI ASSOCIATE has 1 registration on GujRERA, including AKSHAR GREEN. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if AKSHAR GREEN is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of AKSHAR GREEN?
The registered promoter entity is SHREENATHJI ASSOCIATE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in AKSHAR GREEN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at AKSHAR GREEN?
The professionals named in the filing: Architect: RUCHIR SHETH(DESIGN STUDIO ASSOCIATES); Engineer: AASHUTOSH A DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AKSHAR GREEN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.