ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / ADHYAY

Valid until 30 Oct 2025 Mixed Development project

ADHYAY

By TITHI DEVELOPERS

RG-GJ-37389 · RERA PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA09483/171221 · Last updated on GujRERA portal: 5 Oct 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 10 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Oct 2025Possession promisedmoved 10 months from the original
3 of 8Construction stages donefurthest along: Staircases, 83%
68 of 74Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

ADHYAY is a Mixed Development project by TITHI DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA09483/171221 on 17 Dec 2021. Possession is promised by 30 Oct 2025. The completion date has moved by 10 months from the original filing. 6 of the 74 units on this registration are recorded sold or booked, and 3 of 8 construction stages are filed complete.

At a glance

Project

  • NameADHYAY
  • TypeMixed Development
  • Location
    • survey no 675 FP -168
    • Opp. shalvin industrial estate B/h singarva lake
    • Singarva gam
    • ahmedabad
    • Daskroi
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA09483/171221
  • ReraGenie IDRG-GJ-37389

Builder

  • NameTITHI DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2021First promiseDec 2024Revised toOct 2025

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2025
  • Registered on17 Dec 2021
  • Promised completion30 Oct 2025
  • Revised completionRevised to 30 Oct 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed43 files

Current status

8%6 of 74 units booked
65.5%Of the estimated cost spent so far

Figures as on 5 Oct 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
01---631174

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 5 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 8 construction stages are filed complete. The stage furthest along is Staircases, at 83%.

01: 65% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats46%
Sanitary fittings within the flats2%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks83%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing26%

Progress on shared amenities19

As on 5 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,639 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 6.75 cr
Cost incurredRs 4.42 cr
Spent of the estimate65.5%
BuildingWingEstimatedIncurred
01NARs 6.75 crRs 4.42 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Feb 2025; no approval date filed

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA09483/171221 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)5 Oct 2023
Architect's certificate (Form 1)4 Oct 2023
Engineer's certificate (Form 2)4 Oct 2023
Engineer's certificate annexure4 Oct 2023
Site photograph, 012 Oct 2023
Site photograph, 012 Oct 2023
Site photograph, 012 Oct 2023
RERA registration certificate17 Dec 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

8%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 10 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep ADHYAY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmADHYAYOther 210Dot size: filed unitsN

Filed coordinates, straight-line distance. 210 registered projects within 2 km.

Builder: TITHI DEVELOPERS

TITHI DEVELOPERS has 1 registration on GujRERA, including ADHYAY. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if ADHYAY is delayed beyond 30 Oct 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ADHYAY?

The registered promoter entity is TITHI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ADHYAY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in ADHYAY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADHYAY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADHYAY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.