AASTHA AVENUE
By AASTHA LAND
RG-GJ-29997 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA14339/A1C/061026/150429 · Last updated on GujRERA portal: 21 Sep 2026
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
AASTHA AVENUE is a Commercial project by AASTHA LAND in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA14339/A1C/061026/150429 on 28 Oct 2024. Possession is promised by 15 Aug 2029. 35 of the 105 units on this registration are recorded sold or booked, and 5 of 9 construction stages are filed complete.
At a glance
Project
- NameAASTHA AVENUE
- TypeCommercial
- Location
- Aastha Avenue
- Panchvati Circle
- Satymev Hospital Road
- Tragad
- Chandkheda
- Chandkheda
- Ahmedabad City
- Ahmedabad
- 382424
- Pincode382424
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA14339/A1C/061026/150429
- ReraGenie IDRG-GJ-29997
Builder
- NameAASTHA LAND
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 15 Aug 2029
- Registered on28 Oct 2024
- Promised completion15 Aug 2029
- Revised completionNone
- Buildings1 building record
- Documents filed29 files
Current status
Figures as on 21 Sep 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 0 | 40 | 105 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building1
As on 21 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
A: 92% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 95% |
| Sanitary fittings within the flats | 50% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 90% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 90% |
Progress on shared amenities19
As on 21 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 95% |
| Water supply | Yes | 90% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 90% |
| Storm water drains | Yes | 90% |
| Landscaping and tree planting | Yes | 50% |
| Street lighting | Yes | 100% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 100% |
| Water conservation, rain water harvesting | Yes | 90% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | Yes | 100% |
| Drinking water facilities | Yes | 90% |
| Emergency evacuation | Yes | 100% |
| Use of renewable energy | Yes | 50% |
| Security | Yes | 100% |
| Letter box | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 17.50 cr | Rs 16.62 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mansi Sagar Shah |
| Engineer | VIREN DILIPBHAI PAREKH |
Documents filed29
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA14339/A1C/061026/150429 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer's certificate (Form 2) | 21 Sep 2026 |
| Engineer's certificate annexure | 21 Sep 2026 |
| Accountant's certificate (Form 3) | 21 Sep 2026 |
| Architect's certificate (Form 1) | 18 Sep 2026 |
| Site photograph, A | 17 Sep 2026 |
| RERA registration certificate | 28 Oct 2024 |
| Proforma agreement for sale | - |
| Auditor's report (3 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ahmedabad
Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.
Keep AASTHA AVENUE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chandkheda5,400+ in Ahmedabad
Filed coordinates, straight-line distance. 206 registered projects within 2 km.
EWS 66
AHMEDABAD MUNICIPAL CORPORATION
LIG 21
AHMEDABAD MUNICIPAL CORPORATION
UPVAN
SAMBHAVNATH DEVELOPERS
3RD EYE LOTUS
CALICA ECO SPACES PRIVATE LIMITED
ADHIRATH BY SAMPAD
ADHIRATH INFRACON LLP
Dwarkesh Fragrance
DHARMJIVAN INFRASTRUCTURE
See every Ahmedabad project, with the district possession charts
Builder: AASTHA LAND
AASTHA LAND has 1 registration on GujRERA, including AASTHA AVENUE. Read the full track record. See more projects on the Ahmedabad district page.
Frequently asked questions
What are my rights if AASTHA AVENUE is delayed beyond 15 Aug 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of AASTHA AVENUE?
The registered promoter entity is AASTHA LAND, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in AASTHA AVENUE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at AASTHA AVENUE?
The professionals named in the filing: Architect: Mansi Sagar Shah; Engineer: VIREN DILIPBHAI PAREKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AASTHA AVENUE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.