Home / Browse projects / Ahmedabad, Gujarat / Dwarkesh Fragrance

Valid until 30 Jun 2025 Mixed Development project

Dwarkesh Fragrance

By DHARMJIVAN INFRASTRUCTURE

RG-GJ-63760 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA00625/A1M/EX2/141024/300625 · Last updated on GujRERA portal: 24 Jun 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Jun 2025Possession promisedmoved 24 months from the original
25 of 27Construction stages doneacross 3 buildings; furthest along: Sanitary fittings within the flats, 69%
51 of 334Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

Dwarkesh Fragrance is a Mixed Development project by DHARMJIVAN INFRASTRUCTURE in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA00625/A1M/EX2/141024/300625 on 7 Nov 2017. Possession is promised by 30 Jun 2025. The completion date has moved by 24 months from the original filing. 283 of the 334 units on this registration are recorded sold or booked, and 25 of 27 construction stages are filed complete.

At a glance

Project

  • NameDwarkesh Fragrance
  • TypeMixed Development
  • Location
    • Nr. "SWA" Opp. Mac Donals House
    • Chandkheda
    • Ahmedabad
    • Ahmedabad City
    • Ahmedabad
    • 382424
  • Pincode382424
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA00625/A1M/EX2/141024/300625
  • ReraGenie IDRG-GJ-63760

Builder

  • NameDHARMJIVAN INFRASTRUCTURE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredNov 2017First promiseJun 2023Revised toJun 2025

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2025
  • Registered on7 Nov 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Jun 2023)
  • Buildings3 building records
  • Documents filed37 files

Current status

85%283 of 334 units booked
91.7%Of the estimated cost spent so far

Figures as on 24 Jun 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B+C---1440144
D---48048
E+F---8854142

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 24 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

25 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary fittings within the flats, at 69%.

A+B+C91%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats69%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E+F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 24 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes85%
Water supplyYes95%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsYes100%
Landscaping and tree plantingYes95%
Street lightingYes95%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes25%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes100%
Plinth protectionYes100%
Water tankYes100%
Other requirementsYes90%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,236 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 60.00 cr
Cost incurredRs 55.00 cr
Spent of the estimate91.67%
BuildingWingEstimatedIncurred
A+B+CNARs 20.00 crRs 20.00 cr
DNARs 20.00 crRs 15.00 cr
E+FNARs 20.00 crRs 20.00 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA00625/A1M/EX1/091123Applied Jun 2023; approved Nov 2023
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA00625/A1M/EX2/141024/300625Applied Jun 2024; approved Oct 2024

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA00625/A1M/EX2/141024/300625 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)24 Jun 2024
Engineer's certificate annexure24 Jun 2024
RERA registration certificate7 Nov 2017
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Approved building or plotting plan-
NOCs from authorities-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

85%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 24 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Dwarkesh Fragrance on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmDwarkesh FragranceOther 127Dot size: filed unitsN

Filed coordinates, straight-line distance. 127 registered projects within 2 km.

Builder: DHARMJIVAN INFRASTRUCTURE

DHARMJIVAN INFRASTRUCTURE has 1 registration on GujRERA, including Dwarkesh Fragrance. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Dwarkesh Fragrance is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Dwarkesh Fragrance?

The registered promoter entity is DHARMJIVAN INFRASTRUCTURE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Dwarkesh Fragrance?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Dwarkesh Fragrance?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dwarkesh Fragrance. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dwarkesh Fragrance to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.