Home / Browse projects / Vadodara, Gujarat / Aashray Vatika
Aashray Vatika
RG-GJ-15539 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA02971/EX1/160319 · Last updated on GujRERA portal: 30 Sep 2020
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
Aashray Vatika is a Residential/Group Housing project by Shiv Infrastructure in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA02971/EX1/160319 on 22 Jun 2018. Possession is promised by 31 Mar 2020. The completion date has moved by 12 months from the original filing. 280 of the 308 units on this registration are recorded sold or booked, and 30 of 30 construction stages are filed complete.
At a glance
Project
- NameAashray Vatika
- TypeResidential/Group Housing
- Location
- Hanumanpura Road
- Opp Madhavnagar
- Ajwa Road
- Bakrol
- Vadodara
- 390019
- Pincode390019
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA02971/EX1/160319
- ReraGenie IDRG-GJ-15539
Builder
- NameShiv Infrastructure
- Entity typePARTNERSHIP FIRM
- Other registrations3 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Mar 2020
- Registered on22 Jun 2018
- Promised completion31 Mar 2020
- Revised completionRevised to 31 Mar 2020 (originally 31 Mar 2019)
- Buildings4 building records
- Documents filed41 files
Current status
Figures as on 30 Sep 2020, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TYPE A | - | - | - | 136 | 0 | 136 |
| TYPE B | - | - | - | 20 | 0 | 20 |
| TYPE C | - | - | - | 135 | 0 | 135 |
| TYPE D | - | - | - | 17 | 0 | 17 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building4
As on 30 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 30 construction stages are filed complete across 4 buildings.
TYPE A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TYPE B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TYPE C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TYPE D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 30 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | No | Not applicable |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TYPE A | NA | Rs 5.05 cr | Rs 4.56 cr |
| TYPE B | NA | Rs 5.05 cr | Rs 4.56 cr |
| TYPE C | NA | Rs 5.05 cr | Rs 4.56 cr |
| TYPE D | NA | Rs 5.05 cr | Rs 4.56 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ruchir Sheth |
| Engineer | Dr.Vinubhai R Patel |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed41
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA02971/EX1/160319 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 30 Sep 2020 |
| Engineer's certificate (Form 2) | 30 Sep 2020 |
| Engineer's certificate annexure | 30 Sep 2020 |
| Accountant's certificate (Form 3) | 30 Sep 2020 |
| Site photograph, TYPE A | 30 Sep 2020 |
| Site photograph, TYPE B | 30 Sep 2020 |
| Site photograph, TYPE C | 30 Sep 2020 |
| Site photograph, TYPE D | 30 Sep 2020 |
| RERA registration certificate | 22 Jun 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep Aashray Vatika on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bakrol2,900+ in Vadodara
Filed coordinates, straight-line distance. 45 registered projects within 2 km.
SHYAMALCOUNTY
SHREE GANESH INFRA
AKSHAR AASHRAY
SHREE AKSHAR ENTERPRISE
ROYAL LIFES
MAKHIJA INFRASTRUCTURE PRIVATE LIMITED
SHREE SIDDHESHWAR HILLCREST
N K CAMPUS
SHREE SIDDHESHWAR HIGHNESS
NYALKARAN PROCON
BLUE'S SPRINGFIELD
BLUE RIVER PROJECTS
See every Vadodara project, with the district possession charts
Builder: Shiv Infrastructure
Shiv Infrastructure has 4 registrations on GujRERA, including Aashray Vatika and KABIR PARADISE. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if Aashray Vatika is delayed beyond 31 Mar 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Aashray Vatika?
The registered promoter entity is Shiv Infrastructure, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Aashray Vatika?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Aashray Vatika?
The professionals named in the filing: Architect: Ruchir Sheth; Engineer: Dr.Vinubhai R Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Aashray Vatika?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback