Valid until 31 Mar 2026 Residential/Group Housing project

Aarambh Zest

By SAANVI NIRMAN LLP

RG-GJ-01659 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10367/EX1/280525/310326 · Last updated on GujRERA portal: 13 Jun 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Mar 2026Possession promisedmoved 12 months from the original
8 of 9Construction stages donefurthest along: Stilt Floor, 0%
30 of 260Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

Aarambh Zest is a Residential/Group Housing project by SAANVI NIRMAN LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10367/EX1/280525/310326 on 28 Jun 2022. Possession is promised by 31 Mar 2026. The completion date has moved by 12 months from the original filing. 230 of the 260 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameAarambh Zest
  • TypeResidential/Group Housing
  • Location
    • F.P. No. 154/2
    • Survey No. 321
    • 322/1
    • T.P.S. No. 45 (Chandlodia-Gota)
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10367/EX1/280525/310326
  • ReraGenie IDRG-GJ-01659

Builder

  • NameSAANVI NIRMAN LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations5 more →

Key dates

this monthRegisteredJun 2022First promiseMar 2025Revised toMar 2026

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2026
  • Registered on28 Jun 2022
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Mar 2025)
  • Buildings1 building record
  • Documents filed39 files

Current status

88%230 of 260 units booked
116.0%Of the estimated cost spent so far

Figures as on 13 Jun 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---2600260

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 13 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

A: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 13 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,256 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 25.89 cr
Cost incurredRs 30.03 cr
Spent of the estimate116.02%
BuildingWingEstimatedIncurred
ANARs 25.89 crRs 30.03 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Cunal Parmar (Director-FLXBL Design Consultancy Pvt. Ltd.)
EngineerMr. Haaris M Mal (Sarjan Consultants)

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10367/EX1/280525/310326Applied Apr 2025; approved May 2025

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10367/EX1/280525/310326 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)13 Jun 2025
Accountant's certificate (Form 3)13 Jun 2025
Site photograph, A12 Jun 2025
Engineer's certificate (Form 2)9 Apr 2025
Engineer's certificate annexure9 Apr 2025
RERA registration certificate28 Jun 2022
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

88%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Aarambh Zest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmAarambh ZestOther 222Dot size: filed unitsN

Filed coordinates, straight-line distance. 222 registered projects within 2 km.

Builder: SAANVI NIRMAN LLP

SAANVI NIRMAN LLP has 6 registrations on GujRERA, including Skydeck Serene and Aarambh Vistara. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Aarambh Zest is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Aarambh Zest?

The registered promoter entity is SAANVI NIRMAN LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Aarambh Zest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Aarambh Zest?

The professionals named in the filing: Architect: Mr. Cunal Parmar (Director-FLXBL Design Consultancy Pvt. Ltd.); Engineer: Mr. Haaris M Mal (Sarjan Consultants). Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aarambh Zest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aarambh Zest. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aarambh Zest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.