Home / Browse projects / Bharuch, Gujarat / AAGAM RESIDENCY

Valid until 31 Dec 2024 Residential/Group Housing project

AAGAM RESIDENCY

By ANANT LABDHI ENTERPRISE

RG-GJ-18114 · RERA PR/GJ/BHARUCH/BHARUCH/Others/RAA06171/EX1/091224/311224 · Last updated on GujRERA portal: 25 Dec 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 3 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2024Possession promisedmoved 3 months from the original
584 of 657Construction stages doneacross 73 buildings; furthest along: Stilt Floor, 0%
8 of 73Units unsoldnot recorded sold or booked
Jump to the 115 documents Report an error

AAGAM RESIDENCY is a Residential/Group Housing project by ANANT LABDHI ENTERPRISE in Bharuch, Gujarat, registered with GujRERA as PR/GJ/BHARUCH/BHARUCH/Others/RAA06171/EX1/091224/311224 on 15 Oct 2019. Possession is promised by 31 Dec 2024. The completion date has moved by 3 months from the original filing. 65 of the 73 units on this registration are recorded sold or booked, and 584 of 657 construction stages are filed complete.

At a glance

Project

  • NameAAGAM RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • AAGAM RESIDENCY
    • OLD BLOCK NO. 121+122 PAIKI NEW R.S. NO. 553
    • 555
    • VILLAGE CHAVAJ
    • BHARUCH
    • Chavaj
    • Bharuch
    • 392001
  • Pincode392001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BHARUCH/BHARUCH/Others/RAA06171/EX1/091224/311224
  • ReraGenie IDRG-GJ-18114

Builder

  • NameANANT LABDHI ENTERPRISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2019First promiseSep 2024Revised toDec 2024

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2024
  • Registered on15 Oct 2019
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Sep 2024)
  • Buildings73 building records
  • Documents filed115 files

Current status

89%65 of 73 units booked
100.0%Of the estimated cost spent so far

Figures as on 25 Dec 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
67---101
68---101
69---101
70---101
71---101
72---101
73---101
1---101
2---101
3---101
4---101
5---101
6---101
7---101
8---101
9---101
10---101
11---101
12---101
13---101
14---101
15---101
16---101
17---101
18---101
19---101
20---101
21---101
22---101
23---101
24---101
25---101
26---101
27---101
28---101
29---101
30---101
31---101
32---101
33---101
34---101
35---101
36---101
37---101
38---101
39---101
40---101
41---101
42---101
43---101
44---101
45---101
46---101
47---101
48---101
49---101
50---101
51---101
52---101
53---101
54---101
55---101
56---101
57---101
58---101
59---101
60---101
61---101
62---101
63---101
64---101
65---101
66---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 25 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 73 buildings; the table lists the first 20.

584 of 657 construction stages are filed complete across 73 buildings. The stage furthest along is Stilt Floor, at 0%.

6789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
6889%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
6989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
7089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
7189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
7289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
7389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
489%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
589%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
889%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
1089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
1189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
1289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
1389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 25 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,729 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 6.04 cr
Cost incurredRs 6.04 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
1NARs 8.28 lakhRs 8.28 lakh
10NARs 8.28 lakhRs 8.28 lakh
11NARs 8.28 lakhRs 8.28 lakh
12NARs 8.28 lakhRs 8.28 lakh
13NARs 8.28 lakhRs 8.28 lakh
14NARs 8.28 lakhRs 8.28 lakh
15NARs 8.28 lakhRs 8.28 lakh
16NARs 8.28 lakhRs 8.28 lakh
17NARs 8.28 lakhRs 8.28 lakh
18NARs 8.28 lakhRs 8.28 lakh
19NARs 8.28 lakhRs 8.28 lakh
2NARs 8.28 lakhRs 8.28 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPARIMAL JHUVAR
EngineerANIL MISTRY

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/BHARUCH/BHARUCH/Others/RAA06171/EX1/091224/311224Applied Sep 2024; approved Dec 2024

Documents filed115

As listed on the registration, under the names the promoter filed them with; the newest 80 of 115 are shown. The files themselves are available at source: search the registration number PR/GJ/BHARUCH/BHARUCH/Others/RAA06171/EX1/091224/311224 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)25 Dec 2024
Engineer's certificate (Form 2)14 Dec 2024
Engineer's certificate annexure14 Dec 2024
Architect's certificate (Form 1)13 Dec 2024
Site photograph, 6713 Dec 2024
Site photograph, 6813 Dec 2024
Site photograph, 6913 Dec 2024
Site photograph, 7013 Dec 2024
Site photograph, 7113 Dec 2024
Site photograph, 7213 Dec 2024
Site photograph, 7313 Dec 2024
Site photograph, 113 Dec 2024
Site photograph, 213 Dec 2024
Site photograph, 313 Dec 2024
Site photograph, 413 Dec 2024
Site photograph, 513 Dec 2024
Site photograph, 613 Dec 2024
Site photograph, 713 Dec 2024
Site photograph, 813 Dec 2024
Site photograph, 913 Dec 2024
Site photograph, 1013 Dec 2024
Site photograph, 1113 Dec 2024
Site photograph, 1213 Dec 2024
Site photograph, 1313 Dec 2024
Site photograph, 1413 Dec 2024
Site photograph, 1413 Dec 2024
Site photograph, 1513 Dec 2024
Site photograph, 1613 Dec 2024
Site photograph, 1713 Dec 2024
Site photograph, 1813 Dec 2024
Site photograph, 1913 Dec 2024
Site photograph, 2013 Dec 2024
Site photograph, 2113 Dec 2024
Site photograph, 2213 Dec 2024
Site photograph, 2313 Dec 2024
Site photograph, 2413 Dec 2024
Site photograph, 2513 Dec 2024
Site photograph, 2613 Dec 2024
Site photograph, 2713 Dec 2024
Site photograph, 2813 Dec 2024
Site photograph, 2913 Dec 2024
Site photograph, 3013 Dec 2024
Site photograph, 3113 Dec 2024
Site photograph, 3213 Dec 2024
Site photograph, 3313 Dec 2024
Site photograph, 3413 Dec 2024
Site photograph, 3513 Dec 2024
Site photograph, 3613 Dec 2024
Site photograph, 3713 Dec 2024
Site photograph, 3813 Dec 2024
Site photograph, 3913 Dec 2024
Site photograph, 4013 Dec 2024
Site photograph, 4113 Dec 2024
Site photograph, 4213 Dec 2024
Site photograph, 4313 Dec 2024
Site photograph, 4413 Dec 2024
Site photograph, 4513 Dec 2024
Site photograph, 4613 Dec 2024
Site photograph, 4713 Dec 2024
Site photograph, 4813 Dec 2024
Site photograph, 4913 Dec 2024
Site photograph, 5013 Dec 2024
Site photograph, 5113 Dec 2024
Site photograph, 5213 Dec 2024
Site photograph, 5313 Dec 2024
Site photograph, 5413 Dec 2024
Site photograph, 5513 Dec 2024
Site photograph, 5613 Dec 2024
Site photograph, 5713 Dec 2024
Site photograph, 5813 Dec 2024
Site photograph, 5913 Dec 2024
Site photograph, 6013 Dec 2024
Site photograph, 6113 Dec 2024
Site photograph, 6213 Dec 2024
Site photograph, 6313 Dec 2024
Site photograph, 6413 Dec 2024
Site photograph, 6513 Dec 2024
Site photograph, 6513 Dec 2024
Site photograph, 6613 Dec 2024
RERA registration certificate15 Oct 2019

How this compares with Bharuch

89%of this project is bookeddistrict median 52%
20%of Bharuch projects moved their completion datethis one moved by 3 months

Computed across the 200+ Bharuch projects on ReraGenie, from their own filings.

Keep AAGAM RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Chavaj200+ in Bharuch

2 kmAAGAM RESIDENCYOther 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 28 registered projects within 2 km.

Builder: ANANT LABDHI ENTERPRISE

ANANT LABDHI ENTERPRISE has 1 registration on GujRERA, including AAGAM RESIDENCY. Read the full track record. See more projects on the Bharuch district page.

Frequently asked questions

What are my rights if AAGAM RESIDENCY is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AAGAM RESIDENCY?

The registered promoter entity is ANANT LABDHI ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AAGAM RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AAGAM RESIDENCY?

The professionals named in the filing: Architect: PARIMAL JHUVAR; Engineer: ANIL MISTRY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAGAM RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAGAM RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAGAM RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.