ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / 33LE

Valid until 30 Jun 2020 Residential/Group Housing project

33LE

By KABEL BUILDCON SOLUTIONS PRIVATE LIMITED

RG-GJ-18116 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA00093/EX2/030120 · Last updated on GujRERA portal: 30 Dec 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Jun 2020Possession promisedmoved 18 months from the original
21 of 21Construction stages doneacross 3 buildings; every applicable stage filed complete
22 of 33Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

33LE is a Residential/Group Housing project by KABEL BUILDCON SOLUTIONS PRIVATE LIMITED in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA00093/EX2/030120 on 7 Sep 2017. Possession is promised by 30 Jun 2020. The completion date has moved by 18 months from the original filing. 11 of the 33 units on this registration are recorded sold or booked, and 21 of 21 construction stages are filed complete.

At a glance

Project

  • Name33LE
  • TypeResidential/Group Housing
  • Location
    • BLOCK NO 1778
    • MOJE BHAYLI
    • NEAR NAVRACHNA UNIVERSITY
    • Bhayali
    • Vadodara
    • 390007
  • Pincode390007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA00093/EX2/030120
  • ReraGenie IDRG-GJ-18116

Builder

  • NameKABEL BUILDCON SOLUTIONS PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations2 more →

Key dates

this monthRegisteredSep 2017First promiseDec 2018Revised toJun 2020

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2020
  • Registered on7 Sep 2017
  • Promised completion30 Jun 2020
  • Revised completionRevised to 30 Jun 2020 (originally 17 Dec 2018)
  • Buildings3 building records
  • Documents filed40 files

Current status

33%11 of 33 units booked
100.0%Of the estimated cost spent so far

Figures as on 30 Dec 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---11011
C---11011
A---11011

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 30 Dec 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 21 construction stages are filed complete across 3 buildings.

B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Dec 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,463 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 35.60 cr
Cost incurredRs 35.60 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 11.87 crRs 11.87 cr
BNARs 11.87 crRs 11.87 cr
CNARs 11.87 crRs 11.87 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHAURYA PATEL
EngineerAASHUTOSH DESAI

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA00093/EX1/071218Applied Sep 2018; approved Dec 2018
PR/GJ/VADODARA/VADODARA/Others/RAA00093/EX2/030120Applied Nov 2019; approved Jan 2020

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA00093/EX2/030120 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)30 Dec 2020
Architect's certificate (Form 1)29 Dec 2020
Engineer's certificate (Form 2)29 Dec 2020
Engineer's certificate annexure29 Dec 2020
Site photograph, B29 Dec 2020
Site photograph, C29 Dec 2020
Site photograph, A29 Dec 2020
RERA registration certificate7 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

33%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 18 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep 33LE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhayali2,900+ in Vadodara

2 km33LEOther 240Dot size: filed unitsN

Filed coordinates, straight-line distance. 240 registered projects within 2 km.

Builder: KABEL BUILDCON SOLUTIONS PRIVATE LIMITED

KABEL BUILDCON SOLUTIONS PRIVATE LIMITED has 3 registrations on GujRERA, including 33LE and Uma Residences. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if 33LE is delayed beyond 30 Jun 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of 33LE?

The registered promoter entity is KABEL BUILDCON SOLUTIONS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in 33LE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at 33LE?

The professionals named in the filing: Architect: SHAURYA PATEL; Engineer: AASHUTOSH DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 33LE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 33LE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 33LE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.